Notice is hereby given to
all that the Punjab State Power Corporation Limited has submitted that
continuous process industries are getting uninterrupted power supply for the
full load whereas actual load required to run continuous process is far less
than the total load. Even in the peak load season when the PSPCL is short of
supply, Continuous Process Consumers avail uninterrupted power supply for the
full load whereas peak load restrictions are imposed on other industrial
consumers. To sort out this problem, PSPCL has proposed the following changes
in the criteria for allowing continuous process status:
S.No. |
Existing
Provision |
Proposed
Provision |
1 |
Clause-131.4
(i) of ESIM In
case of general industry the manufacturing Process of the consumer should be
continuous in nature (The manufacturing process of the firm shall be
considered as continuous in nature, if the material under process get
permanently damaged/loose quality in case of power failure & consumer has
DG sets as fall back arrangement) The
competency to grant Continuous Process Industry Status to General Industry
shall be with the committee consisting of Director/Distribution (as Chairman
of the Committee), CE/PP&R and concerned CE/Distribution or his
representative as Members and SE/PR&C as Member Secretary. The request of
firm for grant of Continuous Process Status to a general industry shall be
considered if the Industry fulfills the above conditions. |
Clause-131.4
(i) of ESIM In
case of general Industry the manufacturing Process of the consumer should be
continuous in nature, but the load
portion for continuous process will be identified and certified by SE/DS
concerned before forwarding the application to the committee competent to
grant continuous process industry status. The manufacturing process of
the firm shall be considered as continuous in nature, if the material under
process get permanently damaged/lose quality in case of power failure & consumer must have a DG set equivalent to
the continuous process load as a fall back arrangement, alternatively
indemnify the PSPCL against any loss due to absence of DG set. |
2 |
Clause-131.4
(iii) of ESIM The
consumer shall be allowed Peak Load Exemption if he agrees to pay Peak Load
Exemption Charges over & above the normal tariff as applicable from time
to time |
Clause-131.4
(iii) of ESIM The
consumer shall be allowed Peak Load Exemption to the extent of load required to run the continuous process part of
load sanctioned if he agrees to pay Peak Load Exemption Charges over
& above the normal tariff as applicable from time to time. |
3 |
Clause-131.4
(vi) of ESIM Presently
not existing |
Clause-131.4
(vi) of ESIM During off days
declared on industry, continuous process industry will be allowed to run the
load to the extent Peak Load exemption is obtained from the PSPCL. |
2. The
objections/views against the proposal of the PSPCL may be filed with the
Secretary, PSERC at the address mentioned above in person or through registered
post so as to reach him upto 30.4.2012.
3. The
objections to the Commission should be filed in seven copies and carry full
name and postal address of the person sending the objection. If the objection
is filed on behalf of any organization or any class of consumers, it should be
so mentioned.
(P.S.
JINDAL)
SECRETARY