List of  Commission orders/ judgments passed in various cases.

 

 

 

 

S.No.

Petition No.

Filed by

Subject matter

Date of final decision.

 

1.

1/2009 (On remand by Appellate Tribunal for Electricity, New Delhi)

  Northern Railway

Determination of Tariff for the year 2009-10 in respect of Northern Railway.

02.11.2012

2.

3/2009

 Punjab State Electricity Board

OYT Scheme for release of tubewell connections on priority.

10.12.2009

3.

5/2009

 Nabha Power Limited

Petition for allowing the applicant, an authorized representative of the procurer, . PSEB to issue LOI (Letter of Intent) in favour of M/s Lanco Infratech Ltd. for development of 1320 MW Rajpura Thermal Project on Build, Own & Operate basis.

27.05.2009

4.

06/2009

 Punjab State Electricity Board

Petition for approval of Fuel Cost Adjustment (FCA) surcharge for 3rd Quarter(Oct. 08 to Dec. 08), FY 2008-09.

08.09.2009

5.

7/2009

 Punjab State Electricity Board

Petition under Section 23 of the Electricity Act, 2003 for authorizing the Board to impose Power cuts, Peak Load Hours Restrictions and taking other Power Regulatory Measures for the year 2009-10.

27.05.2009

6.

8/2009

  Punjab State Electricity Board

Petition for Continuation of Tariff as revised by the Commission vide its Order 3.07.2008 after 31.3.2009 till the time ARR/Tariff for 2009-10 is determined by the Commission.

30.03.2009

7.

9/2009

 Punjab State Electricity Board

Petition for approval of amendment in the existing clause No.22.2 & 22.4 of General Conditions of Tariff.

1.1.2010

8.

10/2009

 Punjab State Electricity Board

Petition for approval of Fuel Cost Adjustment (FCA) surcharge for 4th Quarter(Jan. 09 to March, 09), FY 2008-09.

08.09.2009

9.

11/2009

Universal Bio-mass Energy Pvt. Ltd

Petition under Section 86 of the Electricity Act, 2003 for revision of rates fixed by the Commission’s order dated 13.12.2007 whereby the tariff of Bio-mass based power project has been fixed as Rs.3.49/unit (with base year 2006-07) with five annual escalations @ 5% upto 2011-12

26.11.2010

10.

12/2009

Punjab State Electricity Board

Petition to review order dated 27.5.2009 passed by the Commission in petition No.7 of 2009 and clarification given vide letter dated 11.6.09 vis a vis compliance of the para 6 (vi) of the order dated 27.5.09 regarding grant of PLE to Industrial Consumers who had been availing the same in the past and to enhance the rate of Peak Load Exemption Charges.

30.4.2010

11.

13/2009

 M/S Golden Melodies (P) Limited

Petition under section 42(1),43 read with Section 86 of the Electricity Act,2003 for direction/Clarification in respect of Regulation 13.5.2 of Electricity Supply Regulations - Suplly of Electricity to the corporate agricultural consumers

04.02.2010

12.

14/2009

 Punjab State Electricity Board (now Punjab State Power Corporation Limited)

Petition for approval of Power Sale Agreement dated 26.02.2009 signed between PSEB and TATA Power Trading Co. Ltd., (TPTCL) for purchase of 300 MW Power from 1050 MW Maithon Right Bank Thermal Power Project, Dhanbad, District Jharkhand and related matters.

19.01.2011

12.a

I.A. in Petition no. 14/2009

  Punjab State Power Corporation Limited

Interlocutory Application in Petition No.14 of 2009 under Regulation 69, 71 and 72 of Punjab State Electricity Regulatory Commission (Conduct of Business Regulations) 2005 (“PSERC Conduct of Business Regulations”) filed under Section 86(1)(b) read with Section 2(39) and Section 14 of the Electricity Act (“Act”) , read with Regulations 46(6)(a) and 57(1) of PSERC Conduct of Business Regulations for the approval of Power Sale Agreement dated 26.02.2009 signed between erstwhile Punjab State Electricity Board (“PSEB”) now Punjab State Power Corporation Limited (“PSPCL”) and Tata Power Trading Company Limited (TPTCL”) for purchase of 300 MW power from 1050 MW Maithon Right Bank Thermal Power Project (“Maithon RBTPP”), District Dhanbad, Jharkand and related matters.

23.01.2013

13.

15/2009

 Punjab State Electricity Board (now Punjab State Power Corporation Limited)

Petition for approval of Draft Power Sale Agreement to be signed between PSEB and PTC India Ltd., New Delhi for purchase of 100 MW Power from Baglihar Hydro Electric Project and related matters.

19.01.2011

14.

16/2009

 M/s. Malwa Power Pvt. Ltd.,

Petition for re-determination / revision of tariff for bio-mass based Power Plant with an aggregate capacity of 6 MW taking into account the escalation in input cost as specified by the Commission in its order dated 13.12.2007.

18.01.2011

15.

17/2009

 Punjab State Electricity Board

Petition for approval of Fuel Cost Adjustment (FCA) surcharge for 1st Quarter (April, 2009 to June, 2009) of FY 2009-10.

25.11.2009

16.

18/2009

 Punjab State Electricity Board

Petition for deferment of implementation of Tariff Order for 2009-10 dated 8.9.2009

1.1.2010

17.

19/2009

 M/s GlaxoSmithKline Consumer Healthcare Ltd.

Petition as per Orders dated 9.9.2009 passed by Hon’ble Punjab & Haryana High Court, Chandigarh in R.A.No.324 of 2009 in CWP No.6250 of 2008

4.1.2010

18.

20/2009

 M/S R.N.Gupta and Co. Ltd

Petition as per Orders dated 9.9.2009 passed by Hon’ble Punjab & Haryana High Court, Chandigarh in R.A.No.319 of 2009 in CWP No.5928 of 2008

4.1.2010

19.

21/2009

M/s Supreme Tex Mart Ltd

 

Petition as per Orders dated 9.9.2009 passed by Hon’ble Punjab & Haryana High Court, Chandigarh in R.A.No.319 of 2009 in CWP No.1826 of 2009

 

10.09.2010

20.

22/2009

M/s JMP  Ltd.,

 

Petition as per Orders dated 9.9.2009 passed by Hon’ble Punjab & Haryana High Court, Chandigarh in R.A.No.323 of 2009 in CWP No.7643 of 2008.

 

10.09.2010

21.

23/2009

Punjab State Electricity Board

Review Petition  against Tariff Order dated 8.9.2009 passed by the Commission for the year 2009-10.

 

16.4.2010

22.

24/2009

Punjab State Electricity Board (now Powercom)

Petition for approval of Fuel Cost Adjustment (FCA) surcharge for 2nd Quarter of FY 2009-10

23.04.2010

23.

25/2009

Punjab State Electricity Board

ARR and Tariff Petition filed by PSEB for the year 2010-11

 

29.03.2010

24.

25/2009(On remand by Appellate Tribunal for Electricity, New Delhi)

Northern Railway

Determination of Tariff for the year 2010-11 in respect of Northern Railway.

 

02.11.2012

25.

26/2009

 Suo motu Petition


OYT Scheme for release of tubewell connections on priority.


24.02.2010

26.

27/2009

M/s Steel Furnace Association of India

 

Petition for Amendment of PSERC (Open Access) Regulations, 2005 dated 9.8.2005 and 1st Amendment dated 31st August 2007

 

17.08.2010

27.

28/2009

 M/S Universal Bio-mass Energy Pvt. Ltd

Petition under section 86 of the Electricity Act,2003 for issuance of a direction to the respondent not to charge 8% of the tariff and the same be ordered to be waived as the respondent is the nodal agency with a duty to assist the petitioner for which the respondent can charge only a lump sum fee and not on the basis of ad-valorem(14.5 MW)

04.02.2010

28.

29/2009

M/s Wahid Sandhar Sugars Ltd. and others

 

Petition under Section 39 (2) (c) & (d) r/w Regulation 9 of the PSERC (Conduct of Business) Regulations, 2005 to remove difficulties and to amend the Open Access Regulations under Regulation 33 and 34 of the PSERC (Open Access) Regulations, 2005.

 

17.08.2010