SCO NO. 220-221, SECTOR-34-A
PETITION NO. 1 OF 2009
IN THE MATTER OF:
ANNUAL
REVENUE REQUIREMENT
FILED
BY THE
FOR
THE FINANCIAL YEAR 2009-10
PRESENT : Mr.
Jai Singh Gill, Chairman
Ms. Baljit Bains, Member
Mr.
Satpal Singh Pall, Member
Date of Order:
ORDER
The Punjab State
Electricity Regulatory Commission (Commission), in exercise of powers vested in
it under the Electricity Act, 2003 (Act) passes this order determining the
Annual Revenue Requirement (ARR) and Tariff for supply of electricity by the
Punjab State Electricity Board (Board) to consumers of the State of Punjab for
the year 2009-10. The ARR filed by the
Board, facts presented by the Board in its various filings, objections received
by the Commission from consumer organizations and individuals, issues raised by
the public in hearings held at Ludhiana, Bathinda, Jalandhar and Chandigarh,
the responses of the Board to the objections and observations of the Govt.
(Government) in this respect have been considered. The State Advisory Committee
constituted by the Commission under Section 87 of the Act has also been
consulted and all other relevant facts and material on record have been perused
before passing this Order.
1.1
Background
The Commission has in its
previous six Tariff Orders determined tariff in pursuance of the Tariff
Applications and ARRs submitted by the Board for the years 2002-03 to 2006-07 and
2008-09. Tariff Order for the year 2007-08 has been passed by the Commission in
suo motu proceedings.
1.2
ARR
for the year 2009-10
The Board did not file the
ARR and Tariff Application for the year 2009-10 by 30th November,
2008 which is the due date as per PSERC (Terms and Conditions for Determination
of Tariff) Regulations, 2005 (PSERC Tariff Regulations) but filed a petition
(No.24 of 2008) on 2.12.2008 seeking extension of time upto 31.12.2008 in
filing the ARR and Tariff Application which was allowed by the Commission. The
Board filed the ARR for 2009-10 on 29.12.2008. Therein the Board had worked out
a cumulative revenue gap of Rs.6980 crore for the year 2009-10 including
carried over gaps of 2007-08 and 2008-09 but there was no proposal to cover up
the gap depicted in the ARR.
The Government had authorized the
Board under Section 172 of the Act to continue to function as a STU (State
Transmission Utility) and a licensee upto 30.11.2008 and not thereafter, the
Board was asked to clarify this aspect. A reference was also made to the
Government in this respect. The Board in its letter dated 25.2.2009 stated that
the Govt. has on 24.2.2009 authorized it to function as STU and a licensee upto
15.6.2009. Thereupon the Commission took the ARR on record on 27.2.2009. The
Board in its letter dated 19.3.2009 stated that due to inadvertence, cumulative revenue gap for 2007-08, 2008-09
and 2009-10 had been shown as Rs.6980 crore instead of Rs.8546 crore and the
letter was considered as a part of the
ARR. The petition filed by the Board did not contain any proposal to cover this
gap stating that the Commission may determine the gap and fix tariff
accordingly based on the details furnished by it in its ARR. On
scrutiny it was noticed that the ARR was deficient in some respects and in
letter dated 27.3.2009 the Commission sought further information, a part of
which was furnished by the Board in its letters dated 16.4.2009,23.4.2009 and 6.5.2009. The
Board had also filed Petition No.14 of
2008 for review of Tariff Order dated 3.7.2008 passed by the Commission for the
year 2008-09 which the Commission disposed of in its order dated 24.3.2009.
1.3 Invitation
of objections and p
A public notice was
published by the Board in the Tribune, Hindustan Times, Ajit, Jagbani and
Punjab Kesri on
The Commission received 13
written objections by 4.5.2009 and 15 additional written objections thereafter.
The Commission decided to take all these objections into consideration.
Number of objections
received from individual consumers, consumer groups, organizations and others
are detailed below:
Sr. No. |
Category |
No. of
Objections |
1. |
Chambers of Commerce |
1 |
2. |
Industrial Associations |
5 |
3 |
Industry |
7 |
4 |
Railways |
1 |
5 |
PSEB Engineers/Employees Associations |
2 |
6 |
Individuals |
8 |
7 |
Association of Affiliated Schools |
1 |
8 |
Forums |
3 |
|
Total |
28 |
The list of objectors is
given in Annexure-I to this Tariff Order. The Board submitted its comments t
The Commission decided to hold
public hearings at
Venue |
Date & time of public hearing |
Category
of consumers to be heard. |
|
Commission Office i.e. SCO No.220-221, Sector 34-A, |
|
Industry |
|
|
Agriculture consumers |
||
Commission Office i.e. SCO No.220-221, Sector 34-A, |
|
All consumers except Industry, Agricultural consumers and staff
associations/unions of the Board. |
|
|
Staff associations/unions of Board and other organizations. |
||
Circuit House, |
|
All consumers/organizations |
|
JALANDHAR Circuit House, Skylark Chowk,
Opp. Skylark Hotel, Jalandhar. |
|
All consumers/organizations |
|
BATHINDA Circuit House, Civil Lines, Near D.C.Residence, Bathinda. |
|
All consumers/organizations |
|
Through public notices
published in different newspapers, it was intimated that the Commission will
conduct a public hearing at
The public hearings were held as
per schedule, and objectors, general public and the Board were heard by the
Commission. A summary of the issues raised, the
responses of the Board and the views of the Commission are contained in
Annexure-II of this Tariff Order.
1.4 The Government was approached by the
Commission through a letter dated 8.4.2009 seeking its views on the ARR to
which the Government responded on 9.7.2009, which has been taken note of by the
Commission.
1.5
State Advisory Committee
The State Advisory Committee
set up under Section 87 of the Act, discussed the Board’s ARR in a meeting
convened for the purpose on 09.06.2009. The minutes of the meeting of the State
Advisory Committee are enclosed as Annexure–III to this Order.
The Commission has thus
taken the necessary steps to ensure that the due process, as contemplated under
the Act and Regulations framed by the Commission, is followed and adequate
opportunity given to all stakeholders in presenting their views.
1.6
Compliance
of Directives
In its previous Tariff
Orders, the Commission had issued certain directives to the Board in the public
interest. A summary of directives issued along with the comments of the
Commission is given in Annexure-IV of this Tariff Order.
True-up for the year 2007-08
Table 2.1: Energy Sales – 2007-08
(MU)
Sr. No. |
Category |
Projected
by PSEB during suo motu determination of ARR 07-08 |
Approved by the
Commission in T.O. 07-08 |
Revised Estimates of PSEB
during determination of ARR of 08-09 |
Approved by the
Commission in review |
Actuals as in the ARR of 09-10 |
Now approved by the Commission |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
1 |
Domestic |
5897 |
5926 |
6302 |
6273 |
6491 |
6491 |
2 |
Non-Residential |
1774 |
1748 |
1877 |
1876 |
1919 |
1919 |
3 |
Small Power |
712 |
655 |
736 |
732 |
738 |
738 |
4 |
Medium Supply |
1560 |
1649 |
1568 |
1564 |
1579 |
1579 |
5 |
Large Supply |
8522 |
8412 |
8877 |
8825 |
8733 |
8733 |
6 |
Public Lighting |
145 |
143 |
141 |
139 |
140 |
140 |
7 |
Bulk
Supply & Railway Traction |
603 |
630 |
585 |
583 |
614 |
614 |
8 |
Total Metered sales (within State) |
19213 |
19163 |
20085 |
19992 |
20214 |
20214 |
9 |
Agriculture pumpsets |
8939 |
8645 |
9537 |
8960 |
10030 |
8902 |
10 |
Total sales within the State
|
28152 |
27808 |
29622 |
28952 |
30244 |
29116 |
11 |
Common pool |
300 |
300 |
303 |
303 |
302 |
303 |
12 |
Outside State sales |
952 |
827 |
1615 |
1615 |
1576 |
1576 |
13 |
Total
(10+11+12) |
29404 |
28935 |
31540 |
30870 |
32122 |
30995 |
The Board has furnished the
actual total sales at 32122 MU for the year 2007-08 as per audited accounts
including the theft of energy of 208 MU. This theft of energy has not been
apportioned to different consumer categories in the audited accounts but the
Board in its ARR petition (Vol. 1) for the year 2009-10 has submitted
category-wise sales for 2007-08 including theft of energy which is as per
column 7 of Table 2.1.
2.2.2
Metered
Sales: In metered sales, the Board has included 208 MU of energy on account
of theft. The revenue on this account has been shown as Rs.27.98 crore in the
annual accounts which is not commensurate with the revenue accruing from sale of energy of 208 MU to
metered categories. Owing to this discrepancy in figures and in the absence of any
proper justification forthcoming from the Board, the Commission had been
following the approach of re-estimating energy on account of theft by matching
it with the revenue shown therefrom. Now, the Board in its letter of 06.05.2009
has submitted that as per accounting procedures, the amount assessed under
theft and the amount assessed under sale of power are required to be booked
under different account heads. It is noticed, however, that the theft amount is
sometimes credited as sale of power (SOP), whereas consumption is accounted for
as theft of energy which results in lower realization on this account being
reflected in
The Commission accepts common pool sales at 303 MU and outside state sales as 1576 MU on the basis of actuals as given in the audited accounts for 2007-08.
Metered sales now approved
by the Commission are as shown in column 8 of Table 2.1.
2.2.3
AP Consumption: The
Commission in its tariff order of 2007-08 approved AP consumption of 8645 MU
after allowing a normative growth of 5% over the revised approved consumption
of 8233 MU for the previous year (2006-07). While doing so, the Commission
observed that the methodology of computing AP consumption on the basis of
sample meter readings and connected load needs further refinement. The Board in
its ARR for 2008-09, reported a revised AP consumption of 10012 MU in 2007-08
against an average connected load of 5351380 KW. The increase was explained to
be on account of deficient rainfall in the kharif season, increased load owing
to regularization of connected load under Voluntary Disclosure Schemes (VDS)
launched during 2006-07 and 2007-08 and the increasing use of submersible
pumps. The Commission in its Tariff Order for the year 2008-09 observed that
the assessment of AP consumption is based on the calculation of AP consumption
factor which is worked out from sample meter readings and the connected load of
pumps on which these meters are installed. The Commission had noted that the
verified actual connected load of the pump sets on which sample meters have
been installed was not available and there were several inconsistencies in
reporting connected load on account of VDS and release of new connections. For the
reasons discussed in that Tariff Order, the Commission was not convinced of the
correctness of the revised AP consumption for 2007-08 reported as 10012 MU. In
the circumstances the Commission decided to revise the estimate of AP
consumption in 2007-08 by applying an increase in connected load of 8.81% to AP
consumption of 8235 MU determined for the year 2006-07. Accordingly, estimate
of AP consumption for the year 2007-08 was revised to 8960 MU. The Board has
now submitted the AP consumption for 2007-08 as 10030 MU as per audited
accounts.
During the course of
hearings of the ARR and Tariff Petition for the year 2008-09, the Board offered
that in case the present method of assessing AP consumption is not acceptable,
the Commission may appoint an independent agency for reassessing the same, the
full cost of which will be borne by the Board. The Commission thereupon decided
to undertake a study on the subject.
The Commission appointed
M/s ABPS Infrastructure Advisory Private Limited, Mumbai (Agency) for
validation of AP consumption reported by the Board for the year 2007-08 and
first three quarters of 2008-09. As per the terms of reference of the work
assigned to the Agency, it was to collect the details of connected load and the
recorded consumption of the sample meters for 2007-08 and the first three
quarters of 2008-09 in respect of five circles i.e. Sangrur, Khanna,
Hoshiarpur, Gurdaspur and Bathinda. One circle in each zone was selected with a
view to make the sample of the study as representative as possible of the
various regions of the State. The figures so obtained were then to be validated
after comparing it with the records maintained in the field.
The Agency following the
methodology adopted by the Board did not take into account the sample meters
falling under the following categories:
· Defective Meters
· Locked Meters
· Meters with initial readings and Meters with zero readings
·
Meters with abnormal readings/inconsistent
readings
The Agency collected the
details of connected load, supply hours and the consumption of sample meter
connections from the Board’s System Losses Study Cell (SLSC) in respect of all
the five circles. It also observed that consumption shown by some of the
sample meters was more than it possibly could have been with the supply hours
intimated by SLSC. This sample meter load was thereafter validated by
the Agency from the AP ledgers/VDS registers maintained at the Sub Divisional
offices of the Board. The Agency observed that the load of some of the sample
meters was not updated inspite of actual enhancement under VDS or otherwise.
The circle wise percentage increase in the actual load was observed as under: -
Khanna 4.9
Bathinda 4.7
Sangrur 3.8
Gurdaspur 1.5
Hoshiarpur 2.5
After updating the loads of
sample meters and recalculating the consumption of those meters which showed
consumption inconsistent with the reported loads and given supply hours, the
Agency calculated the month wise AP factor of each division for all the five
circles and thereafter computed the monthly consumption of each division by
multiplying the AP factor thus arrived at with the total connected load of the
division.
The Agency submitted its
report in May 2009. The AP consumption worked out by the Agency in the five
circles with the AP factor of the Board, the AP consumption determined with AP
factor calculated with updated loads and the difference in percentage terms is
given in Table 2.1(A).
Table 2.1(A)
Circles |
Consumption as per PSEB AP factor (MU) |
Consumption as per AP factor computed by
the Agency (MU) |
% difference |
Khanna |
509.94 |
399.39 |
21.68 |
Bathinda |
479.52 |
356.13 |
25.73 |
Sangrur |
1543.80 |
1188.31 |
23.03 |
Gurdaspur |
486.20 |
366.62 |
24.59 |
Hoshiarpur |
386.87 |
307.83 |
20.43 |
A copy of the preliminary
report submitted by the Agency to the Commission was sent to the Board for its
comments. The Board made the following observations:
·
Average AP connected load is not
as per PSEB records.
·
Light load has not been considered
at a number of places.
·
The supply hours considered in the
study are not as per actuals.
·
The efficiency of the motors has
not been taken into account.
·
Possibility of unauthorized loads
not being accounted for.
In view of these observations, the Agency was asked to recalculate the AP consumption for all the five circles. The Agency has, by and large, accepted the Board’s contentions as mentioned above and considered supply hours data provided by the office of the Chief Engineer/SO&C, factored in the efficiency of motors and also had taken into account the lighting load while computing the total load of the division. The possibility of unauthorized loads could not be taken into account because of difficulties in its quantification. The Agency then recalculated the AP factor with updated load on sample meters and consumption earlier supplied by the Board excluding the excessive consumption recorded by sample meters to the extent it was incompatible with the revised figures of connected load and supply hours. The connected load of each Division as furnished by the Board and AP factor arrived at as above was considered to calculate the total consumption in each Division of the five circles. The Agency submitted its report giving circle-wise consumption for 2007-08 which is compared with the AP consumption earlier supplied by the Board as in Table 2.1(B).
Table 2.1(B)
Circle |
AP
consumption for 2007-08 (MU) |
% difference |
|
Supplied
by Board |
Computed by the
Agency |
||
Khanna |
513.05 |
452.2 |
11.86 |
Bathinda |
497.463 |
416.0 |
16.38 |
Sangrur |
1592.764 |
1452.0 |
8.84 |
Gurdaspur |
489.608 |
435.0 |
11.15 |
Hoshiarpur |
381.022 |
328.0 |
13.92 |
Total |
3473.907 |
3083.2 |
11.25 |
Based on the validation of data for the five circles, a variation of 11.25% is observed between AP consumption reported by the Board to the Commission and that computed by the Agency. It is evident that the difference is mainly on account of non-updation of loads of AP connections on which sample meters have been installed and excessive consumption shown in the recordings of sample meters that is inconsistent with the given supply hours and the connected load. The report of the Agency is based primarily on the data furnished by the Board which has also been validated from the Board’s records. Moreover, the observations of the Board to the preliminary report made available to them have also, by and large, been taken into account. For these reasons, the Commission has no hesitation in accepting the findings of the Agency.
As the sample in the study represents 25% of the circles and about 33% of the total estimated AP consumption, its findings can with some measure of assurance be applied to the rest of the State. The Commission, accordingly, finds sufficient reason to presume that a similar pattern of over reporting agricultural consumption prevails in other circles of the Board as well. Accordingly, the Commission decides to reduce agriculture consumption reported by the Board (10030 MU) by 11.25% by applying the findings of this study to the State as a whole.
The Commission thus approves AP consumption of 8902 MU based on the
validated data and report of the Agency for the year 2007-08.
2.3.1
The Commission in its Tariff Order of 2007-08
fixed the target of T&D losses at 19.50%. During the determination of ARR
of 2008-09, the Board stated that T&D losses in 2007-08 would be 22.70% but
the Commission retained the T&D losses at 19.50% in the review. The Board
has now intimated that the actual losses of 2007-08 are 22.53%. The Commission,
however, sees no reason to accept T&D losses in excess of the target fixed
by the Commission.
The Commission, therefore, retains the T&D losses at 19.50% as
approved in the Tariff Order for the year 2007-08.
Table
2.2: Thermal Generation – 2007-08
(MU)
Sr.
No. |
Station |
Projected by PSEB during suo motu
determination of ARR 07-08 |
Approved
by the Commission T.O. 07-08 |
Revised
Estimates by PSEB in ARR 08-09 |
Approved
by the Commission T.O. 08-09 |
Actuals
by PSEB submitted in ARR 09-10 |
Now
approved by the Commission |
||||||
Gross |
Net |
Gross |
Net |
Gross |
Net |
Gross |
Net |
Gross |
Net |
Gross |
Net
|
||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1 |
GNDTP |
2540 |
2248 |
2769 |
2464 |
2885 |
2549 |
3008 |
2677 |
3008* |
2663 |
3008 |
2677 |
2 |
GGSTP |
9200 |
8418 |
9510 |
8702 |
9356 |
8553 |
9806 |
8972 |
9806 |
8979 |
9806 |
8972 |
3 |
GHTP
Stage-1 |
4500 |
4095 |
3542 |
3223 |
3418 |
3110 |
3509 |
3193 |
3508 |
3197 |
3508 |
3192 |
4 |
GHTP
Stage-2** |
|
|
|
|
|
|
|
|
135 |
120 |
135 |
123 |
5 |
Total |
16240 |
14761 |
15821 |
14389 |
15659 |
14212 |
16323 |
14842 |
16457 |
14959 |
16457 |
14964 |
Plant-wise generation is not available in the annual statement of accounts and as such the data supplied along with the ARR of 2009-10 and the generation figures validated by the Commission have been taken into account.
Accordingly, the Commission approves gross thermal generation for the year 2007-08 at 16457 MU.
Auxiliary Consumption
The auxiliary consumption projected by the Board during suo motu determination of ARR by the Commission for the year 2007-08, auxiliary consumption approved by the Commission in the Tariff Order, revised estimates furnished during determination of ARR of 2008-09, auxiliary consumption approved by the Commission in the review, actuals now supplied by the Board with the ARR for 2009-10 and auxiliary consumption finally approved by the Commission is given in Table 2.3 below.
Table
2.3: Auxiliary Consumption – 2007-08
Sr. No. |
Station |
Projected by PSEB during suo motu determination of
ARR 07-08 |
Approved by the
Commission in T.O. 07-08 |
Revised Estimates by PSEB in
ARR 08-09 |
Approved by the Commission in
T.O. 08-09 |
Actuals by PSEB submitted in ARR 09-10 |
Now approved by the
Commission |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
1 |
GNDTP |
11.50% |
11% |
11.63% |
11% |
11.41% |
11.00% |
2 |
GGSTP |
8.50% |
8.50% |
8.58% |
8.50% |
8.44% |
8.50% |
3 |
GHTP |
9% |
9% |
9.01% |
9% |
8.87% |
9.00% |
It is observed that actual
auxiliary consumption now reported by the Board is marginally higher for GNDTP
and lower for GGSTP and GHTP than the approved levels. As auxiliary consumption has been approved on normative basis, the
Commission is inclined to retain the levels as approved in the Tariff Order for
2007-08.
The net
thermal generation on this basis works out to 14964 MU as shown in column 14 of
Table 2.2.
The Commission further
observes that the Board has over-achieved in thermal generation by 501 MU (16322*
- 15821) gross and 452 MU (14841**-14389) net as compared to generation
originally approved, as shown in Table 2.2.
* 16322 = 16457 - 135
** 14841
= 14964 - 123
The Commission takes note
of higher thermal generation and consequential less power purchase to that
extent. This is further
discussed in para 2.9.
Table 2.4:
Hydel Generation – 2007-08
(MU)
Sr. No. |
Hydel Station |
Projected by PSEB during
suo motu determination of ARR
07-08 |
Approved by Commission in TO 07-08 |
RE by PSEB in ARR 08-09 |
RE accepted by Commission in TO 08-09 |
Actuals by PSEB in ARR 09-10 |
Now approved by Commission |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
1 |
Shanan |
529 |
529 |
517 |
540 |
540 |
540 |
2 |
UBDC |
446 |
446 |
380 |
428 |
428 |
428 |
3 |
RSD |
1568 |
1568 |
1484 |
1539 |
1538 |
1538 |
4 |
MHP |
1026 |
1026 |
1399 |
1362 |
1362 |
1362 |
5 |
ASHP |
657 |
642 |
790 |
710 |
710 |
710 |
6 |
Micro Hydel |
7 |
7 |
8 |
7 |
7 |
7 |
7 |
Total own hydel |
||||||
a |
Gross |
4233 |
4218 |
4578 |
4586 |
4585 |
4585 |
b |
Net |
4203 |
4059 |
4404 |
4425 |
45271 |
43653 |
8 |
PSEB Share from BBMB |
|
|
|
|
|
|
a |
Gross Share |
4204 |
4204 |
4653 |
4325 |
4327 |
4327 |
b |
Add Common pool share |
300 |
300 |
303 |
303 |
302 |
303 |
c |
Less External losses |
161 |
146 |
183 |
168 |
171 |
171 |
d |
Net Share from BBMB |
4343 |
4358 |
4773 |
4460 |
44582 |
4459 |
9 |
Total Net Hydel (Own + BBMB) |
8546 |
8417 |
9177 |
8885 |
8985 |
8824 |
1.
Net of auxiliary consumption (8 MU) and
transformation loss (50 MU).
2.
BBMB share including common pool is net of
transmission loss of 171 MU (3.95%) of gross share not including common pool.
3.
Own generation is net of
·
HP share (free) in RSD @ 4.6% (71 MU),
·
Royalty to HP in Shanan (53 MU),
·
Diversion to BBMB from ASHP (59 MU) on account of
extra power generated because of diversion of water from Nangal Hydel Channel
to Anandpur Sahib Hydel Channel during repair at Ganguwal/Kotla power houses,
·
Transformation loss @ 0.5% (23 MU)
·
Auxiliary consumption @ 0.5% for RSD generation of
1538 MU and UBDC Stage-1 generation of 184 MU (having static exciters) and @ 0.2%
for others (14 MU).
The actual gross hydel
generation from the Board’s own hydel stations for the year 2007-08 is 4585 MU
and the Commission accepts the same. While calculating the net generation, the
Board has not deducted the free HP share in RSD and royalty in Shanan. In line
with the principle being followed in such sales, the Commission has worked out
net hydel generation by deducting HP share in RSD, royalty in Shanan and
diversion to BBMB from ASHP from gross generation along with the auxiliary
consumption and transformation losses. Net hydel generation for the year
2007-08 thus works out to 4365 MU. The actual net availability from BBMB is
4459 MU which the Commission accepts.
The Commission, therefore, approves net
hydel generation for the year 2007-08 at 4365 MU from the Board’s own
generation and 4459 MU as net share from BBMB as shown in table 2.4.
Table 2.5: Energy
Balance – 2007-08
(MU)
Sr.
No. |
Particulars |
Approved
by the Commission in T.O. 08-09 |
Actual
by PSEB in ARR 09-10 |
Now
approved by the Commission |
Sales
& actual T&D losses as per approved
availability |
1 |
2 |
3 |
4 |
5 |
6 |
A)
Energy Requirement |
|||||
1 |
Metered
Sales |
19,992 |
20,214 |
20,214 |
20,214 |
2 |
Sales
to Agriculture Pumpsets |
8,960 |
10,030 |
8,902
|
8,902
|
3 |
Total
Sales within the State |
28,952 |
30,244 |
29,116
|
29,116
|
4 |
Loss
percentage |
19.50%
|
22.53% |
19.50%
|
25.12%
|
5 |
T&D
losses |
7,013 |
8,796 |
7,053
|
9,767
|
6 |
Sales
to Common pool consumers |
303 |
302 |
303 |
303 |
7 |
Outside
State Sales |
1,615 |
1,576 |
1,576 |
1,576 |
8 |
Total
requirement |
37,883 |
40,918 |
38,048
|
40,762
|
B)
Energy Available |
|||||
9 |
Own
generation (Ex-bus) |
||||
10 |
Thermal |
14,842 |
14,959 |
14,964
|
14,964
|
11 |
Hydro |
4,425 |
4,527 |
4,365 |
4,365 |
12 |
Share
from BBMB (incl.share of common pool consumers |
4,460 |
4,458 |
4,459
|
4,459
|
(common pool = 303) |
(common pool = 302) |
(common pool = 303) |
(common pool = 303) |
||
13 |
Purchase
net |
14,156 |
16,974 |
16,974 |
16,974
|
14 |
Total
Available |
37,883 |
40,918 |
40,762
|
40,762
|
Table 2.6: Fuel Cost – 2007-08
Sr. No. |
Station |
As per T.O. 07-08 |
As per Review in T.O.
08-09 |
||
Gross Generation (MU) |
Fuel Cost (Rs.crore) |
Gross Generation (MU) |
Fuel Cost (Rs.crore) |
||
1 |
2 |
3 |
4 |
5 |
6 |
1 |
GNDTP |
2769 |
474.16 |
3008 |
513.90 |
2 |
GGSTP |
9510 |
1416.83 |
9806 |
1,467.20 |
3 |
GHTP |
3542 |
513.28 |
3509 |
502.90 |
4 |
Total |
15821 |
2404.28 |
16323 |
2,484.00 |
The Commission observes that the Board
is still an integrated utility and the power generated during trial run of GHTP
Stage II Units had been injected into the grid of the Board without
consideration of frequency at that time. As such, the Commission is not
inclined to treat the power generated during trial run as power purchased at UI
rate and consequently reduce that amount from the capital cost of the plant.
However, fuel cost of the generation during trial runs will be considered and
allowed as revenue expense.
Table 2.7A: Calorific Value
and Price of Coal and Oil as submitted
by the Board for 2007-08
Sr. No. |
Station |
As submitted by PSEB |
||||
Calorific value of coal
(kCal/Kg) |
Calorific Value of Oil
(K.cal/Ltr) |
Price of Oil (Rs/KL) |
Price of coal including
transit loss (Rs./MT) |
Transit loss (%) |
||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
1 |
GNDTP |
4181 |
10056 |
23383 |
2313 |
2.04% |
2 |
GGSTP |
3972 |
10000 |
23254 |
2397 |
2.50% |
3 |
GHTP |
4153 |
9400 |
19250 |
2354 |
1.49% |
Table 2.7B: Calorific
Value and Price of Coal and Oil as approved
by the Commission for 2007-08
|
As
accepted by the Commission |
|
||||
Station |
Gross
Calorific value of coal (kCal/Kg) |
Calorific
Value of Oil (K.cal/Ltr) |
Price
of Oil (Rs/KL) |
Price
of coal including transit loss (Rs./MT) |
Transit
loss (%) |
Price
of coal excluding transit loss
(Rs./MT) |
|
1 |
2 |
3 |
4 |
5 |
6 |
GNDTP
|
4181 |
10066 |
23383 |
2313 |
1.87% |
2270 |
GGSTP |
3972 |
10000 |
23251 |
2397 |
2.40% |
2339 |
GHTP |
4153 |
9400 |
19246 |
2354 |
1.49% |
2319 |
Table 2.8: Fuel Cost- 2007-08
Sr.
No. |
Item |
Derivation |
Unit |
Approved
for 2007-08 |
|||
GNDTP |
GGSTP |
GHTP |
Total |
||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
1 |
Generation |
A |
MU |
3008 |
9806 |
3643 |
16457 |
2 |
Heat
Rate |
B |
k.cal/kWh
Generated |
3000 |
2500 |
2500 |
|
3 |
Specific
oil consumption |
C |
Milli
litre/kwh |
3.50 |
2.00 |
2.00 |
|
4 |
Calorific
value of oil |
D |
k.cal/litre |
10066 |
10000 |
9400 |
|
5 |
Calorific
value of coal |
E |
k.cal/kg |
4181 |
3972 |
4153 |
|
6 |
Overall
heat |
F
= (A x B) |
G.cal |
9024000 |
24515000 |
9107500 |
|
7 |
Heat
from oil |
G
= (A x C x D) / 1000 |
G.cal |
105975 |
196120 |
68488 |
|
8 |
Heat
from coal |
H
= (F-G) |
G.cal |
8918025 |
24318880 |
9039012 |
|
9 |
Oil
Consumption |
I=(Gx1000)/D |
KL |
10528 |
19612 |
7286 |
|
10 |
Transit
loss of coal |
J |
(%) |
2 |
2 |
2 |
|
11 |
Total
Coal Consumption excluding transit loss |
K=(H*1000)/E |
MT |
2132989 |
6122578 |
2176502 |
|
12 |
Quantity
of PANAM coal |
L |
MT |
901533 |
1842539 |
830668 |
|
13 |
Quantity
of coal other than PANAM coal excluding
transit loss. |
M=K-L |
MT |
1231456 |
4280039 |
1345834 |
|
14 |
Quantity
of coal other than
PANAM coal including transit loss |
N=M/(1-J/100) |
MT |
1256588 |
4367387 |
1373300 |
|
15 |
Total
Quantity of coal required |
O=L+N |
MT |
2158121 |
6209926 |
2203968 |
|
16 |
Cost
of oil |
P |
Rs./KL |
23383 |
23251 |
19246 |
|
17 |
Cost
of coal (excluding transit loss) |
Q |
Rs./MT |
2270 |
2339 |
2319 |
|
18 |
Total
cost of oil |
R=P
x I / 107 |
Rs.crore |
24.62 |
45.60 |
14.02 |
|
19 |
Cost
of coal |
S=O
x Q/107 |
Rs.crore |
489.89 |
1452.50 |
511.10 |
|
20 |
Total
Fuel cost |
T=
R+S |
Rs.crore |
514.51 |
1498.10 |
525.12 |
2537.73
|
The Commission, thus, approves the fuel
cost at Rs.2537.73 crore for gross
thermal generation of 16457 MU for the year 2007-08.
The Commission thus approves a cost of Rs.6020.37 crore for power
purchase of 16974 MU net.
The
Commission, therefore, disapproves expenses to the extent of Rs. 962.61 crore
on account of higher T&D losses.
The effect of this is
reflected at Sr. No. 12 (ii) of Table 2.13.
Table 2.9: Increase in Fuel Cost due to higher Thermal
Generation: 2007-08
Stations |
Now
approved by the Commission |
Increase
due to higher generation |
||
Generation
(MU) |
Fuel
Cost |
Increase
in generation (MU) |