1.

01/2010

Punjab State Power Corporation Limited

Supply Code – Compliance thereof

01.11.2010

2.

02/2010

PSEB

Petition  under Section 43 of the Electricity Act, 2003 for authorizing the Board to waive off Cost of A&A Form, Meter & Meter Cup Board Security & Service Connection charges to be recovered from BPL Families to whom single point connections are to be released under Centrally Sponsored RGGVY Scheme, however only ACD  charges @ Rs.500/- shall be charged from the consumers to be covered under this scheme. They shall have the option of paying this amount upfront or in the first bill.

16.06.2010

3.

3/2010

Punjab State Electricity Board

Petition under Section 23 of the Electricity Act, 2003 for authorizing the Board to impose power cuts, Peak Load Hours Restrictions and taking other Power Regulatory Measures for the year 2010-11.

30.4.2010

4.

4/2010

Punjab State Electricity Board (now Punjab State Power Corporation Limited)

Petition for seeking amendments in the Open Access Regulations 2009 regarding applicability of UI tariff in case of open access customers and other related issues thereto AND PSERC Notification No.PSERC/Secy.Reg.44 dated 1.12.2009 (Second Amendment) for amendment in PSERC Open Access Regulations dated 9.8.2005 and mater related thereto

01.11.2010

5.

05/2010

M/S R.N.Gupta and Co. Ltd.

Review Petition under Section 94 (1) (f) read with Section 86 (a) & (k) read with Section 45 and Section 142 of the Electricity Act, 2003 for recalling the order dated 4.1.2010 passed by the Commission in Petition No.20 of 2009.

15.06.2010

6.

6/2010

Punjab State Transmission Corporation Limited         

Petition for approval of  amendments in  Section 17 and Appendix F6 relating to Metering Code of Punjab State Grid Code.

14.07.2010

7.

7/2010

Punjab State Electricity Board (now Punjab State Power Corporation Limited.).

Petition for approval of Fuel Cost Adjustment (FCA) Surcharge for 3rd Quarter (Oct. 09 to Dec. 09) of FY 2009-10.

09.05.2011

8.

8/2010

Punjab State Electricity Board (now Powercom)

Petition under  Section 63 of the Electricity Act, 2003 for Adoption of Tariff for Rajpura Thermal Power Project at Village Nalash near Rajpura, Distt. Patiala (Punjab).

14.07.2010

9.

9/2010

Punjab State Electricity Board (now Punjab State Power Corporation Limited)

Petition under Section 43 of the Electricity Act, 2003 for giving ex-post facto approval to the Board for issuing commercial circular No.44/2009 dated 27.11.2009 wherein it has been stipulated to allow the Cotton Ginning Industry customers a second connection of 15-20 KW or as per their requirement in their premises for office use during off season period only under NRS category for which entire cost including cost of transformer and metering equipment shall be borne by them

01.11.2010

10

9/2010
(Suo motu)

Punjab State Electricity Board (now Punjab State :Power Corporation Limited)

Notice under Section 142 of the Electricity Act 2003 for issuing commercial circular No.44/2009 dated 27.11.2009 without the approval of the Commission.

20.04.2011

11.

10/2010

Punjab State Electricity Board (now Punjab State Power Corporation Limited)

Petition for approval for Tariff in respect of Electricity Connection to Sh. Kuldip Singh Brar, resident of V&PO Sandhwan, District Faridkot.

03.11.2010

12.

11/2010

M/S Bansal Alloys & Metals Pvt. Ltd

Petition In The Matter of Bansal Alloys & Metals (P) Ltd. (Unit-II) to recover of SCC @ 5% of Prevalent rate of SCC for Transformer Capacity Over and above 120% of the sanctioned CD under section 46 of the Electricity Act, 2003 – Power to recover expenditure, read with Regulation 9 of the Electricity Supply Code & other related matters.

26.5.2010

13.

12/2010

Punjab Government

Petition for refund of Arrears of Power increase – Tariff Order 2009-10

16.4.2010

14.

13/2010

Shri Gurnek Singh Brar

Petition for imminent financial collapse of PSEB resulting from non-payment of subsidy in full by Govt. of Punjab and related matters AND incorporating safeguards in Tariff Order 2010-11 against re-occurrence of payment defaults in respect of subsidy.

6.5.2010

15.

14/2010

Punjab State Power Corporation Limited

Petition under Section 86 of the Electricity Act, 2003 for including Kinnow grading and waxing centres as ‘Seasonal Industry’ in clause 18.2 of the General Conditions of Tariff circulated vide CC No.36/2006 dated 14.7.2006

06.01.2011

16.

15/2010

Punjab State Power Corporation Limited

Petition regarding approval for allowing the PSPCL to restart checking of loads of DS & NRS Consumers.

09.05.2011

17.

16/2010

M/s A.K Multimetals Private Limited

Petition against clause No.13.4 of the General Conditions of Tariff approved by Punjab State Electricity Regulatory Commission applicable w.e.f. 01.04.2006 and adopted by PSEB vide circular No.36/06 dated 14.07.2006

17.08.2010

18.

17/2010

Punjab State Power Corporation Limited

Petition under Section 45 of the Electricity Act, 2003 for levy of electricity charges @ Rs.50/- BHP per month and its collection on biannual basis from AP consumers as per the Punjab Cabinet decision taken in its meeting held on 22.1.2010

06.01.2011

19.

18/2010

Gidderbaha Power Limited

Petition under Para 5.16 of the Guidelines issued by the Ministry of Power, Government of India, vide notification No.23/11/2004-R&R (Vol. II) dated 19.01.2005 (including amendments dated 30.03.2006, 18.08.2006, 27.09.2007, 27.03.2009 and 12.03.2010) (hereinafter “the Guidelines”) under Section 63 of the Electricity Act, 2003

10.09.2010

20.

19/2010

Northern Railways

Petition regarding Issue No.6 and 7 of Objection No.17 received from Northern Railways in Petition No.25 of 2009 in respect of ARR 2010-11

06.01.2011

21.

20/2010

Punjab State Power Corporation Limited

Petition for approval of Fuel Cost Adjustment (FCA) Surcharge for 4th Quarter (Jan.10 to March 10) FY 2009-10.

09.05.2011

22.

21/2010

Punjab Alkalies & Chemicals Limited

Petition for review of Tariff Order dated 8.9.2009 passed by the Commission for the year 2009-10 against discontinuation of HT rebate w.e.f. 01.04.2010

12.10.2010

23.

22/2010

Punjab State Transmission Corporation Limited

Non compliance of PSERC Open Access Regulations, 2007

17.08.2010

24.

23/2010

Punjab State Power Corporation Limited

Review Petition on Tariff Order dated 23.4.2010 passed by the Commission on Annual Revenue Requirement and Tariff for the FY 2010-11 under the provisions of Regulation 64 of PSERC (Conduct of Business) Regulations, 2005.

06.01.2011

25.

24/2010

M/s Tata Power Trading Company Limited

Petition under Section 86(1)(f) of the Electricity Act, 2003 read with Regulation 20 of the Punjab State Electricity Regulatory Commission (Conduct of Business) Regulations, 2005 for adjudication of disputes between the petitioner and the respondent arising under the Agreement dated 15th June, 2009.

4.10.2011

26.

25/2010

Shri Gurnek Singh Brar (Retd. SE PSEB)

Petition for non compliance of Tariff Order dated 23.4.2010 passed by the Commission for FY 2010-11 and non-compliance of IEGC under provisions of Sec. 142 and 86(b) of Electricity Act, 2003.

19.01.2011

27.

26/2010

Suo Motu Petition

Determination of generic levellised generation Tariff for Solar Power Projects

07.07.2010

27(a).

26/2010 (Suo-Motu)

Suo Motu

Petition regarding Determination of Generic Levellised Generation Tariff for Solar Power Projects

8.7.2011

28.

27/2010

Dee Development Engineers Pvt. Ltd., Registered Office #1255, Sector 14, Faridabad

Petition under Section 86 of the Electricity Act, 2003, for redetermination/revision of tariff for bio-mass based Power Plant with an aggregate capacity of 8 MW, taking into account the escalation in input cost as specified by the Commission in Order dated 13.12.2007.

16.12.2010

29.

28/2010

(Erstwhile PSEB) (now Punjab State Power Corporation Limited)

Petition to regularize the procurement of power under short term power purchase and removal of the price cap on short term power purchase & UI for the year 2010-11 under the Tariff Order for FY 2010-11 issued by the Commission on dated 23.4.2010.

19.01.2011

30.

29/2010

Green Planet Energy (P) Ltd.,

Petition under Section 86 of the Electricity Act, 2003 for revision of rates fixed by the Commission vide order dated 13.12.2007 whereby the tariff of Bio-mass has been fixed as Rs.3.49/- unit (with base year 2006-07) with five annual escalations @ 5% upto 2011-12.

13.01.2011

31.

30/2010

Punjab State Power Corporation Limited

Petition for approval of Fuel Cost Adjustment (FCA) surcharge for 1st Quarter (April, 2010 to June, 2010) of FY 2010-11.

09.05.2011

32.

31/2010

M/s Mukesh Steels Limited and another

Petition for re-determination of the cost of supply and surcharge as directed by the Hon’ble Appellate Tribunal for Electricity vide its order dated 16.7.2010 in Appeal No.192 of 2009.

19.01.2011

33.

32/2010

Suo Motu Petition

Determination of generic levellised generation Tariff for Renewable Energy Power Projects(Other than Solar)

30.09.2010

34.

33/2010

Induction Furnace Association of North India and another

Petition under Section 142 r/w Regulation 9 of the PSERC (Conduct of Business) Regulations, 2005, for implementing the directions given by the Commission vide Order dated 30.04.2010 passed by the Commission in Petition No.3 of 2010.

19.01.2011

35.

34/2010

Induction Furnace Association of North India (Regd,) and another

Petition under Section 23 and section 86(1)(c) of the Electricity Act, 2003 r/w Regulation 9 of the PSERC (Conduct of Business) Regulations, 2005, for giving time to the petitioners to install CT/PT metering in line with the metering guidelines and provide uninterrupted use of open access to the members of the petitioner association.

06.01.2011

36.

35/2010

M/s Siel Chemical Complex, a Unit of M/s Mawana Sugars Ltd

Petition under Section 142 R/W Regulation 9 of the PSERC (Conduct of Business) Regulations, 2005, for implementing the directions given by the Commission vide Order dated 30.04.2010 passed in Petition No.3 of 2010 and the directions enshrined in policy in peak load hours (PLH) restrictions and exemptions thereto.

19.01.2011

37.

36/2010

M/s Vardhman Spinning & General Mills

Petition under Section 142 r/w Regulation 9 of the PSERC (Conduct of Business) Regulations, 2005, for implementing the directions given by the Commission vide Order dated 30.04.2010 passed in Petition No.3 of 2010.

19.01.2011

38.

37/2010

M/s Vardhman Special Steels

Petition under Section 142 r/w Regulation 9 of the PSERC (Conduct of Business) Regulations, 2005, for implementing the directions given by the Commission vide Order dated 30.04.2010 passed in Petition No.3 of 2010.

19.01.2011

39.

38/2010

M/s Arihant Spinning Mills

Petition under Section 142 r/w Regulation 9 of the PSERC (Conduct of Business) Regulations, 2005, for implementing the directions given by the Commission vide Order dated 30.04.2010 passed in Petition No.3 of 2010.

19.01.2011

40.

39/2010

Dayanand Medical College and Hospital, Ludhiana

Petition for review of Tariff Order dated 8.9.2009 for the Financial Year 2009-2010 for clarification of Clause No.5.6.3 of that Tariff Order.

1.12.2010

41.

40/2010

Mandi Gobindgarh Induction Furnace Association and another

Petition under Regulation 31 of Open Access Regulations for restraining Respondent No.1 from forcing Consumers/ Members of Petitioner Associations in respect of entering and execution of new/un-approved ‘Short Term Open Access Agreement’, which is contrary to the provisions of PSERC Open Access Regulations-2005 and also contrary to Power Market Regulations framed by CERC; AND Suitable directions to both the Respondents to provide Single Window Documentation/Formalities for allowing Open Access rather than Multiple Forms/Documentations with both the bifurcated Constituents of the erstwhile PSEB.

19.01.2011

42.

41/2010

Suo motu Petition

Regarding violations of Regulations 5.6, 6.3(b) and 6.3(c) of PSERC (Electricity Supply Code and Related Matters) Regulations 2007 (Supply Code).

07.03.2012

43.

42/2010

Chadha Sugars & Industries Limited

Petition for adjudication under Clause 20 (Chapter III) PSERC (Conduct of Business) Regulations 2005 - Evacuation of surplus power from 23 M.W. T.G. (Cogen) plant for sale to PSPCL/Third Party

26.11.2010

44.

43/2010

Punjab State Power Corporation Limited

Petition for incorporation of para 5.5.1 to 5.5.3 of Tariff Order of 2009-10 regarding withdrawal of voltage rebate of 3% in the Tariff Order for the year 2010-11 passed on 23.4.2010 in light of the judgement passed by Hon’ble ATE, New Delhi dated 31.8.2010 passed in respect of Appeal No.14 of 2010 and 15 of 2010.

06.01.2011

45.

44/2010

Punjab State Power Corporation Limited

Petition for approval of Fuel Cost Adjustment (FCA) Surcharge for 2nd Quarter (July 10 to Sept. 10) of FY 2010-11.

09.05.2011

46.

45/2010

Punjab State Transmission Corporation Limited

Petition for ARR and Determination of Tariff for the Financial Year 2011-12 filed by Punjab State Transmission Corporation Limited

31.3.2011

47.

46/2010

Rana Sugar Limited

Petition under Section 86 of the Electricity Act, 2003 for re-determination/revision of rates for sale of power from petitioner’s Co-generation Power Plant with an aggregate capacity of 12 MW taking into account the escalation in operational cost in order to promote co-generation and generation of electricity from renewable sources of energy as envisaged under the Electricity Act and the NRSE Policy.

24.6.2013

48.

47/2010

Punjab State Power Corporation Limited

Petition under Section 45 of the Electricity Act, 2003 for withdraw of electricity charges @ Rs.50/- per BHP per month flat rate and @ 59 Ps/KWH from metered supply AP consumers w.e.f. 3.11.2010 as per Punjab Council of Ministers decision dated 3.11.2010.

27.6.2011

49.

48/2010

Siel Chemical Complex, (A Unit of M/s Mawana Sugars Ltd.), Vill. Khadoli, Rajpura, District Patiala, Punjab

Petition under Section 86 (1) (K) of the Electricity Act, 2003 r/w Reg. 49 and 50 of PSERC (Electricity Supply Code and Related Matters) Regulations, 2007 (as amended upto date) for removal of difficulty pertaining to security deposit based on average monthly consumption charges as per Reg.15.

29.12.2010

50.

50/2010

Gurdaspur Cooperative Sugar Mills Ltd

Petition under Section 142 read with Regulation 9 of the Punjab State Electricity Regulatory Commission (Conduct of Business) Regulations, 2005, Exemption of charges – on Peak Load and setting aside the order dated 16.4.2010 passed by the Chief Engineer/SO&C, PSEB, Patiala.

18.01.2011

51.

51/2010

M/s. Malwa Cotton Spinning Mills Ltd.

Petition under Regulation 48 read with Regulation 50 of the PSERC (Electricity Supply Code and Related Matters) Regulations, 2007 read with Section 86 (1))k)/S.47 of the Electricity Act 2003 regarding direction to respondent to grant interest on the amount of security/ACD AND suitable amendment providing for basis of average monthly consumption of an existing consumer over a period of 12 months.

18.01.2011

52.

VDS ORDER

Implementation of Govt. of Punjab directive issued under Section 108 of the Electricity Act 2003 for compliance of Policy notified by the State Govt. for voluntary disclosure of unauthorized extension in load by AP consumers.

09.11.2010