SCO NO. 220-221, SECTOR-34-A
PETITION NO. 25 OF 2009
IN THE MATTER OF:
ANNUAL REVENUE REQUIREMENT
FILED BY THE
FOR THE FINANCIAL YEAR 2010-11
PRESENT : Mr. Jai Singh Gill,
Chairman
Mr. Satpal Singh Pall, Member
Mr.
Virinder Singh, Member
Date of Order:
ORDER
The Punjab State
Electricity Regulatory Commission (Commission), in exercise of powers vested in
it under the Electricity Act, 2003 (Act) passes this order determining the
Annual Revenue Requirement (ARR) and Tariff for supply of electricity by the
Punjab State Electricity Board (Board)/Successor Entities to consumers of the
State of Punjab for the year 2010-11.
The ARR filed by the Board, facts
presented by the Board in its various filings, objections received by the
Commission from consumer organizations and individuals, issues raised by the public in hearings held
at Bathinda, Chandigarh, Ludhiana and
Jalandhar, the responses of the Board to the objections and observations of the
Government of Punjab (GoP) in this respect have been considered. The State
Advisory Committee constituted by the Commission under Section 87 of the Act
has also been consulted and all other relevant facts and material on record
have been perused before passing this Order.
1.1
Background
The Commission has
in its previous seven Tariff Orders determined tariff in pursuance of the ARRs
and Tariff Applications submitted by the Board for the years 2002-03 to
2006-07, 2008-09 and 2009-10. Tariff Order for the year 2007-08 had been passed
by the Commission in suomotu proceedings.
1.2 ARR for the year 2010-11
The Board filed the
ARR for 2010-11 on 30.11.2009. Therein the Board had worked out a cumulative
revenue gap of Rs.6575 crore for the year 2010-11 including carried over gaps
of 2008-09 and 2009-10. As the petition filed by the Board did not contain any
proposal to cover this gap a letter dated 1.12.2009 was issued to the Board
asking it to submit a tariff or any other proposal to cover this gap. The Board
in its response on 3.12.2009 replied that the Commission may determine the gap
and fix tariff accordingly based on the details furnished by it in its ARR. The
Commission took the ARR on record on 7.12.2009. On scrutiny it was noticed that
the ARR was deficient in some respects and in its communication of 01.01.2010
the Commission sought further information which was furnished by the Board in
its letters dated 28.1.2010, 25.2.2010 and 26.2.2010.
The Annual Revenue
Requirement determined by the Commission in this Tariff Order is based on the
petition filed by the Punjab State Electricity Board, operating as an
integrated utility performing function of Generation, Transmission and
Distribution of electricity. The tariff determination by the Commission is
based on the audited accounts of 2008-09, revised estimates of 2009-10 and
projections of 2010-11 as submitted by the Board.
The Commission notes
that the GoP, in exercise of powers conferred under section 131, 132, 133 and
other enabling provisions of the Electricity Act, 2003, has on April 16, 2010,
notified that the Board constituted under section 5 of the Electricity Supply
Act, 1948 has ceased to exist and stands replaced by two corporate entities
namely Punjab State Power Corporation Ltd (POWERCOM) and Punjab State
Transmission Corporation Ltd (TRANSCO), referred to as Successor Entities. The
Government has also notified a Transfer Scheme in Notification No.1/9/08-EB(PR)
/196 dated 16th April, 2010 which details the process of
classification/division of assets and liabilities, functions, transfer of
personnel etc. between the two entities.
Clause 8, of the
aforementioned Notification, clearly states that all pending proceedings by or
against the Board on the Effective Date of Transfer (to be reckoned as
16.04.2010) of the undertaking to the Transferee shall not abate or discontinue
or otherwise in any way be effected prejudicially by reasons of the transfer
provided in this Scheme, and such proceedings may be continued by or against
the Transferee(s). Accordingly, the Commission treats the ARR Petition filed by
the Board on 30.11.2009, as a pending petition of POWERCOM and TRANSCO.
The Commission also
observes that the Provisional Balance Sheets, ending 31.03.09, of the two
successor entities, as appended to the above mentioned Notification shows
significant variation when compared to the audited balance sheet of the
integrated utility. The Commission understands that the Balance Sheet so
determined is provisional and shall be firmed up in due course as would be
evident from clause 9 of the Transfer Scheme which explicitly states that the
classification and transfer under this scheme, is provisional and will be made
final upon the expiry of 12 months from the Effective Date of Transfer or 6
months after the audited accounts are available, whichever is later. Also,
clause 3 of the Transfer Scheme extinguishes and cancels all assets and
liabilities of the Board towards GoP and vice-versa whereas in clause 5 they
are restored and passed on to the Successor Entities as is seen from the
provisional Balance Sheet of these entities wherein GoP loans have been shown
as outstanding. In these circumstances, the Commission for the purpose of
tariff determination deems proper to rely on the information filed by the Board
in its ARR petition and not on the Provisional Balance Sheet, yet to be
approved by the CAG.
Various charges
approved in the Tariff Order of 2010-11 are based on prudent determination of
generation, transmission & distribution cost and the formation of two
separate entities as a result of unbundling may not immediately warrant
re-determination of cost and further apportionment of revenue is possible as
per GoP (Deptt of Power) Notification No 229 dated 16.04.2010. However, the
Successor Entities would be free to submit fresh petitions which shall be duly
considered by the Commission. During True Up and review of the ARR, the
Commission generally adheres to existing norms and principles but consequent
upon the implementation of the Transfer Scheme, it will be open to modification
of norms when required in the subsequent ARRs.
1.3 Invitation of objections and public
hearings
A public notice was
published by the Board in the Tribune, The Hindustan Times, Dainik Bhaskar and
Daily Ajit on
The Commission
received 24 written objections by 19.01.2010 and 16 additional written
objections thereafter. The Commission decided to take all these objections into
consideration.
Number of
objections received from individual consumers, consumer groups, organizations
and others are detailed below:
Sr. No. |
Category |
No. of Objections |
1. |
Chambers
of Commerce |
3 |
2. |
Industrial
Associations |
10 |
3 |
Industry |
11 |
4 |
Railways |
1 |
5 |
PSEB
Engineers/Employees Association |
2 |
6 |
Individuals |
10 |
7 |
Govt.
of |
1 |
8 |
Forums |
2 |
|
Total |
40 |
The list of
objectors is given in Annexure-I to
this Tariff Order. The Board submitted its comments to all the objections which
were made available to the respective objectors.
The Commission
decided to hold public hearings at Bathinda,
Venue |
Date
& time of public hearing |
Category of consumers to be heard. |
|
BATHINDA Circuit
House, Civil Lines, Near D.C.Residence, Bathinda. |
|
All
consumers/organizations of the
area |
|
Commission
Office i.e. SCO No.220-221, Sector 34-A, |
|
Industry |
|
3.00 PM onwards |
Agriculture
consumers and their unions |
||
Commission
Office i.e. SCO No.220-221, Sector 34-A, |
|
All
consumers except Industry, Agriculture consumers and staff unions of the
Board. |
|
|
Staff
unions of Board and other organizations. |
||
Circuit
House, |
|
All
consumers/ organizations of the area. |
|
JALANDHAR Circuit
House, Skylark Chowk, Opp.
Skylark Hotel,
Jalandhar. |
|
All
consumers/ organizations of the area. |
|
Through public
notices published in different newspapers, it was intimated that the Commission
will conduct a public hearing at
The public hearings
were held as per schedule and objectors, general public and the Board were
heard by the Commission. A summary of the issues raised, the response of the
Board and the views of the Commission are contained in Annexure-II of this Tariff Order.
1.4
The Government was approached by the Commission through
letter dated 21.12.2009 seeking its views on the ARR to which the Government
responded on 10.3.2010, which has been taken note of by the Commission.
1.5
State Advisory Committee
The State Advisory
Committee set up under Section 87 of the Act, discussed the Board’s ARR in a
meeting convened for the purpose on 10.02.2010. The minutes of the meeting of
the State Advisory Committee are enclosed as Annexure–III to this Order.
The Commission has
thus taken the necessary steps to ensure that due process, as contemplated
under the Act and Regulations framed by the Commission, is followed and
adequate opportunity given to all stakeholders in presenting their views.
1.6
Compliance of Directives
In its previous
Tariff Orders, the Commission had issued certain directives to the Board in the
public interest. A summary of directives issued along with the comments of the
Commission is given in Annexure-IV
of this Tariff Order.
Chapter 2
True-up for the
year 2008-09
2.1.
Background
The Commission approved the ARR
and Tariff for the year 2008-09 in its Tariff Order dated
2.2.
Energy Demand (Sales)
2.2.1.
The sales
projected by the Board during the determination of ARR for the year 2008-09,
sales approved by the Commission in the Tariff Order of the year 2008-09, revised
estimates furnished during determination of ARR of the year 2009-10, sales
approved by the Commission in review and actual sales figures now given by the
Board are summarized in Table 2.1 below.
Table 2.1: Energy Sales – 2008-09
(MUs)
Sr. No. |
Category |
Projected by PSEB during determination of ARR 08-09 |
Approved by the Commission in T.O.
08-09 |
Revised Estimates of PSEB during
determination of ARR of 09-10 |
Approved by the Commission in
review |
Actual as in the ARR of 10-11 |
Now approved by the Commission |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
1 |
Domestic |
6476 |
6449 |
6692 |
6456 |
6695 |
6695 |
2 |
Non-Residential |
2039 |
2030 |
2067 |
1911 |
1967 |
1967 |
3 |
Small
Power |
734 |
748 |
731 |
712 |
743 |
743 |
4 |
Medium
Supply |
1571 |
1542 |
1555 |
1489 |
1556 |
1556 |
5 |
Large
Supply |
9394 |
9359 |
9081 |
8587 |
8747 |
8747 |
6 |
Public
Lighting |
153 |
149 |
147 |
137 |
147 |
147 |
7 |
Bulk
Supply |
485 |
497 |
507 |
477 |
480 |
480 |
8 |
Railway
Traction |
110 |
111 |
118 |
123 |
126 |
126 |
9 |
Total
Metered sales (within State) |
20962 |
20885 |
20898 |
19892 |
20461 |
20461 |
10 |
Agriculture
pump sets |
10014 |
9408 |
9766 |
8374 |
9349 |
8395 |
11 |
Total
sales within the State |
30976 |
30293 |
30664 |
28266 |
29810 |
28856 |
12 |
Common
pool |
303 |
303 |
303 |
303 |
302 |
302 |
13 |
Outside
State sales |
2036 |
2036 |
1541 |
2323 |
2515 |
2515 |
14 |
Total
(11+12+13) |
33315 |
32632 |
32508 |
30892 |
32627 |
31673 |
The Board has
furnished the actual total sales at 32627 MUs for the year 2008-09 as per
audited accounts including the theft of energy of 396 MUs. This theft of energy
has not been apportioned to different consumer categories in the audited
accounts but the Board in its ARR petition (Vol. 1) for the year 2010-11 has
submitted category-wise sales for year 2008-09 by apportioning such energy to each
category of consumers on pro-rata basis which is as per column 7 of Table 2.1.
2.2.2 Metered Sales: In metered sales, the
Board has included 396 MUs of energy on account of theft. The revenue on this
account has been shown as Rs.63.80 crore in the annual accounts which is not
commensurate with the revenue accruing from sale
of energy of 396 MUs to metered categories. In the tariff order for 2009-10,
the Commission accepted the revenue and the sales figures for 2007-08 as per
the audited accounts of the Board since the same were audited by AG (
The Commission notes
that the Board had been asked to correctly account for the amount assessed on
account of theft as per actual consumer categories only in the Tariff Order of
2009-10. Thus, action on the part of the Board could at best be taken for the
year 2009-10 and this aspect will be considered by the Commission at the time
of review for that year. Accordingly, the Commission estimates sales for the
year 2008-09 on the basis of actuals given in the audited accounts for that
year and adjusted by adding theft of energy to the extent of 396 MUs to
different metered consumer categories on a pro-rata basis. The Commission,
thus, approves metered sales within the State at 20461 MUs.
The Commission accepts common pool sales at 302 MUs and
outside State sales as 2515 MUs on the basis of actuals as given in the audited
accounts for 2008-09.
Metered sales now
approved by the Commission are as shown in column 8 of Table 2.1.
2.2.3
AP Consumption: The Commission in its Tariff Order of the
year 2008-09 approved AP consumption of 9408 MUs after allowing a normative
growth of 5% over the revised approved consumption of 8960 MUs for the previous
year (year 2007-08). While doing so, the Commission observed that the
methodology of computing AP consumption on the basis of sample meter readings
and connected load needs further refinement. Based on the observation of the
Commission in the Tariff Order of 2008-09 and Board’s willingness to undertake
a validation exercise through an independent agency, the Commission appointed
M/s
The Board in its ARR petition has submitted that very little time was
available to examine in detail both the approach adopted by the Agency and the
estimated AP consumption based thereon and the final report of the Agency was
received by the Board only a month before the tariff petition for 2010-11 was
to be filed. The Board has, therefore, requested that it should be permitted to
submit further comments on the final conclusions of the Agency after submission
of the ARR in case need therefor is envisaged by the Board. However, the Board
has made the following observations in the ARR petition:
·
The Agency, in the preliminary report, had pointed out that
the connected load in case of several meters was higher on account of VDS or
other such reasons in comparison with the records being maintained by the
Board. Based on these findings, the connected load of such meters was revised
to calculate the consumption and thereafter the load factor. If the operating
load is found to be higher than the load in the ledgers, then under such
circumstances, the better way to estimate the load would be only through
correct energy meters. Any normative calculation of the operating load/estimation
of consumption can result in skewed consumption levels.
·
The Agency has worked out the consumption of sample meters
by applying a check that in case the consumption recorded by a meter is more
than the theoretical consumption (calculated using formula i.e. connected load
multiplied by hours of supply), then the theoretical consumption is to be
considered for the purpose of calculating the load factor and vice versa. The
Board has observed that once a meter is identified to be giving incorrect reading
then the same meter should ideally be excluded from the study, which has not
been done by the agency. The Board understands that in case a meter is showing
excess consumption, the same may be a pointer towards theft, poor condition of
equipment at the site, supply hours in excess of the average considered in the
study etc, which cannot be ignored in this manner.
·
The Agency, in the final report has, considered a motor
efficiency of 80% across all the divisions. The Board understands that there
are around 55-60% submersible motors and 40-45% monoblock motors installed by
the farmers in the State. Moreover, the Board understands that even brand new
motors have an efficiency of less than 50% for submersible motors and around
60-65% in case of monoblock motors. Consideration of such higher motor
efficiency by the Agency has resulted in lower AP sales estimation.
The Commission observes that the points urged by the Board regarding
manner in which agriculture consumption was computed for 3 quarters of the year
2008-09 are substantially the same as made at the time of considering the ARR
for 2009-10. All these matters had been carefully considered by the Commission
and there is, at the stage of true up, no scope to reopen the principles and
norms on which these matters were earlier decided.
The
Commission thus approves AP consumption of 8395 MUs by reducing the AP
consumption of 9349 MUs by 10.20% based on the report of the Agency, for the
year 2008-09.
2.3.
Transmission and Distribution Losses (T&D Losses)
The
Commission, in its Tariff Order of 2008-09, fixed the target of T&D losses
at 19.50%. During the determination of ARR of 2009-10, the Board stated that
T&D losses in 2008-09 would be 21.00% but the Commission retained T&D
losses at 19.50% in the review. The Board has now intimated that actual losses in
2008-09 are 19.92% at the level of AP consumption computed by it. The
Commission, however, sees no reason to accept T&D losses in excess of the
target earlier fixed.
The
Commission, therefore, retains the T&D losses at 19.50% as approved in the
Tariff Order for the year 2008-09.
2.4.
PSEB’S Own Generation
2.4.1.
Thermal Generation: The station-wise generation projected by the
Board during the determination of ARR by the Commission for the year 2008-09,
generation approved by the Commission in the Tariff Order, revised estimates
furnished by the Board during determination of ARR of 2009-10, generation
approved by the Commission in the review, actuals now supplied by the Board
with the ARR for 2010-11 and generation finally approved by the Commission is
given in Table 2.2.
Table 2.2: Thermal Generation – 2008-09
(MUs)
Sr. No. |
Station |
Projected by PSEB during determination of ARR 08-09 |
Approved by the Commission T.O.
08-09 |
Revised Estimates by PSEB in ARR 09-10 |
Approved by the Commission T.O.
09-10 |
Actuals by PSEB submitted in ARR
10-11 |
Now approved by the Commission |
||||||
Gross |
Net |
Gross |
Net |
Gross |
Net |
Gross |
Net |
Gross |
Net |
Gross |
Net |
||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
1A |
GNDTP Unit I&II |
2411 |
2146 |
1542 |
1402 |
2748 |
2428 |
1562 |
1402 |
2846 |
2517 |
15625 |
1390 |
1B |
GNDTP Unit III&IV |
1004 |
894 |
1284 |
1143 |
12845 |
1143 |
||||||
2 |
GGSTP |
9469 |
8655 |
9886 |
9046 |
9224 |
8434 |
9611 |
8794 |
9611 |
8809 |
9611 |
8794 |
3A |
GHTP Stage-1 |
3265 |
2971 |
61271 |
5576 |
3391 |
3078 |
3532 |
3214 |
56103 |
5126 |
5610 |
5105 |
3B |
GHTP Stage-2 |
2800 |
2534 |
1160 |
1056 |
20782 |
1891 |
||||||
4 |
Total |
17945 |
16306 |
18559 |
16918 |
16523 |
14996 |
18067 |
16444 |
180674 |
16452 |
18067 |
16432 |
1 Comprises
of 3457 MUs by Stage 1 and 2670 MUs by Stage II.
2 Includes 1168 MUs
generated during trial runs.
3 Includes 1168 MUs
generated during trial runs of Unit III and Unit IV.
4
Against 18066 MUs gross generation submitted by the Board.
5 1562 MUs generated by GNDTP Unit 1&2 and
1284 MUs by GNDTP Unit 3&4 (on the basis
of data supplied during processing of ARR
for the year 2009-10).
Plant-wise generation is not
available in the annual statement of accounts and as such the data supplied
along with the ARR of 2010-11 and the generation figures validated by the
Commission have been taken into account.
Accordingly, the Commission approves gross thermal
generation for the year 2008-09 at 18067 MUs.
Auxiliary Consumption
The auxiliary consumption
projected by the Board during determination of ARR by the Commission for the
year 2008-09, auxiliary consumption approved by the Commission in the Tariff
Order, revised estimates furnished during determination of ARR of 2009-10,
auxiliary consumption approved by the Commission in the review, actuals now
supplied by the Board with the ARR for 2010-11 and auxiliary consumption
approved by the Commission is given in Table 2.3 below.
Table 2.3:
Auxiliary Consumption – 2008-09
Sr. No. |
Station |
Approved by the Commission in T.O.
08-09 |
Revised Estimates by PSEB in
ARR 09-10 |
Approved by the Commission in T.O.
09-10 |
Actuals by PSEB submitted in ARR 10-11 |
Now approved by the Commission |
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
1A |
GNDTP
Unit I & II |
11.00% |
9.10% |
11.66% |
10.22% |
11.57% |
11.00% |
1B |
GNDTP
Unit III & IV |
11.00% |
11.00% |
||||
2 |
GGSTP |
8.60% |
8.50% |
8.56% |
8.50% |
8.34% |
8.50% |
3A |
GHTP Stage I |
9.00% |
9.00% |
9.21% |
9.00% |
8.71% |
9.00% |
3B |
GHTP Stage II |
9.50% |
9.00% |
9.00% |
8.35% |
9.00% |
It is observed that actual auxiliary consumption now
reported by the Board is marginally higher for GNDTP and lower for GGSTP and
GHTP than the approved levels. The
Commission observes that the auxiliary consumption of GGSTP and GHTP Thermal
Plants has been approved on normative basis, whereas for GNDTP, the Commission
has been adopting the operational norms of Tanda Thermal Plant. In its Tariff
Order for the Year 2009-10, the Commission had fixed the auxiliary consumption
of GNDTP Bhatinda based on an order of CERC approving the revised operating
norms of the Tanda Thermal Plant after its R&M works.
The Commission had revised
auxiliary consumption as 10.22% for GNDTP Units 1&2 for the year 2008-09 in
the Tariff Order for 2009-10 after reducing 1.78% (0.95+0.83%) from the norm of
12% fixed by CERC for the Tanda Thermal Station. On re-examination, the
Commission observes that it would be inappropriate to effect a deduction of
0.95% as this represents the losses in the generator transformer, unit
auxiliary transformer, station transformer and excitation power which are
theoretically occurring both in Bathinda and Tanda station. Thus, a deduction
of 0.83% alone would be justified as that is the energy consumption on account
of the three stage water cooling system existing at Tanda but not in GNDTP. On
that basis, auxiliary consumption for GNDTP Unit 1&2 would work out to
11.17 (10.22+0.95). However, the Commission finds no justification in allowing
auxiliary consumption after R&M works of Units 1&2 in excess of the pre
R&M value. Assuming that the auxiliary consumption in the case of Unit
1&2 is less than 11% and that for Unit 3&4 in excess thereof, the
Commission compositely determines auxiliary consumption for all 4 units of
GNDTP at 11%.
In view of the above, the
Commission approves the auxiliary consumption of 11.00%, 8.50% and 9.00% for
GNDTP, GGSTP and GHTP respectively.
The net thermal generation on
this basis works out to 16432 MUs as shown in column 14 of Table 2.2.
The Commission
further observes that the Board has not been able to achieve gross and net thermal
generation originally approved.
The Board has
under-achieved the target by 492 MUs (18559-18067) gross and 486 MUs (16918-16432)
net as compared to generation originally approved, as shown in Table 2.2. The
Commission takes into account the loss in thermal generation of 492 MUs gross
(486 MUs net) and disapproves consequential additional power purchase
requirement to that extent. This is discussed further in para 2.9.
2.4.2.
Hydel Generation: The station-wise generation submitted by the
Board to the Commission during determination of ARR and Tariff for the year
2008-09, generation approved by the Commission in its Tariff Order, revised
estimates furnished by the Board during determination of ARR of 2009-10,
generation approved by the Commission in review and actuals now furnished by
the Board and those accepted by the Commission are given in Table 2.4.
Table 2.4: Hydel Generation –
2008-09
(MUs)
Sr. No. |
Hydel Station |
Projected by PSEB during determination of ARR 08-09 |
Approved by Commission in TO 08-09 |
RE by PSEB in ARR 09-10 |
Approved by Commission in TO 09-10 |
Actuals by PSEB in ARR 10-11 |
Now approved by Commission |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
1 |
Shanan |
507 |
507 |
507 |
532 |
532 |
532 |
2a |
UBDC Phase 1 |
432 |
432 |
311 |
140 |
339 |
339 |
2b |
UBDC Phase 2 |
199 |
|||||
3 |
RSD |
1586 |
1612 |
1539 |
1474 |
1474 |
1474 |
4 |
MHP |
1074 |
1074 |
797 |
1122 |
1132 |
1132 |
5 |
ASHP |
596 |
587 |
726 |
751 |
689 |
6892 |
6 |
Micro
Hydel |
6 |
6 |
8 |
4 |
10 |
10 |
7 |
Total own hydel |
||||||
a |
Gross |
4201 |
4218 |
3888 |
4222 |
4175 |
4175 |
b |
Net Own
Hydel |
4027 |
4056 |
3841 |
4005 |
41311 |
40203 |
8 |
PSEB
Share from BBMB |
|
|
|
|
|
|
a |
Net Share |
4187 |
4187 |
4256 |
4473 |
4307 |
4307 |
b |
Add
Common pool share |
303 |
303 |
303 |
303 |
302 |
302 |
c |
Less
External losses |
165 |
163 |
168 |
166 |
|
|
d |
Net Share
from BBMB |
4325 |
4327 |
4391 |
4610 |
4610 |
4609 |
9 |
Total
Net Hydel (Own + BBMB) |
8352 |
8383 |
8232 |
8615 |
8741 |
8629 |
1.
Net of auxiliary consumption (7.18 MUs) and transformation
loss (36.83 MUs).
2.
Net of diversion of 62 MUs to BBMB on account of extra power
generation at ASHP owing to diversion of water from NHC to AHC.
3.
Own generation is net of
·
HP share (free) in RSD @ 4.6% (68 MUs).
·
Royalty to HP in Shanan (53 MUs).
·
Transformation losses @ 0.5% (21 MUs).
·
Auxiliary consumption @ 0.5% for RSD generation of 1474 MUs
and UBDC Stage-1 generation of 140 MUs (having static exciters) and @ 0.2% for
others (13 MUs).
The actual gross
hydel generation from the Board’s own hydel stations for the year 2008-09 is
4175 MUs and the Commission accepts the same. While calculating the net
generation, the Board has not deducted the free HP share in RSD and royalty in
Shanan. In line with the principle being followed in such sales, the Commission
has worked out net hydel generation by deducting HP share in RSD and royalty in
Shanan along with the auxiliary consumption and transformation losses. Net
hydel generation for the year 2008-09 thus works out to 4020 MUs. The actual
net availability from BBMB is 4609 MUs which the Commission accepts.
The Commission, therefore, approves net
hydel generation for the year 2008-09 at 4020 MUs from the Board’s own
generation and 4609 MUs as net share from BBMB as shown in table 2.4.
2.5.
Power Purchase
The Commission in its Tariff Order of 2008-09 approved net power purchase
of 14669 MUs. During determination of ARR of 2009-10, the Board furnished
revised estimates for net power purchase of 15575 MUs during presentation on 10.06.09
but in review, the Commission approved 12680 MUs only. The Board has now submitted
net purchases during 2008-09 of 14851 MUs (net) as per audited accounts. This matter is further discussed in para 2.8.
2.6.
Energy Balance
2.6.1. The details of energy requirement and availability for 2008-09 approved
by the Commission in review in the Tariff Order of 2009-10 and the actuals now
furnished by the Board are given in Table 2.5. The energy balance, including
T&D losses along with sales and availability now approved by the Commission
is depicted in column 6 of Table 2.5.
Table 2.5: Energy Balance –
2008-09
(MUs)
Sr. No. |
Particulars |
Approved
by the Commission in T.O. 09-10 |
Actual
by PSEB in ARR 10-11 |
Now
approved by the Commission |
Sales
& actual T&D losses as per approved energy available |
1 |
2 |
3 |
4 |
5 |
6 |
A) Energy Requirement |
|||||
1 |
Metered Sales |
19,892 |
20,461 |
20,461 |
20,461 |
2 |
Sales to Agriculture Pumpsets |
8,374 |
9,349 |
8,395 |
8,395 |
3 |
Total Sales within the State |
28,266 |
29,810 |
28,856 |
28,856 |
4 |
Loss percentage |
19.50% |
19.92% |
19.50% |
22.21% |
5 |
T&D losses |
6,847 |
7,416 |
6,990 |
8,239 |
6 |
Sales to Common pool consumers |
303 |
302 |
302 |
302 |
7 |
Outside State Sales |
2,323 |
2,515 |
2,515 |
2,515 |
8 |
Total requirement |
37,739 |
40,043 |
38,663 |
39,912 |
B) Energy Available |
|||||
9 |
Own generation (Ex-bus) |
||||
10 |
Thermal |
16,444 |
16,451 |
16,432 |
16,432 |
11 |
Hydro(Including share from BBMB and common pool
consumers |
8,615 |
8,741 |
8,629 |
8,629 |
12 |
Purchase net |
12,680 |
14,851 |
14,851 |
14,851 |
13 |
Total Available |
37,739 |
40,043 |
39,912 |
39,912 |
2.6.2.
The total
energy requirement now approved by the Commission considering T&D losses at
19.50% is 38663 MUs (net) as against 40043 MUs projected by the Board, whereas
total energy availability now approved is 39912 MUs (net). The difference of 1249
MUs (net) between energy requirement and energy availability is owing to the
underachievement of T&D loss target as discussed in para 2.3 and depicted
in columns 5 & 6 of Table 2.5. Higher T&D loss over and above the level
approved by the Commission has resulted in increased net power purchase to the
extent of 1249 MUs (8239 - 6990) MUs. The matter is further discussed in para 2.9.
The Commission
approves the total energy requirement for the year 2008-09 at 38663 MUs (net)
after retaining T&D losses at 19.50%.
2.7.
Fuel Cost
2.7.1. In its Tariff Order of 2008-09, the Commission approved the fuel cost as
Rs. 2742.62 crore for a gross thermal generation of 18559
MUs. In review, this cost was revised to Rs. 2978.85 crore
for the then approved gross generation of 18067 MUs. Details of approved fuel cost
in the Tariff Order of 2008-09 and review are given in Table 2.6.
Table 2.6: Fuel Cost – 2008-09
Sr.
No. |
Station |
As per T.O. 08-09 |
As per Review in T.O. 09-10 |
||
Gross Generation (MUs) |
Fuel Cost (Rs.crore) |
Gross Generation (MUs) |
Fuel Cost (Rs.crore) |
||
1 |
2 |
3 |
4 |
5 |
6 |
1 |
GNDTP Unit I&II |
1542 |
214.17 |
1562 |
264.81 |
2 |
GNDTP Unit III&IV |
1004 |
172.10 |
1284 |
233.25 |
3 |
GGSTP |
9886 |
1480.84 |
9611 |
1581.42 |
4 |
GHTP |
6127 |
875.51 |
5610 |
899.37 |
5 |
Total |
18559 |
2742.62 |
18067 |
2978.85 |
2.7.2.
The Board
in its ARR of 2010-11 has indicated actual fuel cost for 2008-09 for a gross
generation of 18067 MUs as Rs.3154.35 crore (including fuel cost for infirm
power) whereas in the audited accounts of 2008-09, the total generation
expenses are Rs. 3175.23 (3171.49+ 3.74) crore net of capitalisation. These
comprise of Rs.3064.65 crore for coal and oil consumption, Rs.36.27 crore for
other fuel related costs including octroi, contract handling charges, siding
charges etc., Rs.49.39 crore for fuel related losses including transit losses
and Rs.21.17 crore for other operating expenses such as cost of water,
lubricants, consumable stores and station supplies. Out of these, Rs.21.17 crore
booked towards other operating expenses do not form part of the fuel cost and
are being considered under repair and maintenance expenses in para 2.11. Thus,
the net fuel cost as per audited accounts is taken as Rs. 3154.06 (3175.23 – 21.17) crore.
2.7.3.
The actual
fuel cost intimated by the Board for 2008-09 in its ARR of 2010-11 for a gross
thermal generation of 18067 MUs is based on calorific value and price of coal /
oil as given in Table 2.7A. The fuel cost on account of generation of GHTP
Stage II during its trial run has been proposed as actually incurred by the
Board. The Board has submitted that the units cannot be expected to run at the
normative levels during trial runs and according to the CERC Regulations
(2004-09) a grace period of 180 days is to be provided for stabilization of the
unit. The Board has further stated that in case of PSEB, the period under
consideration was the trial operations prior to declaration of
The Commission observes that
effective from 1st April 2006, CERC in its notification
no.L-7/25(5)/2003-CERC dated 27.09.07 has done away with the provision for
relaxation in operating parameters for generating stations during the stabilization period. As such the
Commission does not find any merit in the submission of the Board that the
operating parameters of GHTP stage II unit should be relaxed and be considered on
an actual basis.
Table 2.7A: Calorific Value and Price of Coal and Oil
as submitted
by the Board for 2008-09
Sr. No. |
Station |
As considered by PSEB |
||||
Calorific value of coal (kCal/Kg) |
Calorific Value of Oil (K.cal/Ltr) |
Price of Oil (Rs/KL) |
Price of coal including transit
loss (Rs./MT) |
Transit loss (%) |
||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
1 |
GNDTP |
4239 |
10000 |
28297 |
2449 |
1.41% |
2 |
GGSTP |
4019 |
10000 |
30712 |
2518 |
2.20% |
3 |
GHTP |
4077 |
9400 |
28347 |
2531 |
1.69% |
2.7.4.
Fuel cost being a major item of expense, the
Commission thought it prudent to get the same validated. The finally accepted values are indicated in
Table 2.7B.
Table 2.7B: Calorific Value and Price of Coal and Oil as approved
by the Commission for 2008-09
|
As
accepted by the Commission |
|||||
Station |
Gross
Calorific value of coal (kCal/Kg) |
Calorific
Value of Oil (K.cal/Ltr) |
Price of
Oil (Rs/KL) |
Price of
coal including transit loss (Rs./MT) |
Transit
loss (%) |
Price of
coal excluding transit loss (Rs./MT) (computed) |
|
1 |
2 |
3 |
4 |
5 |
6 |
GNDTP |
4239 |
10181 |
28297 |
2449 |
1.41% |
2414.5 |
GGSTP |
4019 |
10000 |
30712 |
2518 |
2.20% |
2462.6 |
GHTP |
4077 |
9400 |
28347 |
2531 |
1.69% |
2488.2 |
2.7.5.
With
regard to Station Heat Rate (SHR) of GGSTP, the Board has pointed out that the
average aging for the turbines of 6 units as on 30.9.2009 was 14.89% and that
in these circumstances, the efficiencies of the boiler and other plant
assemblies are bound to decline from their designed values. Accordingly, the
proposed SHR of 2700 Kcal/Kwh would be a more realistic assessment. In respect
of GNDTP, the Board has brought out that certain elements of renovation and
modernization of Unit 1 and 2 had not been undertaken in 2008-09 which had led
to higher fuel costs for these units. However, with the completion of the said
works, the SHR for these units has since improved. The Commission notes that
similar submissions regarding the performance parameters of the Board’s Thermal
Plants were made at the time when the ARR for 2009-10 came up for consideration
and that the Commission had, after taking all relevant factors into account,
decided these issues. The Commission is of the view that the principles and
norms on which these matters were decided can not be reopened during true up
for the year 2008-09 and accordingly, performance parameters as fixed in the Tariff
Order of the previous year are proposed to be retained.
2.7.6.
In the ARR
for the year 2009-10, the Board had not reported any consumption of imported
coal for the year 2008-09. This was also verified at the power stations at the
time of validation when it was noted that a substantial quantity of coal from
the Board’s captive coal mine (PANAM) was used during 2008-09 which is priced
F.O.R. destination. The price of coal and corresponding calorific values given
in the ARR of the Board (Table 2.7A) and those validated by the Commission
(Table 2.7B) are weighted average values of coal, including PANAM coal.
2.7.7.
The
Commission has now approved revised gross thermal generation of 18067 MUs (2846
MUs for GNDTP, 9611 MUs for GGSTP and 5610 MUs for GHTP) as discussed in para
2.4.1. The fuel cost for different thermal stations corresponding to generation
now approved has been worked out, based on the parameters adopted by the
Commission in its Tariff Order of 2008-09. Price and calorific value of coal
and oil has been adopted as validated and accepted by the Commission.
2.7.8. No transit loss has been allowed for PANAM
coal while arriving at fuel cost as prices according to the contract are on
F.O.R. destination basis. In case of coal other than PANAM coal, transit loss
of 2% has been allowed by the Commission.
2.7.9.
On the
above basis, fuel cost for the year 2008-09 for different thermal stations
corresponding to actual generation is given in Table 2.8.
Table 2.8: Approved Fuel
Cost 2008-09
Sr.
No. |
Item |
Derivation |
Unit |
Approved
for 2008-09 |
||||
GNDTP
(I&II) |
GNDTP
(III&IV) |
GGSTP |
GHTP |
Total |
||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
8 |
1 |
Generation |
A |
MU |
1562 |
1284 |
9611 |
5610 |
18067 |
2 |
Heat Rate |
B |
k.cal/kWh
Generated |
2850 |
3000 |
2500 |
2500 |
|
3 |
Specific oil consumption |
C |
Milli
litre/kwh |
2.00 |
3.50 |
2.00 |
2.00 |
|
4 |
Calorific value of oil |
D |
k.cal/litre |
10181 |
10181 |
10000 |
9400 |
|
5 |
Calorific value of
coal |
E |
k.cal/kg |
4239 |
4239 |
4019 |
4077 |
|
6 |
Overall heat |
F
= (A x B) |
G.cal |
4451700 |
3852000 |
24026675 |
14024800 |
|
7 |
Heat from oil |
G
= (A x C x D) / 1000 |
G.cal |
31805 |
45753 |
192213 |
105466 |
|
8 |
Heat from coal |
H
= (F-G) |
G.cal |
4419895 |
3806247 |
23834462 |
13919334 |
|
9 |
Oil Consumption |
I=(Gx1000)/D |
KL |
3124.00 |
4494.00 |
19221.34 |
11219.84 |
|
10 |
Transit loss of coal |
J |
% |
2.00 |
2.00 |
2.00 |
2.00 |
|
11 |
Total Coal Consumption excluding transit loss |
K=(H*1000)/E |
MT |
1042792 |
898013 |
5930180 |
3414221 |
|
12 |
Quantity of PANAM coal |
L |
MT |
601019 |
494051 |
2452406 |
2635682 |
|
13 |
Quantity of coal other than PANAM coal excluding transit
loss. |
M=K-L |
MT |
441773 |
403962 |
3477774 |
778539 |
|
14 |
Quantity of coal
other than PANAM coal including transit loss |
N=M/(1-J) |
MT |
450789 |
412206 |
3548749 |
794427 |
|
15 |
Total Quantity of coal required |
O=L+N |
MT |
1051808 |
906257 |
6001155 |
3430109 |
|
16 |
Price of Coal without transit loss |
P |
Rs.
/ T |
2414.50 |
2414.50 |
2462.60 |
2488.20 |
|
17 |
Price of Oil |
Q |
Rs./KL |
28297 |
28297 |
30712 |
28347 |
|
20 |
Total cost of oil |
R=Q
x I / 107 |
Rs.crore |
8.84 |
12.72 |
59.03 |
31.80 |
|
21 |
Cost of coal |
S=O
x P/107 |
Rs.crore |
253.96 |
218.82 |
1477.84 |
853.48 |
|
22 |
Total Fuel cost |
T=
R+S |
Rs.crore |
262.80 |
231.54 |
1536.87 |
885.28 |
2916.49 |
* Quantity of Panam coal where not given for different units of a plant
has been considered on pro-rata basis of generation.
The Commission,
thus, approves the fuel cost at Rs. 2916.49 crore
for gross generation of 18067 MUs for the year 2008-09.
2.8.
Power Purchase Cost
2.8.1.
The Commission, in its Tariff
Order for the year 2008-09, approved a cost of Rs. 4186.33 crore for purchase of 15381 MUs (gross). In review, the
Commission revised it to Rs. 4414.59 crore for the
purchase of 13307 MUs (gross), inclusive of 4.71% external losses.
2.8.2.
The actual
gross power purchase for the year 2008-09 now reported by the Board is 15587.42
MUs (gross) including unscheduled interchange (UI) of 483.07 MUs. The net power
purchase after accounting for external losses of 4.73% is 14851 MUs. The actual cost of power purchase for 2008-09
as per ARR 2010-11 is Rs. 5184.05
crore. The power purchase cost as per audited accounts for 2008-09 is also Rs.
5184.05 crore.
The Commission
observes that as per previous practice, requirement of power purchase at the
time of review is taken based only on the energy balance as determined in the
Tariff Order for the relevant year and approved accordingly. However, at the time of true up, the actual
quantum of power purchased has been allowed since it has been obtained by the
Board and supplied to the consumers of different categories.
Going by the same practice, the Commission thus
approves a cost of Rs.5184.05 crore for purchase of 14851 MUs net.
2.9.
Expenses Disapproved by the
Commission
2.9.1.
Expenses disapproved on account of higher T&D
losses: As discussed in para 2.3, the Board has under
achieved the T&D loss target approved by the Commission. As per Tariff
Regulations, the entire loss on account of failure to achieve T&D targets
set by the Commission is to be borne by the licensee. As brought out in para 2.6, T&D loss
level higher than that approved by the Commission has resulted in increased
power purchase to the extent of 1249 MUs (net), the
pro-rata cost of which based on power purchase cost approved in para 2.8 works
out to Rs.435.99 (5184.05 x 1249 / 14851)
crore.
The Commission, therefore, disapproves expenses to the
extent of Rs. 435.99 crore on accounts of higher T&D losses.
The effect of this is reflected at Sr. No.
14(i) of Table 2.14.
2.9.2.
Expenses
disapproved for lower thermal generation: The Commission
has noted that there is lower thermal generation to the extent of 492 MUs gross
(486 MUs net) and consequent increase in power purchase as discussed in para
2.4.1. The station wise decrease in gross generation compared to the generation
approved in the Tariff Order of 2009-10 is 275 (9886-9611) MUs for GGSTP and 517
(6127-5610) MUs for GHTP. For GNDTP there is an increase in generation of 300
(2546-2846) MUs.
The net saving in fuel cost
for different stations corresponding to this variation in generation based on
cost now approved works out to Rs.73.36 crore as given in Table 2.9.
Table 2.9: Decrease in Fuel Cost due to lower Generation for 2008-09
Sr.
No. |
Station |
Now
Approved by the Commission |
Increase
/ Decrease in fuel cost due to more/less generation |
||
Generation
(MUs) |
Fuel
Cost (Rs. crore) |
Increase
/Decrease in Generation (+/-) (MUs) |
Increase
/Decrease
in Fuel Cost (+/-) (Rs.
crore) |
||
1 |
GNDTP |
2846 |
495 |
(+)
300 |
(+)
52.18 |
2 |
GGSTP |
9611 |
1537 |
(-)
275 |
(-)
43.98 |
3 |
GHTP |
5610 |
885 |
(-)
517 |
(-)
81.56 |
4 |
Total |
18067 |
2917 |
(-)
492 |
(-)
73.36 |
The increase in power
purchase on account of lower generation is 486 MUs net. The cost of 486 MUs
(net) based on power purchase cost approved as per para 2.8 works out to Rs.169.65
crore ((5184.05/14851)*486). Accordingly, the net increase in power purchase
cost is Rs.96.29 (169.65 - 73.36) crore.
The Commission therefore determines an amount of
Rs.96.29 crore as disincentive on account of lower thermal generation.
The effect of this is
reflected at Sr. No. 14 (ii) of Table 2.14.
2.10 Employee Cost
2.10.1 The Commission, in its Tariff Order for the
year 2008-09, approved employee cost of Rs.1773.55 crore. In the review, in
accordance with PSERC Tariff Regulations, the Commission revised the employee
cost to Rs.1768.19 crore by applying the wholesale price index (WPI) of 8.41%
to the approved employee cost of Rs.1631.02 crore for 2007-08.
2.10.2 The employee cost, as per
audited accounts of the Board for 2008-09, is Rs.2319.86 crore (gross). The net
cost after reducing capitalization amount of Rs.117.82 crore is Rs.2202.04
crore. However, as per audit notes, the employee cost has been understated by
Rs.6.58 crore and taking that into account, the employee cost of the Board
comes to Rs.2208.62 crore.
2.10.3 The Commission also finds no justification in
allowing additional employee cost on account of assets added during the year as
laid down in Regulation 28 (6) of the PSERC Tariff Regulations. It is relevant
to mention here that as per the Appellate Tribunal’s Judgement dated May 26,
2006, employee cost of the Board will remain capped until performance
parameters of the Board improve.
2.10.4 The Commission is, thus, only to adjust
employee cost for 2008-09 in accordance with the annual variations in the rate
of WPI as on 1st April of the year. In line with the principle
adopted in the past, average increase in WPI of 8.41% in the year 2008-09 is
considered to allow the employee cost. The Commission, therefore, retains the
employee cost of Rs.1768.19 crore by allowing an increase of 8.41% over the
approved employee cost of Rs.1631.02 crore for the year 2007-08.
The
Commission, thus, approves the employee cost of Rs.1768.19 crore for the year
2008-09.
2.11 Repairs and Maintenance (R&M) Expenses
2.11.1 The
Commission approved R&M expenses of Rs. 323.19 crore in its Tariff Order of
2008-09. In the review, the R&M expenses were revised to Rs. 339.56 crore,
allowing
·
an increase of 8.41% in WPI over the R&M expenses
approved for the year 2007-08 and
·
R&M expenses for the additional assets of Rs.1914.67
crore approved as added during 2008-09, assuming these remained in use for six
months in the year.
2.11.2 R&M
expenses as per the audited accounts of the Board for the year 2008-09 are Rs.
341.78 crore. This figure is inclusive of operating expenses of Rs. 21.17 crore
as discussed in Para 2.7.2. Reducing capitalized expenses of Rs.3.24 crore, the
actual R&M cost for the year 2008-09, works out to Rs. 338.54 crore.
However, as per audit notes, these expenses have been understated to the extent
of Rs.3.16 crore. Thus, the actual R&M expenses for the year 2008-09 work
out to Rs.341.70 crore.
2.11.3 The PSERC
Tariff Regulations provide for allowing an increase in O&M expenses (which
include R&M expenses) in proportion to the increase in WPI. The base
R&M expenses of Rs. 296.00 (286.91+9.09) crore are being considered to
allow these expenses for the year 2008-09 which include approved R&M expenses of Rs.286.91 crore for
2007-08 and an amount of Rs.9.09 crore being R & M expenses allowed for six
months on fixed assets added during the year.
Thus, after allowing an average WPI increase of 8.41% for the year over
the base R&M expenses of Rs. 296 crore, the allowable R&M expenses work
out to Rs.320.89 crore for assets of Rs. 16424.12 crore as on April 1, 2008, as
determined by the Commission after taking into account audit notes.
2.11.4 According to Regulation 28 (6) of the PSERC
Tariff Regulations, R&M expenses for fixed assets added during the year are
to be considered on pro-rata basis from the date of commissioning. As per
audited accounts for 2008-09, fixed assets added during the year are valued at
Rs. 2011.03 crore. However, as per audit notes, these fixed assets are
understated by Rs. 54.97 crore. Taking the audit notes into account, the value
of the assets added during the year works out to Rs. 2066 crore. The dates of
commissioning of these assets are neither available in the accounts nor in the ARR
of the Board. Therefore, R&M expenses for the assets added are being
considered assuming that these assets remained in service of the Board for six
months on an average during 2008-09. The average percentage rate of R&M
expenses of Rs.320.89 crore for assets of Rs.16424.12 crore works out to 1.95%
(320.89/16424.12*100). By applying the average rate of 1.95%, the allowable
R&M expenses for the additional fixed assets added during the year work out
to Rs.20.14 crore. Thus, allowable R&M expenses for the year 2008-09 work
out to Rs.341.03 (320.89 + 20.14) crore.
The Commission,
accordingly, allows R&M expenses of Rs. 341.03 crore for the year
2008-09.
2.12 Administration and General (A & G) Expenses
2.12.1 In the
Tariff Order of 2008-09, the Commission approved A&G expenses of Rs.79.29
crore. In the review of 2008-09, these expenses were approved at Rs.71.93 crore
being net of capitalization of Rs.23.43 crore as claimed by the Board.
2.12.2 As per the
audited accounts of the Board, the A&G expenses for the year 2008-09 are
Rs.90.73 crore (gross). The net expenses for the year work out to Rs.70.96
crore after reducing capitalized expenses of Rs.19.77 crore.
2.12.3
Regulation 28 of the PSERC Tariff Regulations provides for allowing annual
increase in the approved O&M expenses (which include A&G expenses)
based on average increase in WPI over the year. The base A&G expenses for
2008-09 work out to Rs.68.07 (66.00 + 2.07) crore which include approved
A&G expenses of Rs.66.00 crore for 2007-08 and an amount of Rs.2.07 crore
being A&G expenses allowed for six months on fixed assets added during the
year. Accordingly, after allowing average WPI increase of 8.41% over the base
A&G expenses of Rs.68.07 crore, expenses allowable for 2008-09 work out to
Rs. 73.79 crore for assets valued at Rs.16424.12 crore as on 1st
April, 2008. The average percentage rate of allowable A&G expenses works
out to 0.45% i.e. (73.79/16424.12*100).
2.12.4 The Commission adopts the same principle for
allowing A&G expenses for fixed assets added during the year as has been
applied to R&M expenses.
Accordingly, the average rate of 0.45% is applied to the additional
assets of Rs. 2066 crore added during 2008-09 for arriving at allowable A&G
expenses of Rs.4.65 crore. Thus, allowable A&G expenses for the year
work out to Rs. 78.44 (73.79 + 4.65) crore for the year 2008-09 against which
the Board has claimed expenses of Rs.70.96 crore on actual basis.
The Commission, therefore, approves A&G expenses of
Rs.70.96 crore as claimed by the Board for the year 2008-09.
2.13 Depreciation
Charges
2.13.1 The Commission
approved depreciation charges of Rs.783.34 crore for the year 2008-09 in the
Tariff Order of 2008-09. In the review, these charges were revised to Rs.721.50
crore based on the revised estimates of the Board.
2.13.2 In its ARR for 2010-11, the
Board has claimed depreciation charges of Rs.693.73 crore which are net of
capitalized depreciation of Rs.2.41 crore for the year 2008-09. The Commission
has noted that the depreciation charges as per audited accounts are also at
Rs.693.73 crore (net) as claimed by the Board. However, as per audit notes on
the Annual Accounts for 2008-09, these expenses have been understated by an
amount of Rs.8.62 crore and taking this into account, depreciation charges for
the year work out to Rs.702.35 crore for 2008-09.
The Commission,
therefore, approves depreciation charges of Rs.702.35
crore for the year 2008-09.
2.14 Interest
and Finance Charges
2.14.1 The
Commission approved net Interest
and Finance charges
of Rs.767.48 crore in its Tariff Order for the year 2008-09 after
disallowing interest cost of Rs.100 crore of the Board and Rs.209.32 crore of
interest on GoP loans on account of diversion of capital funds for revenue
purposes. In the review of 2008-09, the Interest & Finance charges were
revised to Rs. 537.66 crore.
2.14.2 The amount of Interest and Finance charges
(gross) as per audited accounts for 2008-09 is Rs.1446.12 crore. After reducing
capitalized interest charges of Rs.251.53 crore, the net interest charges come
to Rs.1194.59 crore. The Interest and Finance charges claimed by the Board and
as allowed by the Commission are detailed in Table 2.10 below.
Table 2.10: Interest
and Finance charges
(Rs. crore)
Sr. No. |
Description |
Interest as depicted in accounts |
Interest payable on GoP loans but
not accounted for in accounts for 2008-09 |
Amount disallowed by Commission |
Amount allowed by Commission |
1. |
Interest
on institutional loans taken by the Board |
602.48 |
- |
6.78 |
595.70 |
2. |
Interest
on loans taken for Rajpura Thermal Plant (RTP) being privately developed on
BOO basis |
16.25 |
- |
16.25 |
0.00 |
3. |
Interest
payable on GoP loans |
0 |
219.19 |
- |
219.19 |
4. |
Interest
for short-term loans of Rs.1362 crs. |
151.05 |
- |
- |
151.05 |
5. |
Interest on GPF |
112.65 |
- |
- |
112.65 |
6. |
Lease rentals |
0.04 |
- |
- |
0.04 |
7. |
i)
Interest to consumers on security deposits ii)
Short provision for interest on security deposits as per audit notes not
accounted for by the Board in accounts. |
70.48 70.61 |
- |
- |
141.09 |
8. |
Discount
to consumers for advance payment of bills |
52.45 |
- |
52.45 |
0 |
9. |
Sub Total |
1076.01 |
219.19 |
75.48 |
1219.72 |
10. |
Interest
on Working Capital Loans (569.54-151.05) |
418.49 |
- |
313.54 |
104.95 |
11. |
Finance
charges for capital loans |
22.23 |
- |
17.04 |
5.19 |
12. |
Total (9+10+11) |
1516.73 |
219.19 |
406.06 |
1329.86 |
13. |
Less capitalization |
251.53 |
- |
- |
251.53 |
14. |
Net
Interest & Finance charges (12-13) |
1265.20 |
219.19 |
406.06 |
1078.33 |
15. |
Less
interest disallowed on account of diversion of capital funds |
|
|
|
262.34 |
16. |
Interest allowed (14-15) |
|
|
|
815.99 |
The interest and
finance charges allowable to the Board are discussed in the ensuing paragraphs.
2.14.3 The
Commission, in its Tariff Order, approved an Investment Plan of Rs.2000 crore
for the year 2008-09. In the review, the Commission revised the Investment Plan
to Rs.1475.28 crore after deducting investment of Rs.442.62 crore and Rs.6.61
crore on Rajpura and Gidderbaha Thermal Plants which are being/proposed to be developed
on BOO basis. The net requirement of loans of Rs.1117.18 crore was approved
after adjustment of consumers’ contribution of Rs.215.58 crore (considered at
previous year’s level) and incentive grant of Rs.142.52 crore received under
(Rs. crore)
Sr. No. |
Particulars |
Loans
o/s as on 31.3.08 |
Receipt
of loans |
Repayment
of loans |
Loans
o/s as on 31.3.09 |
Amount
of interest |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
1 |
As per data furnished by Board (other than GoP
loans & WCL) |
5960.53 |
1292.63 |
921.50 |
6331.66 |
602.48 |
2 |
Approved by Commission (other than GoP loans
& WCL) |
5960.53 |
1154.34 |
921.50 |
6193.37 |
595.70 |
2.14.4 As
per the audited accounts of the Board, GoP loans of Rs.1712.91 crore as on March
31, 2008 decreased to Rs.1660.52 crore by March 31, 2009. Interest payable on
the loan amount works out to Rs.219.19 crore for 2008-09 by applying an average
rate of interest of 13.20%. The Commission observes that the Board has claimed
‘Nil’ interest payable on GoP loans in the audited accounts for the year
2008-09. The Commission, however, allows interest of Rs.219.19 crore for GoP
loans on accrual basis in order to arrive at the gross interest payable in
2008-09. However, after adjusting Rs.162.34 crore disallowed on account of
diversion of capital funds for revenue purposes as discussed in Para 2.14.11,
an amount of Rs.56.85 crore is determined as interest payable on GoP loans.
This amount will be further adjusted as discussed in Para 2.14.12.
2.14.5 In the
Tariff Order of 2009-10, the Commission allowed an interest of Rs.140.15 crore
on short term loans of Rs.1362.00 crore raised to replace GoP loans recalled by
the Govt. The Commission now approves interest of Rs.151.05 crore on short term
borrowings by applying an interest rate of 11.09 % on the basis of the interest
claim for short term borrowings reflected in the audited accounts.
2.14.6. In the ARR of 2008-09, the Board
claimed interest on GPF amounting to Rs.105 crore which was allowed by the
Commission. In the review, the Commission revised these expenses to Rs.115
crore as claimed by the Board. However, in the ARR of 2010-11, the Board has
claimed these expenses at Rs.112.65 crore which is the same as reflected in the
Board’s audited accounts. This being a statutory expenditure, the interest
charges on this account are, accordingly allowed.
2.14.7. The Commission approved lease
rentals of Rs.0.05 crore in the Tariff Order of 2008-09 which were retained in
the review in Tariff Order of 2009-10. In the ARR of 2010-11, the Board has
claimed lease rentals of Rs.0.04 crore which tallies with the audited accounts
of the Board for 2008-09. The Commission, accordingly, approves this
expenditure on actual basis.
2.14.8. In the Tariff Order of 2008-09, the Commission
allowed interest on consumers’ security at Rs.4.20 crore as claimed by the
Board. In the review, these charges were revised to Rs.4.97 crore after
allowing 5% increase in the actual interest of Rs.4.73 crore paid to consumers
in the previous year. In the ARR of 2010-11, the Board has claimed an interest
of Rs.70.48 crore being interest paid to the consumers on their security
deposits. The Commission observes that as per audit notes to the audited
accounts of 2008-09, these expenses have been understated by Rs.70.61 crore due
to short provision of interest on security deposits. After taking into account
the audit notes, the interest payable to the consumers will work out to
Rs.141.09 crore for the year 2008-09. The expenditure being obligatory is
approved at Rs.141.09 crore.
The Commission observes that the Board has claimed
an amount of Rs.52.45 crore under ‘Interest & Finance Charges’, being
discounts allowed to the consumers for advance payment of bills. However, as
this amount is being utilized by the Board for its revenue expenditure, its
requirement of working capital is set off to this extent. Therefore, the
Commission does not approve any interest on this account.
2.14.9 In the
Tariff Order of 2008-09, the Commission approved interest of Rs.98.64 crore as
interest on normative working capital of Rs.758.75 crore for the year. This
expenditure was revised to Rs.97.73 crore on normative working capital of
Rs.796.76 crore. In the ARR of 2010-11, the Board has claimed interest of
Rs.569.54 crore for the working capital which is inclusive of interest on loans
of Rs.1362 crore as allowed in para 2.14.5. This interest has been computed on
the actual quantum of working capital loans availed of by the Board. However,
the allowable working capital loans admissible on normative basis are brought
out in Table 2.12 below:
Table 2.12: Working Capital Requirement
Sr. No. |
Particulars |
Rs. crore |
1 |
One month Fuel Cost |
243.04 |
2 |
One month Power Purchase Cost |
432.00 |
3 |
One month Employee cost |
147.35 |
4 |
One month A&G cost |
5.91 |
5 |
One month R&M Expenses |
28.42 |
6 |
Total Working Capital Required |
856.72 |
The allowable
working capital loans work out to Rs.856.72 crore on normative basis on which
interest charges comes to Rs.104.95 crore at an interest rate of 12.25% being
the PLR of SBI as on April 2008. Accordingly, interest charges of Rs.104.95
crore are allowed.
2.14.10 In the Tariff Order of 2008-09, the Commission
approved finance charges of Rs.11.75 crore at the rate of 0.66% for allowable
loans of Rs.1781 crore. In the review, the Commission approved these charges at
Rs.5.03 crore by applying the rate of 0.45% as claimed by the Board for
allowable loans of Rs.1117.18 crore against Rs.13.52 crore claimed by the Board
for fresh borrowings of Rs.2989.30 crore. In the ARR for the year 2010-11, the
Board has claimed finance charges of Rs.22.23 crore which is the same as
depicted in the audited accounts for loans of Rs.1292.63 crore actually availed
of by the Board. The Board has not provided any justification for claiming
higher finance charges. Therefore, the Commission considers it appropriate to
apply the rate of 0.45% for allowable loans of Rs.1154.34 crore for the year
2008-09 and allows finance charges of Rs.5.19 crore.
2.14.11 The Commission has also re-determined the
diversion of capital funds for revenue purposes at Rs.2624.76 crore based on
the Board’s audited accounts for the year 2008-09 as given in Table 2.13:
Table 2.13: Diversion of
Capital Funds
(Rs. crore)
Sl. No. |
Item |
Year 2008-09 |
1 |
Net
Fixed Block |
10385.69* |
2 |
Works
in progress (WIP) during the year |
3004.72** |
3 |
Inventory
at Const. Stores |
176.53 |
4 |
Total
(1+2+3) |
13566.94 |
5 |
Less
Consumers’ contribution and grants & subsidy towards cost of capital
assets |
3270.41 |
6 |
Balance
capital base (4-5) |
10296.53 |
7 |
Requirement
of Loans +equity |
10296.53 |
8 |
Average
GoP Loans for the year |
1686.71 |
9 |
Other
loans (other than NPL & TSPL) |
7049.15 |
10 |
Equity |
2946.11 |
11 |
SBI
Bonds (Debt servicing charges taken over by GoP) |
637.35 |
12 |
GPF
utilized by Board ( Accumulations in GPF Less amount invested) |
601.97 |
13 |
Actual
Loans + Equity (8+9+10+11+12) |
12921.29 |
14 |
Less
capital base |
10296.53 |
15 |
Amount
diverted (13-14) |
2624.76 |
16 |
Less Bonds for which debt servicing under-taken by
GoP |
637.35 |
17 |
Balance diverted amount (15-16) |
1987.41 |
18 |
Interest effect @13.20% (Average rate of
interest on GoP loans) |
262.34 |
*This figure is worked out as Rs.10385.69
(10339.34+54.97-8.62) crore after taking into account the effect of audit notes
i.e (I) assets were understated by Rs.54.97 crore (II) depreciation was
understated by Rs.8.62 crore.
**This figure is worked out as Rs.3004.72(3264.57-204.88-54.97)
crore after taking into account the audit notes i.e i) assets of Rs.204.88
crore relate to Irrigation Department of
Shahpur Kandi ii)Completed assets of
Rs.54.97 crore are shown as WIP.
The diversion of capital
funds for revenue purposes for the year works out to Rs.2624.76 crore out of
which debt servicing of SBI bonds of Rs.637.35 crore will have no effect on
interest charges of the Board as the same has been taken over by the GoP.
Therefore, the net diverted amount carrying interest liability is Rs.1987.41
crore on which interest works out to Rs.262.34 crore at an average rate of
13.20% (being average rate of interest on GoP loans of Rs.1660.52 crore as on
March 31, 2009). This interest of Rs.262.34 crore is being disallowed from the
interest cost on account of diversion of capital funds for 2008-09.
In this regard, the
Commission retains its decision to disallow interest cost of Rs.100 crore of
the Board on account of deficiencies in its working and the balance of
Rs.162.34 crore is to the account of the GoP. The latter amount is being
adjusted against interest of Rs.219.19 crore payable on GoP loans as determined
in para 2.14.4.
2.14.12 The Commission, in para 2.14.13 of the Tariff
Order of 2009-10, determined the actual interest on GoP loans paid in excess to
the Govt. by the Board at Rs.333.08 (289.92 + 43.16) crore for the years
2006-07 and 2007-08. In its Order dated September 13, 2007, the Commission had
held that the interest paid in excess by the Board is to be refunded by the
GoP. As discussed in para 2.14.4 and
2.14.11 an amount of Rs.56.85 crore is determined as payable by the Board to
GoP. Adjusting this amount, the net sum payable by the GoP to the Board works
out to Rs.276.23 (333.08-56.85) crore. This amount is being carried forward to
para 2.16.4.
2.14.13 In the ARR of 2008-09, the Board had claimed an
amount of Rs.82.40 crore as interest capitalized against which the Commission
allowed Rs.22.29 crore as per practice for capitalization of interest invariably followed by the Commission. In the
review, the Commission allowed capitalization charges at Rs.135.77 crore as
claimed by the Board. In the ARR of 2010-11, the Board has claimed
capitalization of interest charges of Rs.251.53 crore which is the same as per
the Board’s audited accounts. Accordingly, the Commission approves
capitalization of interest charges of Rs.251.53 crore for the year 2008-09.
Accordingly, the Commission approves the net Interest
and Finance charges of Rs.815.99 crore for the year 2008-09.
2.15 Return on Equity
2.15.1 In the Tariff Order of 2008-09, the Commission, in
accordance with Regulation 25 of the PSERC Tariff Regulations, approved a Return
on Equity of Rs.412.46 crore calculated at 14% on the equity of Rs.2946.11
crore as on April 01, 2008. In the review, the Commission retained Return on Equity
at Rs.412.46 crore for that year. As per the audited accounts of the Board for
the year 2008-09, GoP equity in the Board remained unchanged at Rs.2946.11
crore.
Accordingly, the
Commission retains Return on Equity at Rs.412.46 crore for the year 2008-09 as
approved earlier.
2.16 Subsidy and Other Amounts Payable by the GoP
2.16.1 As
per the audited accounts for the year 2008-09, total subsidy of Rs.2601.73 crore has been paid by the GoP to the Board.
2.16.2 The subsidy payable by the
GoP is now trued up as under:
·
AP Consumption: The Commission has accepted AP consumption
at 8395 MUs on which revenue @ 240 paise per unit works out to Rs.2014.80
crore. The consumers were not billed any amount on this account. Thus,
Rs.2014.80 crore (exclusive of meter rentals and service charges of Rs.7.00
crore) was payable by the GoP as AP subsidy.
·
Scheduled Castes (SC) Domestic Supply (DS) Consumers: The
Commission notes that as per the decision of the GoP, Scheduled Castes DS
consumers with a connected load of upto 1000 watts will be given free power
upto 200 units per month. The Board has claimed subsidy of Rs.225.28 crore
besides meter rentals and service charges of Rs.18.34 crore on this account.
Accordingly, the Commission approves subsidy of Rs.243.62 crore under this
head.
·
Non-SC Below Poverty Line (BPL) Consumers: The GoP had also decided to give free supply of power
upto 200 units per month to Non-SC BPL DS consumers with connected load upto
1000 watts. The Board has claimed subsidy of Rs.1.98 crore inclusive of meter
rentals and service charges of Rs. 0.11 crore on this account. The Commission
approves the same.
2.16.3 On the above basis, total subsidy payable by the GoP for the year
2008-09 works out to Rs.2267.40 (2014.80 +7.00+243.62 +1.98) crore.
2.16.4 The subsidy payable to the Board for 2008-09 was paid by the GoP
in a staggered manner, not in keeping with the methodology specified by the
Commission for making such payment. The Board has claimed that it had to meet
its revenue requirements by taking short term loans at an average interest rate
of 11.09% (effective short term rate based on the Board’s ARR) from the open
market to cover for deficit on account of late payment of subsidy. The
Commission, in the review of 2008-09, had determined interest of Rs.42.98 crore
for delayed payment of subsidy. The amount of interest has now been re-worked
to Rs.55.05 crore on payable subsidy of Rs.2267.40 crore.
In para 2.16.2 of the Tariff Order of 2009-10 (true up of 2007-08), the
Commission determined total arrears of subsidy payable by the GoP upto the year
2007-08 as Rs.97.83 crore.
Thus, subsidy of Rs.2420.28 (2267.40+55.05+97.83) crore is
now determined as payable by the GoP to the Board for the year 2008-09 against
subsidy of Rs.2601.73 crore already paid, resulting in excess payment of
subsidy of Rs.181.45 crore. This is being carried forward to para 5.4.
However, the GoP will be liable to pay an amount of Rs.
276.23 crore as discussed in para 2.14.12. This is being carried forward to
para 3.15.
2.17 Prior Period Expenses
In its ARR for 2010-11, the Board has claimed prior period expenses of
Rs.107.60 crore being payments pertaining to the previous years but made during
the year 2008-09. As per the audited accounts, the prior period expenses are
Rs.107.60 crore inclusive of Rs.3.08 crore on account of employee cost. The
Board has not intimated the period to which the expenses on account of employee
cost pertain. These expenses are disallowed assuming that these expenses
pertain to the period during which the employee cost of the Board remained
capped.
Accordingly, the
Commission approves prior period expenses of Rs.104.52 crore for the year 2008-09.
2.18 Non-Tariff Income
2.18.1 The
Commission approved non-tariff income of Rs.412.00 crore for the year 2008-09 in the Tariff Order of 2008-09. This
was increased to Rs.442.57 crore in the Tariff Order of 2009-10 based on
revised estimates of the Board.
2.18.2 As per the
audited accounts of the Board for the year 2008-09, the ‘other income’ of the Board is Rs.303.03 crore.
Besides this, an amount of Rs.104.38 crore is deducted from the sale of power
and counted towards non-tariff income of the Board [as per para 2.19.2].
Accordingly, as per audited accounts of the Board, non tariff income works out
to Rs.407.41 crore. In addition, the
subsidy of Rs.7.00 crore for AP consumers and Rs.18.45 crore for SC and Non-SC
BPL Domestic Supply consumers has been received from the GoP on account of
meter rentals and service charges which also forms part of non tariff income
for 2008-09. Taking these receipts into account, the non-tariff income of the
Board for the year amounts to Rs.432.86 (303.03+104.38+7.00+18.45) crore.
2.18.3 The Commission, in para 5.9 of the Tariff Order
of 2009-10, had directed the Board to report the final outcome of the audit notes
on the Board’s accounts for the year 2007-08 regarding its miscellaneous income failing which the non tariff income of the Board would be
re-determined on the basis of those audit notes. As per the audit notes, the
Misc income was understated to the extent of Rs.151.10 crore and comprised of
(i) deposits of Rs.103.89 crore outstanding for more than 3 years, (ii)
deposits of Rs.0.97 crore received against burnt meters and (iii) advance of Rs.46.24 crore received
against sale of scrap. During processing of the ARR, the Board had intimated that
out of Rs.103.89 crore, Rs.60.00 crore relates to receipts on account of
Central Plan Assistance and efforts were being made to identify the details of
the remaining amount. However, the Board
has not submitted any clarification regarding the remaining amount of Rs.43.89
crore under the head ‘deposits outstanding’. Regarding deposits on account of
burnt meters, the Board has submitted that it is a continuing process and due
credit has been reflected in the Suspense Schedule for the year 2008-09.
Similar treatment has been given to the advance against sale of scrap. This
explanation of the Board is not acceptable as any credit to the Suspense
account is made pending final credit in the books of account. Further
clarification sought on this account did not yield any results. Therefore, the
Commission is left with no alternative but to treat the balance amount of
Rs.91.10 (43.89+0.97+46.24) crore as understated miscellaneous income of the
Board and count the same towards non-tariff income of the Board for the year
2008-09. Accordingly, the non tariff income of the Board for the year is
determined at Rs.523.96 (432.86+91.10) crore.
The Commission
accordingly, approves Non-Tariff Income at Rs. 523.96 crore for the year
2008-09.
2.19
Revenue from Sale of Power
2.19.1 The
Commission approved the revenue from tariff at Rs.11231.11 crore (including GoP subsidy of Rs.2602 crore) in
the Tariff Order for the year 2008-09. In the review, the revenue from sale of
power was revised to Rs.11139.38 crore inclusive of GoP subsidy.
2.19.2 In the audited accounts for 2008-09, the
revenue actually received from sale of power is Rs.9010.34 crore excluding GoP
subsidy. This revenue includes non-tariff income of Rs.104.38 crore on account
of meter rentals and service charges (Rs.81.47 crore), wheeling charges
(Rs.2.07 crore) and miscellaneous charges other than peak load exemption
charges (Rs.20.84 crore). These receipts have been accounted for in the
non-tariff income and are hence deducted from the head ‘revenue from sale of
power’. Therefore, net revenue from sale of power works out to Rs.8905.96
(9010.34-104.38) crore. Besides, the Board had received subsidy of Rs. 2601.73
crore and Rs.0.08 crore on account of revenue grant. However, subsidy of
Rs.2267.40 crore determined as payable for 2008-09 in para 2.16 of this Tariff Order
includes an amount of Rs.25.45 crore related to meter rentals and service
charges which is a part of non-tariff income for the year. Accordingly, after
adding subsidy of Rs.2241.95 (2267.40-25.45) crore paid by the GoP to the
Board, total revenue from sale of power amounts to Rs.11147.91 crore.
The Commission,
therefore, approves the revenue from sale of power at Rs.11147.91 crore
for the year 2008-09.
2.20. Other Debits and Extraordinary Items
2.20.1 The audited accounts of the Board for the year 2008-09, show
‘other debits and extraordinary items’ at Rs.5.80 crore. However, as per audit notes,
these are understated by i) Rs.16.65 crore on account of loss on the
manufacture of PCC Poles shown as receivable ii) Rs.3.95 crore due to
non-charging of expenditure incurred on survey/feasibility study of projects,
which have not matured/sanctioned iii) Rs.4.65 crore due to wrong adjustment of
expenses incurred under liabilities for expenses iv) Rs.0.13 crore outstanding
against deceased employees and (v) Rs.1.93 crore outstanding in respect of idle
labour in TLSC divisions which were required to be written off. Accordingly,
the actual figure under this head works out to Rs.33.11
(5.80+16.65+3.95+4.65+0.13+1.93) crore.
The
Commission allows an expenditure of Rs.33.11 crore for the year 2008-09 on this account.
2.21 Fringe Benefit Tax (FBT)
The audited accounts of the Board
indicate that Rs.4.90 crore was paid as Fringe Benefit Tax (FBT) which is the
same as claimed by the Board in the ARR.
This
being a statutory payment, the Commission approves the amount of Rs.4.90 crore
for the year 2008-09.
2.22 True up of ARR for 2008-09
2.22.1 In view of the above analysis, the trued up revenue requirement
for the year 2008-09 is as per details given in Table 2.14.
Table 2.14:
Revenue Requirement
(Rs. crore)
Sr. No. |
Item of
Expense |
Approved
by Commission in T. O. for 2008-09 |
Approved
by Commission in T. O. for 2009-10 |
Actuals
as per Annual Accounts for 2008-09 |
Final
approval by Commission |
1 |
2 |
3 |
4 |
5 |
6 |
1 |
Cost of fuel |
2742.62 |
2978.85 |
3154.06 |
2916.49 |
2 |
Cost of power purchase |
4186.33 |
4414.59 |
5184.05 |
5184.05 |
3 |
Employee cost |
1773.55 |
1768.19 |
2202.04 |
1768.19 |
4 |
R&M expenses |
323.19 |
339.56 |
338.54 |
341.03 |
5 |
A&G Expenses |
79.29 |
71.93 |
70.96 |
70.96 |
6 |
Depreciation |
783.34 |
721.50 |
693.73 |
702.35 |
7 |
Interest & finance charges |
767.48 |
537.66 |
1194.59 |
815.99 |
8 |
Carrying cost of gap |
102.15 |
- |
|
|
9 |
Return on Equity @ 14% |
412.46 |
412.46 |
412.46 |
412.46 |
10 |
Prior period expenses |
|
|
107.60 |
104.52 |
11 |
Other Debits and Extraordinary
items |
|
|
5.80 |
33.11 |
12 |
Fringe Benefit Tax |
4.56 |
4.98 |
4.90 |
4.90 |
13 |
Total revenue requirement |
11174.97 |
11249.72 |
13368.73 |
12354.05 |
14 |
i) Less expenses disapproved
due to higher T&D loss ii) Less expenses disapproved
due to less generation |
|
|
|
435.99
96.29 |
iii)Add Additional incentive
for higher thermal generation in 2007-08* |
|
|
|
24.16 |
|
15 |
Revenue requirement |
11174.97 |
11249.72 |
13368.73 |
11845.93 |
16 |
Less: non tariff income |
412 |
442.57 |
407.42 |
523.96 |
17 |
Net revenue requirement |
10762.97 |
10807.15 |
12961.31 |
11321.97 |
18 |
Revenue from tariff |
11231.11 |
11139.38 |
11507.77 |
11147.91 |
19 |
Gap (surplus (+)/ deficit (-) |
468.14 |
332.23 |
|
(-)174.06 |
20 |
Gap (deficit (-) for the year
2007-08 |
(-)717.78 |
(-)803.31 |
|
(-)803.31 |
21 |
Total gap (deficit) (-) |
(-)249.64 |
(-)471.08 |
(-)1453.54 |
(-)977.37 |
22 |
Energy sales (MUs) |
32,632 |
30,892 |
32,627 |
31673 |
*As per Order dated
From the true up for the year 2008-09, it is noted that
there is a gap (deficit) of Rs.174.06 crore against a gap (surplus) of Rs.332.23 crore
determined earlier by the Commission in the review of 2008-09 in the Tariff
Order dated
Chapter 3
Review for the Year 2009-10
3.1 Background
3.1.1 The Tariff Order of the Commission for 2009-10 contained its
approvals of costs and revenue projections based on the Board’s estimates for
different items of costs to be incurred and revenue likely to accrue during the
year. The Board has, in its ARR for the year 2010-11, now furnished revised
estimates for 2009-10.
3.1.2 There are differences in certain items of costs as well as
revenues between the approvals granted by the Commission and the revised
estimates now furnished by the Board. The Commission considers it appropriate
and fair to re-visit and review the approvals granted by it in the Tariff Order
(2009-10) with reference to the revised estimates now made available by the
Board but without altering the principles and norms adopted earlier. These
matters are discussed in the succeeding paragraphs.
3.2 Energy Demand (Sales)
3.2.1 Metered Energy Sales
The Board
has re-estimated energy sales to metered categories for 2009-10 on the basis of
actuals for the first 6 months (April ‘09 to Sept ‘09) and by applying category
wise half yearly Cumulative Annual Growth Rate (CAGR) of the second half year
for the period 2005-06 to 2008-09, to the corresponding actual category wise
sales in the second half of 2008-09.
The
Commission has estimated sales to metered categories for 2009-10 on the basis
of actual sales for first 6 months of 2009-10 (April ‘09 to Sept ‘09) submitted
by the Board in its ARR petiton and by applying category wise half yearly CAGR
for the 3 year period from 2005-06 to 2008-09, to the corresponding actual
category wise sales during second half of 2008-09. As per last three year CAGR
of second half sales, two of the categories (medium supply and public lighting)
show a negative growth rate but the Commission has considered 0% growth rate as
the Board has not furnished any information on negative growth in respect of
these two categories. The Commission has worked out the estimated sales to
metered categories as 21092 MUs for the year 2009-10 (detailed in Table 3.1) as
against 21379 MUs projected by the Board.
Table 3.1: Estimated Energy Sales during 2009-10
(MUs)
Sr. No. |
Category |
Sales during 2nd Half of
05-06 (actual) |
Sales during 2nd Half of 08-09
(actual) |
3 year CAGR during 2nd
Half of 06 to 2nd Half of 09 |
Sales during 1st half of FY 09-10 |
Estimated sales during 2nd Half of
09-10 |
Estimated sales for 2009-10 (6+7) |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
1 |
Domestic |
2589 |
3335 |
8.81% |
3671 |
3629 |
7300 |
2 |
Non-Residential |
745 |
998 |
10.24% |
1078 |
1100 |
2178 |
3 |
Small
Power |
352 |
362 |
0.94% |
377 |
365 |
742 |
4 |
Medium
Supply |
806 |
732 |
-3.16% |
777 |
732 |
1509 |
5 |
Large
Supply |
3957 |
4329 |
3.04% |
4158 |
4461 |
8619 |
6 |
Public
Lighting |
67 |
66 |
-0.50% |
62 |
66 |
128 |
7 |
Bulk
Supply |
223 |
236 |
1.91% |
244 |
240 |
484 |
8 |
Railway
Traction |
52 |
57 |
3.11% |
73 |
59 |
132 |
9 |
Metered
|
8791 |
10115 |
|
10440* |
10652 |
21092 |
* Against 10438 projected by the Board
3.2.2 The
Commission has retained sales to common pool consumers at 302 MUs as indicated
by the Board as they are based on the actual figures of sales to common pool
for 2008-09. The Outside State sales projected by the Board in the ARR for
2010-11 as 1383 MUs have been subsequently revised to 297 MUs as furnished by
the Board in its letter dated January 28, 2010 due to change in accounting
procedure for sale/purchase of banking power from 2009-10. The Commission is of
the view that the change in accounting procedure can be considered from 2010-11
but for 2009-10 accepts the Outside state sales of 1383 MUs as projected by the
Board in the ARR.
The metered energy sales projected by the Board
during determination of ARR for the year 2009-10, those approved by the
Commission in the Tariff Order, the revised estimates furnished by the Board
and metered energy sales now approved by the Commission are given in Table 3.2.
Table 3.2: Metered Energy Sales - 2009-10
(MUs)
Sr. No. |
Category |
Projected by PSEB during determination of ARR 09-10 |
Approved by the Commission in T.O.
09-10 |
Revised Estimates of PSEB during
determination of ARR of 10-11 |
Approved by the Commission in
review |
1 |
2 |
3 |
4 |
5 |
6 |
1 |
Domestic |
7240 |
6960 |
7336 |
7300 |
2 |
Non-Residential |
2320 |
2145 |
2135 |
2178 |
3 |
Small
Power |
741 |
722 |
768 |
742 |
4 |
Medium
Supply |
1590 |
1522 |
1607 |
1509 |
5 |
Large
Supply |
9812 |
9278 |
8741 |
8619 |
6 |
Public
Lighting |
158 |
148 |
148 |
128 |
7 |
Bulk
Supply |
531 |
500 |
495 |
484 |
8 |
Railway
Traction |
118 |
123 |
149 |
132 |
9 |
Metered
sales (within State) |
22510 |
21398 |
21379 |
21092 |
10 |
Common
pool |
302 |
303 |
302 |
302 |
11 |
Outside
State sales |
1307 |
1307 |
297 |
1383 |
12 |
Total
(9+10+11) |
24119 |
23008 |
21978 |
22777 |
Metered sales of 21092 MUs within the state, common pool
sales of 302 MUs and Outside State sales of 1383 MUs are now approved by the
Commission as per details shown in Table 3.2.
3.2.3 AP Consumption
The Commission in its Tariff Order of 2009-10
approved AP consumption of 9814 MUs after applying a normative growth of 5%
twice over the consumption of 8902 MUs worked out by the Commission for the
year 2007-08 against 11699 MUs projected by the Board.
The Board, in its ARR for 2010-11, has given
revised estimates of AP consumption for 2009-10 based on the reported
consumption during the first half of 2009-10 and by applying the average CAGR
(7.87%) of the last three years for second half sales on the corresponding
reported sales of the second half of 2008-09 which works out to 10363 MUs.
The Commission has over the last several years been
attemnpting to fine-tune the methodology of computing agricultural consumption
with a view to ensuring that estimates are as accurate as possible. In that
context, the Commission had in the Tariff Order for 2009-10 directed the Board
to take the following specific measures:
a)
Monthly
division-wise consumption recorded by sample meters be made available directly
to the Commission by the agency undertaking this work.
b)
Furnish to the
Commission the following information, division-wise and on a monthly basis:
(i)
Data on the
load of each sample meter, initial and final meter readings, total connected
load of AP sample meters and total consumption recorded by sample meters.
(ii)
Details of
increase/decrease in sample meter loads alongwith total connected load of each
division.
(iii)
Data on actual
AP supply hours.
c)
Sample meter
readings in excess of what can possibly be consumed with the given supply hours
and connected load not to be taken into account for evaluation of AP factor and
division-wise details of such meters to be furnished every month.
d)
Faulty/non-functional
sample meters be replaced in a time bound manner and in no case these will
exceed 10% of the total sample meters in a division during any month of the
year.
e)
The size of
sample meters be gradually increased to 10% of the total number of AP
connections.
In compliance thereof, the Board has promised to
take suitable action with regard to (d) and (e) above. In respect of the
remaining, the action taken on their part is either incomplete or inconclusive.
Till these matters are finally addressed by the Board, the Commission would
find it difficult to rely entirely upon the results of the present methodology
adopted in computing agricultural consumption. Moreover, the Commission notes
that while the Board had in the ARR of 2009-10 projected AP consumption of
11699 MUs, the same has since been revised and reduced to 10363 MUs. The
Commission also observes that the methodology of arriving at the latest
projected AP consumption of 10363 MUs is to take consumption on the basis of
sample meter readings for the first 6 months of 2009-10 and then project a CAGR
of 7.87 % on the Board’s own figure of AP consumption in the second half of
2008-09. The Commission has already taken the view that AP consumption reported
by the Board for 2008-09 as a whole is on the higher side and the same has been
reduced by 10.20 % in the Tariff Order for 2009-10. Thus, the total figure of
AP consumption arrived at by the Board for 2009-10 based upon an obviously
erroneous methodology can not be accepted. In these circumstances, the
Commission is inclined to retain AP consumption of 9814 MUs as approved in the
last Tariff Order as there is no conclusive basis to revise earlier estimated
consumption as proposed by the Board in the current ARR.
3.3 Transmission and Distribution Losses
(T&D Losses)
The Board had projected T&D losses at 19.5% for
2009-10 which represented a reduction of 3.03% from losses of 22.53% for
2007-08 and 1.5% from the level of 21% for 2008-09, in its ARR for the year.
These losses for year 2007-08, 2008-09 and 2009-10 were based on AP consumption
of 10030 MUs, 9766 MUs and 11699 MUs respectively. The Commission in its
previous Tariff Order (2009-10) had decided to reduce AP consumption reported
by the Board by 11.25% and 10.20% for the years 2007-08 and 2008-09
respectively. On the basis of revised estimates of AP consumption, the T&D
losses for the years 2007-08 and 2008-09 were determined at 25.12% and 24.07%
respectively. After considering the issue of T&D losses in its entirety,
the Commission fixed T&D loss target for the year 2009-10 at 22%.
The Board in its ARR for 2010-11 has projected
revised estimates of T&D losses of 19.50% for 2009-10. This revised loss
level proposed by the Board does not take into account the revision of AP
consumption as considered by the Commission in the Tariff Order for 2009-10. If
the approach adopted by the Commission is to be considered, the revised T&D
losses for the year 2009-10 will work out to 22.18%.
The Commission finds no justification for reviewing
the T&D losses fixed in the Tariff Order of 2009-10 and thus, retains the
T&D loss level at 22.0% for the year 2009-10 as fixed earlier.
3.4 Energy Requirement
The
total energy requirement to meet the demand of the system is the sum of
estimated metered energy sales including common pool and Outside State sales,
estimated AP sales and T&D losses. The total energy requirement for 2009-10
projected during determination of ARR of 2009-10, approved by the Commission in
its Tariff Order and revised estimates finally furnished by the Board ( in the
ARR of 2010-11) including subsequent clarifications/amendments and now approved
by the Commission is given in Table 3.3.
Table 3.3:
Energy Requirement for the year 2009-10
(MUs)
Sr. No. |
Particulars |
Projected by PSEB during
determination of ARR 09-10 |
Approved by the Commission in T.O.
09-10 |
Revised Estimates by PSEB in ARR of
10-11 |
Now approved by the Commission |
1 |
2 |
3 |
4 |
5 |
6 |
1 |
Metered
Sales within the State |
22510 |
21398 |
21379 |
21092 |
2 |
Agriculture
Consumption |
11699 |
9814 |
10363 |
9814 |
3 |
Total
sales within State (1+2) |
34209 |
31212 |
31742 |
30906 |
4 |
Common
pool sales |
302 |
303 |
302 |
302 |
5 |
Outside
State sales |
1307 |
1307 |
297 |
1383 |
6 |
Total
sales |
35818 |
32822 |
32341 |
32591 |
7 |
T&D
Losses on item at Sr. No. (3) |
||||
(a) |
Percentage |
19.50% |
22% |
19.50% |
22% |
(b) |
MUs |
8287 |
8803 |
7689 |
8717 |
8 |
Total
energy input required |
44105 |
41625 |
40030 |
41308 |
The revised energy requirement for 2009-10 with T&D
loss of 22% is determined as 41308 MUs, which has to be met from the Board’s
own generation (thermal & hydel), share from BBMB, purchases from Central
Generating Stations and other sources.
3.5 PSEB’s Own Generation
3.5.1 Thermal Generation: The Board has in the
ARR for the year 2010-11 estimated the gross generation for 2009-10 based on
actual generation of the respective plants upto Sept. 2009 and estimating the
revised generation for the second half of 2009-10 on the basis of maintenance
schedule of the respective plants during the second half of 2009-10.
The Commission has, however, obtained the actual gross
generation of different stations for the year 2009-10 till the end of Feb, 2010.
The actual gross generation for the first eleven months of 2009-10 as supplid
by the Board vide letter dated 05.03.10 is summarized in Table 3.4(A) below:
Table 3.4(A): Gross Thermal Generation
from April 09 to Feb 2010
(MUs)
Station |
Period (April 09 to Feb 2010) |
GNDT Unit
I & II |
1417 |
GNDTP Unit
III & IV |
1147 |
GGSTP |
9246 |
GHTP Unit
I, II & III |
5124 |
GHTP Unit
IV |
1685 |
Total
Gross Generation |
18619 |
As the actual station-wsie generation for the eleven months of 2009-10 is
available with the Commission, the Commission decides to determine the gross
generation for the month of March, 2010 on prorata basis based on the basis of
actual gross generation for the first eleven months of 2009-10. The
station-wise generation projected by the Board during determination of ARR of
2009-10, generation approved by the Commission in its Tariff Order for that
year, revised estimates now supplied by the Board in its letter dated 5.3.2010
and the generation approved by the Commission is given in Table 3.4(B).
Table 3.4(B): Thermal Generation
2009-10
(MUs)
Sr. No. |
Station |
Projected by PSEB in ARR 2009-10 |
Approved by the Commission T.O.
2009-10 |
Revised Estimates by PSEB in ARR
2010-11 |
Now approved by the Commission |
||||
Gross |
Net |
Gross |
Net |
Gross |
Net |
Gross |
Net |
||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
1 (a) |
GNDTP Unit
I &II |
2330 |
2062 |
1580 |
1419 |
2702 |
2388 |
15464 |
1376 |
1 (b) |
GNDTP Unit
III & IV |
1221 |
1087 |
12514 |
1113 |
||||
2 |
GGSTP |
9200 |
8409 |
9966 |
9119 |
9564 |
8765 |
10086 |
9229 |
3 (a) |
GHTP,
Stage I |
3220 |
2930 |
6948 |
6323 |
73171 |
67002 |
74283 |
6760 |
3 (b) |
GHTP,
Stage II |
3504 |
3189 |
||||||
4 |
Total |
18254 |
16590 |
19715 |
17948 |
19583 |
17853 |
20311 |
18478 |
1.
Comprising of
5495 MUs by GHTP unit 1,2 & 3, 1247 MUs of infirm power by GHTP unit 4 and
575 MUs of post COD power from GHTP unit 4.
2.
Comprises of
5012 MUs by GHTP unit 1,2 & 3, 1165 MUs of infirm power by GHTP unit 4 and
523 MUs from GHTP unit 4.
3.
Comprises of 5590
MUs by GHTP unit 1,2 & 3 and 1838 MUs (including infirm power) from GHTP unit 4.
4.
Total
estimated generation of 2797 MUs proportioned against GNDTP unit 1&2 and
GNDTP unit 3&4 on the basis of ratio of actual generation for the period
April 09 to Feb 2010 for GNDTP unit 1&2 and GNDTP unit 3&4.
The Commission approves gross thermal generation for the year 2009-10 at 20311
MUs, against 19583 MUs projected by the Board in the ARR.
Auxiliary Consumption & Net
Generation
The plant-wise auxiliary consumption projected by
the Board during determination of ARR of 2009-10, auxiliary consumption
approved by Commission in the Tariff Order of that year, the revised figures
projected by the Board in the ARR of 2010-11 and the figures now approved by
the Commission are given in Table 3.4(C).
Table 3.4 (C): Auxiliary Consumption 2009-10
Sr. No. |
Station |
Projected by PSEB in ARR 2009-10 |
Approved by the Commission in T.O.
2009-10 |
Revised Estimates by PSEB in
ARR 2010-11 |
Now Approved by the Commission |
1 |
2 |
3 |
4 |
5 |
6 |
1 (a) |
GNDTP Unit
I & II |
11.50% |
10.22% |
11.64%* |
11.00% |
1 (b) |
GNDTP Unit
III & IV |
11.00% |
|||
2 |
GGSTP |
8.60% |
8.50% |
8.36%* |
8.50% |
3 (a) |
GHTP
Stage-I |
9.00% |
9.00% |
8.42%* |
9.00% |
3 (b) |
GHTP
Stage-II |
9.00% |
* Computation based on the actual data submitted
for first six months & projected for the remaining six months of 2009-10.
The Commission in its Tariff Order for 2009-10
approved auxiliary consumption for GGSTP and GHTP at 8.5% and 9% respectively
as per CERC norms. In case of GNDTP, the Commission approved auxiliary
consumption at 10.22% for Unit I & II and 11% for Unit III & IV of
GNDTP. However, as discussed in para 2.4.1 of this Order, the auxiliary
consumption for all the four units of GNDTP has been approved at 11%. The
revised estimates of auxiliary consumption reported by the Board are on the
higher side in case of GNDTP and are on lower side in case of GGSTP and GHTP,
when compared with the levels approved by the Commission. The Commission is
inclined to continue adaptation of normative auxiliary consumption for GGSTP
and GHTP as approved in the Tariff Order of 2009-10 and also approves
auxuiliary consumption of 11% in case of all units of GNDTP.
Net thermal generation on this
basis has been worked out to 18478 MUs as shown in Table 3.4(B).
3.5.2
Hydel Generation: The Board
has submitted the revised estimates of hydel generation for 2009-10 in the ARR
of 2010-11. The Board has furnished the actual plant-wise hydel generation for
the first six months of the year 2009-10 (April 09 to Sept. 09) and for the
next six months (October 09 to March 10) has projected generation by RSD and
UBDC to be same as in 2004-05, considering the present reservoir position at
the start of the depletion period to be almost identical to that prevailing during
2004-05 in case of the RSD reservoir. For Shanan and ASHP, the availability has
been projected based on last three years average for the corresponding months.
The revised availability (net) from BBMB and Common Pool share has been
projected at 3689 and 302 MUs respectively, which has been computed by taking
into consideration the actual availability till Sept 09. The external losses
for the BBMB energy (excluding Common Pool share) has been considered by the
Board at 3.70%.
The Commission has obtained from the Board, the actual gross generation
of different hydel stations including BBMB share for the period April 2009 to
January 2010 and tentative generation for the month of February 2010. However,
gross generation for the months of February 2010 and March 2010 has been
determined on the basis of actual achieved by the Board for the month of
January 2010. The gross generation for the period April 2009 to March 2010,
computed in this manner, is almost the same as the projections made by the
Board. Accordingly, gross generation for hydel stations including BBMB share
has been accepted by the Commission as per the projections submitted by the
Board in the ARR.
The station-wise generation projected by the Board during determination
of ARR for 2009-10, generation approved by the Commission in its Tariff Order,
the revised estimates now submitted by the Board in the ARR for 2010-11 and generation
now approved by the Commission is given
in Table 3.5.
Table 3.5: Hydel
Generation - 2009-10
(MUs)
Sr.No. |
Hydel generation |
Projected by PSEB in ARR of 2009-10 |
Approved by Commission in Tariff
Order 2009-10 |
RE by PSEB in ARR 2010-11 |
Now accepted by the Commission |
1 |
2 |
3 |
4 |
5 |
6 |
1 |
Shanan |
515 |
515 |
496 |
496 |
2 (a) |
UBDC Phase
1 |
448 |
448 |
381 |
381 |
2 (b) |
UBDC Phase II |
||||
3 |
RSD |
1744 |
1743 |
1200 |
1200 |
4 |
MHP |
1257 |
1257 |
793 |
793 |
5 |
ASHP |
695 |
695 |
6031 |
603 |
6 |
Micro
Hydel |
7 |
7 |
9 |
9 |
7 (a) |
Gross
Own Hydel |
4665 |
4665 |
34822 |
3482 |
7 (b) |
Net Own
Hydel |
4604 |
4494 |
3436 3 |
3346 4 |
|
|
|
|
|
|
8 |
PSEB
Share from BBMB |
|
|
|
|
(a) |
Gross
Share |
4323 |
4323 |
36895 |
36895 |
(b) |
Add Common
pool share |
302 |
303 |
302 |
302 |
(c) |
Less
External losses |
171 |
171 |
|
|
(d) |
Net
Share from BBMB |
4454 |
4455 |
3991 |
3991 |
|
|
|
|
|
|
9 |
Total
Net Hydel (Own + BBMB) |
9058 |
8949 |
7427 |
7337 |
Notes
1.
Net of 5.75 MUs diverted to BBMB from
ASHP as a result of diversion of water from NHC to AHC upto Sept 09.
2.
Includes Royalty to HP in Shanan and HP
share in RSD @ 4.6%.
3.
Net of Auxiliary consumption of 7 MUs
and transformation losses of 39 MUs.
4.
Own generation is
· Net of auxiliary consumption @ 0.5% for RSD generation of 1200 MUs and UBDC
stage-1 generation of 157 MUs (calculated on pro-rata basis taking actual
generation by UBDC stage-1 and UBDC
stage - 2 in 2008-09) having static exciters and @ 0.2% for others (11
MUs).
· Net of transformation losses @ 0.5% (17 MUs).
· HP share (free) in RSD @ 4.6% (55 MUs).
· Royalty to HP in Shanan (53 MUs).
5.
Net of external transmission loss.
The Commission, thus, approves
revised hydel generation for the year 2009-10 at 3346 MUs (net) from own hydel
stations and 3991 MUs (net) (including common pool share) as share from BBMB as
shown in Table 3.5.
3.6 Power Purchase
3.6.1 To meet the energy demand, the Board projected power purchase at
18457 MUs (net) during determination of ARR for 2009-10. The Commission in its
Tariff Order for the year approved power purchase at 14728 MUs (net).
3.6.2
The Board has furnished revised estimates of
power purchase for 2009-10 at 15836 MUs (net) in its ARR for 2010-11 and
further revised to 14750 MUs during presentation on 11.02.2010. The revised
total energy requirement during 2009-10 including common pool share and Outside
State sales and T&D losses is determined as 41308 MUs as discussed in para 3.4. The energy
available from the Board’s own generating stations including its share from
BBMB is 25815 (18478 MUs thermal generation and 7337 MUs of hydel generation
including share from BBMB) as approved in para 3.5. The balance energy
requirement works out to 15493 MUs (net) which has to be met through purchases
from Central Generating Stations and other sources.
The Commission, accordingly, approves the revised power purchase at 15493
MUs (net) for 2009-10.
3.7 Energy Balance
3.7.1 Details of energy requirement and energy
availability projected during determination of ARR for 2009-10, approved by the
Commission in its Tariff Order, revised estimates supplied by the Board in the
ARR of 2010-11 including subsequent clarifications/amendments and now approved
by the Commission is given in Table 3.6.
Table 3.6: Energy Balance – 2009-10
(MUs)
Sr. No. |
Particulars |
Projected by PSEB during
determination of ARR 09-10 |
Approved by the Commission in T.O.
09-10 |
Revised Estimates by PSEB in ARR of
10-11 |
Now approved by the Commission |
1 |
2 |
3 |
4 |
5 |
6 |
A)
Energy Requirement |
|||||
1 |
Metered
Sales |
22,510 |
21,398 |
21,379 |
21,092 |
2 |
Sales to
AP consumers |
11,699 |
9,814 |
10,363 |
9,814 |
3 |
Total
Sales within the State |
34,209 |
31,212 |
31,742 |
30,906 |
4 |
Loss
percentage |
19.50% |
22.00% |
19.50% |
22.00% |
5 |
T&D losses |
8,287 |
8,803 |
7,689 |
8,717 |
6 |
Sales to
Common pool consumers |
302 |
303 |
302 |
302 |
7 |
Outside
State Sales |
1307 |
1307 |
297 |
1,383 |
8 |
Total
requirement |
44,105 |
41,625 |
40,030 |
41,308 |
B)
Energy Available |
|||||
9 |
Own
generation (Ex-bus) |
||||
10 |
Thermal |
16,590 |
17,948 |
17,853 |
18,478 |
11 |
Hydro |
4,604 |
4,494 |
3,436 |
7,337 |
12 |
Share from
BBMB (incl.share of common pool consumers |
4,454 |
4,455 |
3,991 |
|
13 |
Purchase
net |
18,457 |
14,728 |
14,750 |
15,493 |
14 |
Total
Available |
44,105 |
41,625 |
40,030 |
41,308 |
3.8 Fuel Cost
3.8.1 The
Commission in its Tariff Order of the year 2009-10 approved fuel cost of Rs.3195.93 crore for gross thermal
generation of 19715 MUs. The Board in its ARR of 2010-11 has revised estimates
of fuel cost to Rs 3501.75 crore for gross thermal generation of 19583 MUs based
on estimated calorific value and price of coal / oil for 2009-10 as given in
Table 3.7. The fuel cost worked out by the
Board is based on the actual parameters for the first six months and the
projected values for the remaining six months of the year 2009-10.
The Board, while projecting the
price of coal for 2009-10, has considered escalation of 5% on account of coal
price hike by Coal India Limited for estimating the coal cost for the second
half of the year. Further, the Board while projecting the price of oil for
2009-10, has considered escalation of 10% on the actual average price for the
respective generating stations during the first half of 2009-10.
Table 3.7:
Calorific Value and Price of Coal and Oil as submitted
by the Board for 2009-10
Sr.No. |
Station |
Gross Calorific value of
coal (kCal/Kg) |
Calorific Value of Oil
(Kcal/Ltr) |
Price of Oil (Rs/KL) |
Price of coal (Rs/MT) |
Transit loss |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
1 |
GNDTP |
4102 (H1) 4100 (H2) |
10000 |
24081 (H1) 26489 (H2) |
2517 (H1) 2643 (H2) |
1.84%(H1) 2.00% (H2) |
2 |
GGSTP |
3979 (H1) 4015 (H2) |
10000 |
22613 (H1) 24874 (H2) |
2652 (H1) 2785 (H2) |
0.94% (H1) 2.20% (H2) |
3 |
GHTP (Unit 1 to 3) |
4023 (H1) 4025 (H2) |
9400 |
29167 (H1) 32084 (H2) |
2589 (H1) 2718 (H2) |
1.22% (H1) 2.00% (H2) |
4 |
GHTP (Unit 4) |
4025 (H2) |
9400 |
33000 (H2) |
2800 (H2) |
2.00% (H2) |
H1: April 09 to Sep 09 & H2:
Oct 09 to Mar 10
Fuel cost being the major item of
expense, the Commission thought it prudent to get the same verified. The
calorific value of the coal & oil and price of the coal & oil as
validated and accepted by the Commission are indicated in Table 3.8. These
values are based on data ending Sept. 09.
Table 3.8:
Calorific Value and Price of Coal and Oil as accepted
by the Commission for 2009-10
Sr. No. |
Station |
Gross
Calorific value of coal (kCal/Kg) |
Calorific
Value of Oil (K.cal/Ltr) |
Price
of Oil (Rs/KL) |
Price
of coal including transit loss (Rs./MT) |
Transit
loss |
Price
of coal excluding trasit loss |
1 |
|
1 |
2 |
3 |
4 |
5 |
6 |
1 |
GNDTP |
4102 |
10000 |
24081 |
2517 |
1.84% |
2471 |
2 |
GGSTP |
3979 |
10000 |
22613 |
2652 |
0.74 *% |
2633 |
3 |
GHTP |
4023 |
9400 |
29167 |
2589 |
1.22% |
2558 |
* Upto Oct 2009
3.8.2
The Commission has also taken into
account the coal quantity received from PANAM (Board’s captive coal mine) as
submitted by the Board. The price of the coal and corresponding calorific
values given by the Board (Table 3.7) and those validated by the Commission
(Table 3.8) are weighted average values of coal, including PANAM coal.
3.8.3
The gross generation considered
in the estimation of fuel cost is 20311 MUs which includes 1247 MUs of infirm
power generated during trial runs of GHTP Unit IV. The fuel cost for different
stations corresponding to generation now approved has been worked out in table
3.9 below, based on the parameters adopted by the Commission in its Tariff
Order of 2009-10 and considering the price and calorific value of coal and oil
as validated and accepted by the Commission.
3.8.4
No
transit loss has been allowed for PANAM coal while working out fuel cost as
prices according to the contract are on F.O.R. destination basis. In case of coal other than PANAM coal,
transit loss of 2% has been allowed by the Commission.
Table 3.9: Fuel Cost – 2009-10
Sr. No. |
Item |
Derivation |
Unit |
Approved Fuel Cost 2009-10 |
||||
GNDTP (I&II) |
GNDTP (III&IV) |
GGSTP |
GHTP |
Total |
||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
1 |
Generation |
A |
MU |
1546 |
1251 |
10086 |
7428 |
20311 |
2 |
Heat Rate |
B |
k.cal/kWh Generated |
2825 |
3000 |
2500 |
2500 |
|
3 |
Specific
oil consumption |
C |
Milli litre/kwh |
1.00 |
3.50 |
1.00 |
1.00 |
|
4 |
Calorific
value of oil |
D |
k.cal/litre |
10000 |
10000 |
10000 |
9400 |
|
5 |
Calorific
value of coal |
E |
k.cal/kg |
4102 |
4102 |
3979 |
4023 |
|
6 |
Overall
heat |
F = (A x B) |
G.cal |
4367450 |
3752905 |
25215641 |
18570075 |
|
7 |
Heat from
oil |
G = (A x C x D) / 1000 |
G.cal |
15460 |
43784 |
100863 |
69823 |
|
8 |
Heat
from coal |
H = (F-G) |
G.cal |
4351990 |
3709121 |
25114778 |
18500251 |
|
9 |
Oil
Consumption |
I=(Gx1000)/D |
KL |
1546.00 |
4378.39 |
10086.26 |
7428.03 |
|
10 |
Transit
loss of coal |
J |
% |
2 |
2 |
2 |
2 |
|
11 |
Total Coal
Consumption excluding transit loss |
K=(H*1000)/E |
MT |
1060943 |
904223 |
6311578 |
4598484 |
|
12 |
Quantity
of PANAM coal |
L |
MT |
690283 * |
558552 * |
2559355 |
2900000 |
13 |
Quantity
of coal other than PANAM coal excluding transit loss. |
M=K-L |
MT |
370661 |
345670 |
3752223 |
1698484 |
|
14 |
Quantity
of coal other than PANAM coal
including transit loss |
N=M/(1-J) |
MT |
378225 |
352725 |
3828799 |
1733146 |
|
15 |
Total
Quantity of coal required |
O=L+N |
MT |
1068508 |
911277 |
6388154 |
4633146 |
|
16 |
Price of
Coal |
P |
Rs. / MT |
2471 |
2471 |
2633 |
2558 |
|
17 |
Price of
Oil |
Q |
Rs./KL |
24081 |
24081 |
22613 |
29167 |
|
20 |
Total cost
of oil |
R=Q x I / 107 |
Rs.crore |
3.72 |
10.54 |
22.81 |
21.67 |
|
21 |
Cost of
coal |
S=O x P/107 |
Rs.crore |
263.99 |
225.15 |
1681.72 |
1184.98 |
|
22 |
Total
Fuel cost |
T= R+S |
Rs.crore |
267.71 |
235.69 |
1704.53 |
1206.65 |
3414.58 |
23 |
Cost of
Genration Per unit |
T/A |
Paise Per unit |
173 |
188 |
169 |
162 |
|
* The total
quantity of PANAM coal has been apportioned between GNDTP 1 & 2 and GNDTP 3
& 4 on the basis of approved generation for 2009-10.
The Commission, therefore,
approves the revised fuel cost at Rs. 3414.58 crore for a generation of 20311
MUs.
3.9 Power Purchase Cost
3.9.1
The Commission in its Tariff Order of
2009-10 approved a cost of Rs. 4746.59 crore for purchase of 15456 MUs (gross)
while the Board has in its ARR for the year 2010-11 given revised estimates of
Rs. 5746 crore for purchase of 16818 MUs (gross). Subsequently, the Board in
its letter dated Jan 28, 2010 has submitted revised power purchase cost because
of correction in Outside State sale, according to which Rs. 4999.37 crore has
been projected for power purchase of 15613 MUs (gross). The Board has estimated
the revised power purchase cost for 2009-10 based on the first six months
actual cost of Rs. 3121.06 crore for 9905 MUs and estimated cost of Rs. 1878.31
crore for estimated power purchase of 5708 MUs during second half of 2009-10.
3.9.2
As discussed in para 3.6, the
requirement of 15493 (net) is to be met through purchases from Central
Generating Stations and other sources. The transmission loss external to the
Board’s system has to be added to arrive at the quantum of gross energy to be
so purchased. The Board has stated that the actual external losses in the first
six months of the year are 4.84%. For the full year, the Board has assumed the
external losses as 5.48% to compute the power purchase cost.
The actual
external transmission losses incurred by the Board during 2008-09 were 4.73%. The
Commission, therefore, decides to allow external losses @ 4.73% which were
actually incurred by the Board in 2008-09. After adding 4.73% losses, the gross
energy required to be purchased works out to 16262 MUs (15493 MUs + external
losses of 769 MUs).
The
Commission decides to accept the power purchase cost of Rs. 3121.06 crore
incurred by the Board for the purchase of 9905 MUs during the first six months
of 2009-10. Further, the Commission notes that the Board has purchased 2471 MUs
at a cost of Rs. 727.59 crore during the period from Oct 2009 to Dec 2009. The
Commission decides to determine the power purchase cost for the balance
requirement of 6357 MUs (16262-9905) on prorata basis based on the actual cost
incurred by the Board for the period Oct 2009 to Dec 2009 of 2009-10, Accordingly,
the prorata amount for purchase of 6357 MUs works out to Rs. 1871.79 crore. Therefore,
the total power purchase cost for 2009-10 woks out to Rs. 4992.85 crore.
The
Commisison in its Tariff Order for the year 2009-10 had limited the cost of
power purchase from traders to an average rate of 621.24 paise per unit. It had
also been decided that the cost of power purchased from traders in excess of
the approved quantum of 1073 MUs will be admissible only at an average rate of
realization per unit of 402.46 paise.
The Board in
its ARR has shown purchase of 1731 MUs from the traders during the first six
months of 2009-10 at an average rate of 609.35 paise per unit, whereas the
Commission had allowed 1073 MUs for the full year in the Tariff Order for 2009-10.
Since the Tariff Order for 2009-10 was issued in the month of Sep 2009, the
Commission does not consider it fair to penalize the Board for the purchase of
an additional quantum of 658 (1731-1073) MUs from the traders during the first
six months of 2009-10. However, the Commision takes note of the purchase of an
additional 82.8 MUs by the Board from the traders during Oct. 2009 to Dec. 2009
at an average rate of 675.60 paise per unit and only allows a rate of 402.46
paise per unit therefor. The additional cost (Rs. 22.62 crore) incurred by the
Board for purchase of 82.8 MUs at the excess rate of 273.14 (675.60-402.46) paise
per unit is disallowed.
The
Commission in its Order 2009-10 has also decided not to allow additional UI
surcharge leviable under CERC’s UI Regulations for overdrawal of power when
frequency is below 49.2 Hz. The Board in its letter dated 28.01.10 has
intimated the additional amount payable for UI drawal below frequency 49.2 Hz
for the period from April 09 to Nov. 09 as Rs. 13.84 crore. Since the Tariff
Order for 2009-10 was issued in the month of Sep 2009, therefore, the
Commission decides not to penalize the Board for the UI drawal below frequency
49.2 Hz during the first six months of 2009-10 and has disallowed the surcharge
paid on UI drawal amounting to Rs. 58.35 lac for the months of Oct. 2009 &
Nov. 2009.
The Commission, therefore,
approves the revised power purchase cost of Rs. 4969.65 (4992.85 - 22.62-
0.5835) crore for the now determined purchase of 16262 MUs gross.
3.9.3
The Commission had in
its tariff Order of 2009-10 mentioned that any change in fuel cost from the
level approved by the Commission would be passed on to the consumers as Fuel
Cost Adjustment (FCA). The Board filed petitions (17/2009 & 24/ 2009) for
approval of FCA for the first and second quarters of 2009-10. The petiton for
the first quarter was dismissed being belated, and the petiton for the second
quarter was pending for want of information from the Board. The Commission
observes since the variable cost of fuel has been validated upto Sep, 2009 and
the power purchase cost has been given on the basis of actual power purchase
cost for the first six months of 2009-10, the FCA petitions may be deemed to be
disposed off accordingly.
3.10 Employee Cost
3.10.1 In the ARR of 2009-10, the Board claimed employee cost of
Rs.3454.68 crore for 2009-10. The Commission, in its Tariff Order for 2009-10,
worked out the employee cost in accordance with the amended provisions of the
Tariff Regulations at Rs.2113.36 crore inclusive of Rs.737.43 crore towards
terminal benefits. However, the Commission restricted the employee cost to
Rs.1856.60 crore as per past practice, holding that extra employee cost in line
with the amended regulations would be allowed only when the roadmap for revising
staff strength of the Board, on the basis of the on-going manpower study, is
made available.
3.10.2
In the ARR of 2010-11, the Board projected employee cost of
Rs.2746.73 crore net of capitalization of Rs.120.00 crore. This is inclusive of
Rs.300 crore on account of pay revision for the period August 2009 to March
2010. The Board submitted revised employee cost for 2009-10 taking into account
the decision of the GoP in Circular No 9/1/2010-2PP/572 dated 27.01.2010
whereby retirement was deferred for the period 22.01.2010 to 31.12.2010. The details are tabulated below:
Table 3.10: Employee cost projected
by the Board
(Rs. crore)
Sr. No |
Particulars |
As per ARR |
Revised Estimates |
1 |
Basic
Pay |
1162.65 |
|
2 |
Overtime |
11.52 |
|
3 |
Dearness
Allowance |
459.04 |
|
4 |
Fixed
medical Allowance |
44.45 |
|
5 |
Other
Allowances |
186.49 |
|
6 |
Bonus/
Generation Incentive |
90.86 |
|
7 |
Medical
Expenses Reimbursement |
13.03 |
|
8 |
Workman's
compensation |
0.17 |
0.15 |
|
Total
(1 to 8) |
1968.21 |
1986.68 |
|
Terminal
Benefits |
|
|
9 |
Earned
Leave Encashment |
73.93 |
64.19 |
10 |
Gratuity |
109.99 |
95.41 |
11 |
Commutation
of Pension |
0 |
0 |
12 |
Ex-gratia |
0 |
0 |
13 |
BBMB
share |
70.92 |
70.92 |
|
Total
(9 to 13) |
254.84 |
230.52 |
|
Pension
Payments |
|
|
14 |
Basic
Pension |
561.71 |
555.28 |
15 |
Dearness
pension |
0 |
0 |
16 |
Dearness
Allowance |
0 |
0 |
17 |
Any
other expense |
81.97 |
81 |
|
Total |
643.68 |
636.28 |
|
Total
Expenses |
2866.73 |
2853.48 |
Less: |
Amount
capitalised |
120 |
119.43 |
|
Net
Employee Cost |
2746.73 |
2734.05 |
3.10.3
The
Commission notes that the above mentioned circular of the GoP has been quashed
by the Hon’ble Punjab & Haryana High Court in its Order dated 29.03.2010.
Consequent upon this Order, the GoP/Board retired employees due for retirement
in the period January 22, 2010 to March 31, 2010 and also retained the
retirement age at 58 years. However, the cost pertaining to terminal benefits
of such employees will arise in the year 2010-2011 and is therefore being
considered in Chapter 4 of the Tariff Order.
3.10.4
The
amended provisions of the PSERC Tariff Regulations provide for determination of
employee cost in two parts:
·
Terminal benefits including BBMB share on actual basis.
·
Increase in other expenses limited to average increase in
Wholesale Price Index.
As per revised estimates, the Board has claimed net
employee cost of Rs.2734.05 crore for 2009-10 inclusive of terminal benefits of
Rs.866.80 crore. These terminal benefits include impact of pay revision and are
allowable on actual basis.
As per amended regulations, increase in other employee
cost is to be limited to average WPI increase. However, the average annual
increase in WPI for 2009-10 is not available and the data for the first 9
months (April ’09 to December ’09) shows an average WPI increase of less than
2%. The Commission considers the 9 month average increase in WPI of 2% or less
as unusual, being attributable to worldwide recession. In such a situation it deems
it prudent to allow an adhoc increase of 5% for working out enhancement in
other employee cost for 2009-10. Applying this increase to the base figure of
Rs.1310.41 crore which was the other employee cost determined for 2008-09 in
the previous Tariff Order, would result in such cost increasing to Rs.1375.93
crore. Thus, allowable expenses as per amended regulations work out to
Rs.2242.73 (866.80+1375.93) crore.
3.10.5
The
Commission also observes that the Board claimed Rs.250 crore on account of pay
revision (other than terminal/pension benefits) for the period (August 2009 to
March 2010) in terms of Regulation 28(8)(b) of the amended Tariff Regulations
which provides for consideration of any exceptional increase such as a pay
revision. However, the pay revision actually came into effect in November 2009
and the increased expenses on this account (November 2009 to 31st
March 2010) come to Rs.156.25 crore. This does not include enhancement of
terminal benefits as the same is allowed in full by the Commission in para
3.10.4 above. However, the Commission observes that the additional amount of
Rs.156.25 crore has been based on the total employee expenses being actually
incurred by the Board. On the other hand, the Commission has been determining
employee costs of the Board on a normative basis in accordance with its
Regulations and thus the increase because of pay revision has to be allowed on
the normative figure of employee cost and not on the actual as projected by the
Board. The Commission has taken into account the employee cost claimed by the
Board for the years 2007-08, 2008-09 and 2009-10 (projection) and the cost
allowed by the Commission in those years. It is noted that on an average for
all three years, the employee cost allowed by the Commission is 28.48% less
than the amount actually claimed by the Board. The Commission is, therefore, of
the view that the claim of the Board for an increased sum of Rs.156.25 crore
for pay revision during 2009-10 needs also to be reduced by 28.48%. A reduction
of this order amounts to Rs.44.50 crore and the allowable cost on this account
would be Rs.111.75 crore.
3.10.6
Based
on paras 3.10.4 and 3.10.5 given above, revised employee cost for the year
2009-10 comes to Rs.2354.48 (866.80+1375.93+111.75) crore. The Commission has
also to take into account its observations in the Tariff Order of 2009-10 when
employee cost which worked out to Rs.2113.36 crore as per the Commission’s
Regulations had been restricted to Rs.1856.60 crore keeping in view the Board’s
failure to draw up a road map for revising its staff strength. Unfortunately,
the same position holds good as of now. Accordingly, the Commission imposes a
cut of Rs.100 crore for the Board’s inability to decide upon this crucial
issue. The impact of this cut is being reflected in para 4.9.7 of this Tariff
Order.
The Commission,
accordingly, approves employee cost of Rs.2354.48 (2242.73+111.75) crore for
2009-10.
3.11 Repair and Maintenance
(R&M) Expenses
3.11.3 In the ARR of 2010-11, the Board has claimed R&M expenses of Rs.30.47 crore for fixed assets of Rs.3159.40 crore added during the year on a pro-rata basis from the date of commissioning. However, the Commission notes that the Board’s claim of additional fixed assets added in 2009-10 appears to be on the higher side as against the audited figures of the earlier years. The Commission, in its Tariff Order of 2004-05, directed the Board to maintain a Fixed Asset Register but despite that, the Board was unable to submit actual figures of addition in fixed assets when that information was sought while processing the ARR of 2010-11. The Board has also expressed its inability to provide information with regard to the date of commissioning of each asset on the plea that a large number of assets of different categories are added during the year. In the circumstances, the Commission determines additional fixed assets added in 2009-10 on the basis of the consolidated average annual increase of assets during the previous three years which comes to 7.81%. On this basis, the value of additional assets created in 2009-10 works out to Rs.1444.08 crore. These assets are considered to have remained in service of the Board for six months during the year. R&M expenses of Rs.379.23 crore allowable as per para 3.11.2 are 2.05% of the value of total assets of Rs.18490.12 crore. Applying the same percentage to additional assets of Rs.1444.08 crore created in 2009-10, the allowable expenses work out to Rs.14.80 crore. Total expenses allowable for assets of Rs.19934.20 (18490.12+1444.08) crore for the year, thus, comes to Rs. 394.03 (379.23+14.80) crore. The Board has, however, claimed Rs.385.93 crore only as R&M expenses and the same are allowed. The Commission will in future seek from the Board details of fixed assets added as well as written off during a particular year and the proformae for submission of ARR will be suitably amended accordingly.
The Commission, accordingly, approves R&M
expenses at Rs.385.93 crore for
2009-10 as claimed by the Board.
3.12 Administration and
General (A&G) Expenses
3.12.3 As per Regulation 28 (6) of the PSERC Tariff Regulations, A&G expenses are allowable for additional assets added during the previous year on a pro-rata basis from the date of commissioning of assets. As discussed in para 3.11.3, fixed assets approved to be added during the year are considered as having remained in service of the Board for six months on an average during the year. The average percentage rate of A&G expenses of Rs.78.96 crore for assets of Rs.18490.12 crore works out to 0.43% (78.96/18490.12*100) which when applied to the additional fixed assets of Rs.1444.08 crore, results in additional expenses of Rs.3.10 crore, assuming that these assets remained in service for six months. Thus, allowable A&G expenses for total assets of Rs.19934.20 (18490.12+1444.08) crore work out to Rs.82.06 (78.96+3.10) crore. The Board has, however, claimed Rs.75.95 crore as A&G expenses in the ARR of 2010-11.
The
Commission, therefore, allows A&G expenses at Rs.75.95 crore for 2009-10 as
claimed by the Board.
3.13 Depreciation Charges
Table 3.11: Depreciation charges
|
(Rs. crore) |
% Rate |
(Rs. crore) |
% Rate |
||
Item |
Assets as on |
Depreciation charges
for 2008-09 |
Assets as on |
Depreciation charges
for 2009-10 |
||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
Thermal |
3,020.44 |
137.22 |
4.543% |
4319.19 |
196.22 |
4.543% |
Hydro |
5,847.98 |
133.42 |
2.281% |
5957.44 |
135.89 |
2.281% |
Internal combustion |
2.68 |
0.00 |
0.00% |
2.68 |
0.00 |
0.00% |
Transmission |
1,965.69 |
96.01 |
4.884% |
2040.46 |
99.66 |
4.884% |
Distribution |
5,447.20 |
325.25 |
5.971% |
5975.25 |
356.78 |
5.971% |
Others |
140.13 |
1.83 |
1.306% |
195.10 |
2.55 |
1.306% |
Total |
16,424.12 |
693.73 |
|
18490.12 |
791.10 |
|
The Commission, accordingly, approves depreciation
charges of Rs.791.10 crore for 2009-10.
3.14 Interest and Finance Charges
3.14.1 In the ARR of
2009-10, the Board claimed Interest and Finance charges of Rs.1585.61 crore for
2009-10 against which the Commission approved an amount of Rs.1048.57 crore. In
the ARR of 2010-11, the Board has revised the net Interest and Finance charges
for 2009-10 to Rs.1624.54 crore inclusive of Finance charges of Rs.12.00 crore.
Details of the claim are given in Table 3.12.
Table 3.12: Interest & Finance Charges as claimed by the Board
(Rs.
crore)
Sr. No. |
Description |
Interest as depicted in ARR |
1 |
Interest on institutional
loans (inclusive of Rs.37.81 crore for loans taken for RTP) |
831.56 |
2 |
Interest on GoP
loans |
0.00 |
3 |
Interest on GPF |
115.00 |
4 |
Lease rentals |
0.02 |
5 |
Interest to
consumers |
164.21 |
6 |
Sub-total |
1110.79 |
7 |
Interest on WCL |
576.34 |
8 |
Discount to
consumers for advance payment |
0.24 |
9 |
Finance charges
for loans |
12.00 |
10 |
Total (6+7+8+9) |
1699.37 |
11 |
Less
capitalization |
74.83 |
12 |
Net Interest &
Finance charges (10-11) |
1624.54 |
The Interest & Finance charges
allowable to the Board are discussed in ensuing
paragraphs.
3.14.2 Investment
Plan
The Commission, in its Tariff Order
of 2009-10, approved an Investment Plan of Rs.2000 crore. In the ARR of
2010-11, the Board submitted a revised investment plan of Rs.2724.55 crore for
2009-10. This includes an amount of Rs.2055.40 crore under the head
‘Transmission and Distribution’ which is inclusive of the requirements of the
APDRP scheme and Rs.194.03 crore for rural electrification (PMGY). The revised
investment plan, also includes a sum of Rs.2 crore for the Gidderbaha Thermal
Plant which is being developed on BOO basis which is deductible from the
Board’s Investment Plan for the year. However, the monthly expenditure report
submitted by the Board shows an expenditure of only Rs.1476.44 crore upto
January 31, 2010 and it appears unlikely that the Board would be able to effect
the proposed investment of Rs.2724.55 crore during the remaining two months of
2009-10. On the basis of capital
expenditure actually incurred upto the end of January, 2010, the proportionate
expenditure for the months of February and March, 2010 would be Rs.295.28
crore. Accordingly, the likely capital expenditure for the year 2009-10 would
be Rs.1771.72 (1476.44 + 295.28) crore. On this basis, the Commission approves
an investment plan of Rs.1800 crore for 2009-10. However, increase in actual
capital investment, if any, will be considered by the Commission during true
up.
The Board has also admitted to a
receipt of Rs.23.93 crore as a grant under APDRP on account of investment
component grant during 2009-10. In addition, the Board has received consumer’s
contribution of Rs.302.21 crore upto January 31, 2010 and after raising it
proportionately, estimated receipts on this account during the year work out to
Rs.362.65 crore. Accordingly, actual
loan requirement for this level of investment works out to Rs.1413.42
(1800-23.93-362.65) crore.
In the ARR of 2010-11, interest on
loans availed by the Board is depicted as Rs.831.56 crore inclusive of a
deductible amount of Rs.37.81 crore on account of a loan taken for the Rajpura
Thermal Plant which is being built privately on BOO basis leaving net interest
on borrowings of the Board to be Rs.793.75 (831.56-37.81) crore. However,
interest on allowable loans (other than WCL & GoP loans) is Rs.669.29 crore
as given in Table 3.13.
Table
3.13
(Rs. crore)
Sr. No. |
Particulars |
Loans as on 31.3.09 |
Receipt of loans |
Repayment of loans |
Loans as on 31.3.10 |
Amount of interest |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
1 |
As per data
furnished by Board (other than WCL & GoP loans) |
6331.66 |
3831.80 |
1072.31 |
9091.15 |
793.75 |
2 |
Approved by
Commission (other than WCL & GoP loans) |
6331.66 |
1413.42 |
1072.31 |
6672.77 |
669.29 |
3.14.3 Interest on GoP Loans
In the
Tariff Order of 2009-10, the Commission approved interest of Rs.225.48 crore on
GoP loans payable by the Board. However, this amount was adjusted against
interest disallowed on account of diversion of capital funds for revenue
purposes.
In the Annual
Statement of Accounts for 2008-09, outstanding GoP loans are shown at
Rs.1660.52 crore but as per GoP’s letter dated March 10, 2010, loans of
Rs.1140.43 crore have been adjusted by the GoP against the unpaid subsidy
leaving balance GoP loans of Rs.520.09 crore. On these loans, interest payable
works out to Rs.210.46 crore for the year 2009-10 by applying an average rate
of 13.20% per annum. Out of this interest, an amount of Rs.162.34 crore is
disallowed on account of diversion of capital funds for revenue purposes as discussed
in para 3.14.11. Thus, net interest payable on GoP loans works out to Rs.48.12
(210.46-162.34) crore.
3.14.4 Interest on loans taken to
replace re-called GoP Loans
As decided earlier in para 2.14.5 of
this Order, interest on loans of Rs.1362.00
crore raised to replace re-called GoP loans adjusted against unpaid subsidy by
the GoP is allowed at an average rate of 11.09% per annum. Thus, interest of
Rs.151.05 crore is approved on this account.
3.14.5 Interest
on G.P. Fund
The Board has claimed interest of
Rs.115 crore on GP Fund accumulations.
The interest of Rs.115 crore on G.P. Fund, being a statutory payment, is
allowed as claimed by the Board.
3.14.6 Lease
Rental
In the ARR of 2010-11, the Board has
claimed an amount of Rs. 0.02 crore as lease rental for the year 2009-10 which
the Commission allows.
3.14.7 Finance Charges
In its Tariff Order for 2009-10, the
Commission allowed finance charges of Rs.5.53 crore applying a rate of 0.31% on
the total borrowing requirement of Rs.1784.42 crore. As per revised estimates,
the Board has claimed Finance charges of Rs.12 crore for fresh borrowings of
Rs.3831.80 crore. The rate of Finance charges as per revised estimates of the
Board work out to 0.31% of the proposed borrowings. The Commission has,
however, approved net loan requirement of Rs.1413.42 crore in para 3.14.2
above. Applying a rate of 0.31% to the approved borrowings of Rs.1413.42 crore,
Finance charges are worked out at Rs.4.38 crore for 2009-10 which are allowed.
3.14.8 Interest on Consumers’ Security Deposits
In the Tariff Order of 2009-10,
interest on consumers’ deposits was not allowed for 2009-10 as the same was
payable after 31.03.10. In the ARR of 2010-11, the Board has claimed Rs.164.21
crore towards interest on consumers’ security deposits for 2009-10. As per
Annual Accounts of the Board, there is a balance of Rs.1266.00 crore as on 31st
March, 2009 under this head but the amount of security deposits as on 31st
March, 2010 is not available yet. Accordingly, interest of Rs.164.21 crore as
claimed by the Board is allowed.
3.14.9 Capitalization of
Interest and Finance Charges
The Commission, as per past practice,
capitalizes the interest excluding interest on working capital in the ratio of
net works in progress to total capital expenditure. Based on this principle and
the expenditure as reflected in the revised estimates, the Commission approves
capitalization of interest and finance charges of Rs.170.64 crore for 2009-10
against capitalization of Rs.57.82 crore approved in the Tariff Order of
2009-10.
3.14.10 Working Capital
In the Tariff Order for 2009-10, the Commission
approved working capital of Rs.1466.92 crore with interest cost of Rs.179.70
crore. In the revised estimates, the Board projected working capital loans of
Rs.1797.52 crore which was further revised by the Board to Rs.1735.27 crore.
The interest liability on this amount works out to Rs.212.57 crore.
The working capital requirement as per amended
Regulations works out to Rs.1640.39 crore and interest thereon comes to
Rs.200.95 crore by applying the short term PLR of 12.25% of the State Bank of
India as on April 2009. The details of working capital requirement as per
amended Regulation 30 and allowable interest are depicted in Table 3.14.
Table
3.14: Working capital requirement
(Rs. crore)
Particulars |
Approved by Commission |
Two months Fuel
Cost |
569.10 |
One month Power
Purchase Cost |
414.14 |
One month Employee
Cost |
196.21 |
One month
Administration and General Expenses |
6.33 |
One month Repair
and Maintenance Expenses |
32.16 |
Maintenance
spares @ 15% of O&M expenses (2354.48 EC+385.93 R&M + 75.95 A&G) |
422.45 |
Total requirement
for working capital |
1640.39 |
Interest Rate |
12.25% |
Interest |
200.95 |
Accordingly, the Commission
approves interest of Rs.200.95 crore on
working capital requirement for 2009-10.
3.14.11 Diversion of Capital Funds
The Commission, in para 2.14.11 of this
Order has re-determined the diversion of capital funds for revenue purposes at
Rs.2624.76 crore based on the Boards’ Audited Accounts of 2008-09. Diversion of
capital funds for the year 2009-10 is estimated on the same basis and will be
firmed up on the availability of audited accounts for that year. Of this
amount, Rs.1987.41 crore is the net diversion carrying interest bearing
liability. Interest @ 13.20% (being average rate of interest on GoP loans) on
diverted funds of Rs.1987.41 crore comes to Rs.262.34 crore for 2009-10. This
interest of Rs.262.34 crore on account of diversion of capital funds is being
disallowed from the interest cost for 2009-10.
In this regard, the Commission
retains its earlier decision to disallow interest cost of Rs.100 crore out of
this amount on account of deficiencies in the working of the Board and further
decides that the balance disallowance of interest of Rs.162.34 crore is to the
account of the GoP. Accordingly, after adjustment of this disallowed interest
against the interest of Rs.210.46 crore due on GoP loans worked out in para
3.14.3, net interest payable to the GoP works out to Rs.48.12 crore. This
amount is carried forward to para 3.15
In view of
the above, Interest and Finance charges for 2009-10 are allowed as per Table
3.15.
Table 3.15: Interest and Finance charges
(Rs. crore)
Sr. No. |
Particulars |
Interest
approved in Tariff Order 2009-10 |
Loans as
on 31.3.09 |
Receipt
of loans |
Repayment
of loans |
Loans as
on 31.3.10 |
Interest approved by Commission |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
1 |
Approved by Commission (other than WCL & GoP
loans) |
660.96 |
6331.66 |
1413.42 |
1072.31 |
6672.77 |
669.29 |
2 |
GoP loans |
225.48 |
1660.52 |
0 |
1140.43 |
520.09 |
210.46 |
3 |
Int. on loans taken to replace GoP loans of
Rs.1362 crore. |
163.44 |
|
|
|
|
151.05 |
4 |
Interest on GPF |
125.00 |
|
|
|
|
115.00 |
5 |
Lease rental |
0.03 |
|
|
|
|
0.02 |
6 |
Total (1+2+3+4+5) |
1174.91 |
7992.18 |
1413.42 |
2212.74 |
7192.86 |
1145.82 |
7 |
Add Finance charges |
5.53 |
|
|
|
|
4.38 |
8 |
Add Interest on Consumers’ security Deposits |
197.53 |
|
|
|
|
164.21 |
9 |
Total Gross Interest and Finance charges |
1377.97 |
|
|
|
|
1314.41 |
10 |
Less capitalization |
57.82 |
|
|
|
|
170.64 |
11 |
Net Interest and Finance
charges (9-10) |
1320.15 |
|
|
|
|
1143.77 |
12 |
Add: Interest on working capital |
179.70 |
|
|
|
|
200.95 |
13 |
Total Interest (11+12) |
1499.85 |
|
|
|
|
1344.72 |
14 |
Less: Disallowed on a/c of diversion: a) Board - Rs.100 crore b) GoP - Rs.162.34 crore |
451.28 |
|
|
|
|
262.34 |
15 |
Balance Interest and Finance charges (13-14) |
1048.57 |
|
|
|
|
1082.38 |
Accordingly, the Commission
approves net Interest and Finance charges of Rs.1082.38 crore for 2009-10.
3.15 Subsidy
3.15.1 In
para 6.4.1 of the Tariff Order of 2009-10, the requirement of subsidy for
2009-10 was determined at Rs.3144.25 crore for AP consumers, SC Domestic and
Non-SC BPL DS consumers. Other amounts recoverable from the GoP include
outstandings of Rs. 260.37 crore upto 2008-09 and Rs.125.80 crore which was the
unadjusted interest disallowed on account of diversion of capital funds in
2009-10. Thus, total subsidy and other amounts payable by the GoP to the Board
for 2009-10 were approved at Rs.3530.42 (3144.25+260.37+125.80) crore.
3.15.2 Based on the true-up of 2008-09,
subsidy amounting to Rs.2420.28 crore is determined as payable by the GoP to
the Board in 2008-09 while Rs.2601.73 crore has already been paid resulting in
excess payment of Rs.181.45 crore upto 2008-09. The amount of subsidy payable
by GoP to the Board for 2009-10 is revised as under:
·
AP Consumption: The Board in
its ARR petition for 2010-11 has claimed AP consumption for 2009-10 at 10363 MUs
on which subsidy payable is Rs.2953.34 crore. The Commission has, however,
revised AP consumption for 2009-10 to 9814 MUs as discussed in para 3.2.3 of
this Order. AP revenue for consumption of 9814 MUs @ 285 paise per kwh works
out to Rs.2796.99 crore, which is also in line with the subsidy approved in the
Tariff Order for 2009-10. The GoP has recently decided that AP consumers are to
be charged Rs.50/- BHP per month with effect from 22.1.2010 and that amount is
to be recovered bi-annually. The total connected load as on 1.1.2010 is
reported to be 9466448 BHP (7061970.21KW). On this basis, AP consumers are
liable to pay Rs.108.57 crore for the period 22.1.2010 to 31.3.2010 and
consequently, subsidy payable by the GoP during 2009-10 would be Rs.2688.42
crore. However, the additional revenue will only accrue to the Board during 2010-11 and as
such its effect will be considered in the next financial year. Accordingly, the
Commission retains AP subsidy payable by the GoP for 2009-10 at Rs.2796.99 crore.
·
Meter Rentals and Service Charges: There is no
change in the subsidy of Rs.8.00 crore determined in the Tariff Order for
2009-10 as payable on account of meter rentals and service charges in respect
of AP consumers.
·
Scheduled Castes (SC) Domestic Supply
(DS) consumers: The GoP had decided to supply free power upto
200 units to Scheduled Castes DS consumers with connected load upto 1000 watts
with effect from October 2, 2006. As per the ARR for 2010-11, the Board has
claimed subsidy amounting to Rs.335.62 crore (inclusive of meter rentals and
service charges of Rs.13.13 crore), which is in line with the subsidy approved
in the Tariff Order for 2009-10. However, as per decision dated 22.1.2010 of
the GoP, subsidy now allowable has been reduced to 100 units for consumers with
connected load of upto 1000 Watts to Scheduled Castes DS consumers. However, an
amount of Rs.335.62 crore is being considered for calculation of subsidy since
the details about the number of consumers in the category has not so far been
furnished by the Board. Therefore, the reduced subsidy as per GoP decision will
be considered in the true up on actual basis.
The Commission, thus, approves subsidy of
Rs.335.62 crore.
·
Non-SC Below Poverty Line (BPL) DS consumers: In addition,
the GoP had also decided to give free supply of power upto 200 units per month
to Non-SC BPL DS consumers with connected load of upto 1000 watts with effect
from December 1, 2006. The amount of subsidy claimed by the Board on this
account works out to Rs.3.64 crore inclusive of meter rentals and service
charges amounting to Rs.0.17 crore, which is in line with the subsidy approved
in the Tariff Order for 2009-10. However, as per decision of GoP dated
22.1.2010, subsidy on power supply allowable to this category of consumers has
been reduced to 100 units but the Commission has no option but to retain an
amount of Rs.3.64 crore as subsidy payable as the Board has not been able to
provide the revised figures in this respect. The reduced subsidy on this
account will be determined at the time of true up in the next Tariff Order.
The Commission, therefore, approves subsidy of
Rs.3.64 crore inclusive of meter rentals and service charges of Rs.0.17 crore.
Accordingly, the subsidy payable for 2009-10 has been
retained at Rs.3144.25 (2796.99 +8.00+335.62+3.64)
crore.
3.15.3
Interest on Delayed Payment of Subsidy
The GoP has paid subsidy due to the
Board in 2009-10 initially in staggered monthly installments and subsequently
by adjusting a loan amount of Rs.1140.43 crore and Rs.270.22 crore of ED
payable by the Board to the GoP. However, the Commission has observed that not
only has there been delay in payment of subsidy to the Board but the same has
not been paid at the beginning of the month for which it is due as specified by
the Commission in para 6.4.2 of the Tariff Order of 2009-10. In accordance with
past practice, the Commission, with a view to compensating the Board on this
account, levies interest on the delayed payment of subsidy @11.09% (effective
interest on short term loans as per the ARR of the Board) which works out to
Rs.60.02 crore during 2009-10. This amount will, however, need to be recalculated
as subsidy payable will decrease consequent upon GoP’s recent decision to
reduce subsidy in the case of AP and SC/BPL DS consumers. This exercise would
be taken up at the time of true-up of the year 2009-10, in the next Tariff
Order.
Accordingly, the subsidy payable for 2009-10, inclusive of interest on
delayed payment of subsidy, determined as payable by the GoP to the Board
is Rs.3204.27 (3144.25+60.02) crore.
Besides this, the GoP is liable to pay an amount of Rs.276.23 crore (as
discussed in paras 2.14.12 & 2.16) on account of non-refund of excess
interest paid by the Board. The Commission has been emphasizing the importance
of reducing amounts other than subsidy that are payable to the Board. This is
imperative in the context of the mounting debt of the Board and its precarious
financial position. As discussed in para 3.14.3 and 3.14.11 above net interest
due on GoP loans for 2009-10 is Rs.48.12 crore. This amount is being adjusted
against the non-refunded amount of Rs.276.23 crore after which the net amount
payable to the Board works out to Rs.228.11 (276.23-48.12) crore. This is
carried forward to para 5.4.
3.16 Return on Equity
3.16.1 In accordance with Regulation 25 of the PSERC Tariff Regulations,
the Commission in the Tariff Order of 2009-10 permitted a Return on Equity at
the rate of 14% on an equity base of Rs.2946.11 crore, which worked out to
Rs.412.46 crore.
3.16.2 In the ARR for 2010-11, the
Board has claimed ROE @ 15.5 % (pre-tax) to be grossed up to 23.48% as provided
in the CERC Regulations. The PSERC Tariff Regulations stipulate that CERC
Regulations are to be followed “as far as possible”. The Commission notes that
the Board has been unable to effect requisite improvements in critical
performance parameters such as T&D losses and employee cost. Moreover, the
Board continues to be a loss making entity and any increase in ROE may not for
that reason alone be justified. Accordingly, the Commission finds no
justification to allow ROE at higher rates and allows ROE of Rs.412.46 crore at
14% of the total paid up capital of the Board.
Accordingly, the Commission
approves Return on Equity of Rs.412.46 crore for 2009-10.
3.17
Non-Tariff Income
In
the Tariff Order of 2009-10, the Commission approved non-tariff income of
Rs.444.03 crore as claimed by the Board. In the ARR of 2010-11, the Board, has
revised the non-tariff income for the year 2009-10 to Rs.494.30 crore. This
amount includes Rs.67 crore on account of recovery of theft of energy which has
been counted towards revenue from tariff. Therefore, this is reduced from
Non-tariff income. The subsidy receivable from the GoP on account of meter
rentals and service charges for AP, SC DS and Non-SC BPL DS consumers amounting
to Rs.21.30 (8.00+13.13+0.17) crore is to be accounted for as non-tariff income.
Thus, non-tariff income for the year 2009-10 works out to Rs.448.60
(494.30-67+21.30) crore.
The Commission,
accordingly, approves Rs.448.60 crore as the
Non-Tariff income of the Board for 2009-10.
3.18 Revenue from Existing Tariff
The Board has revised the estimates of revenue at existing tariff in
its letter of 28.01.2010 to Rs.12227.86 crore (inclusive of subsidy of
Rs.3144.25 crore) against Rs.12775.37 crore approved by the Commission in the
Tariff Order of 2009-10. However, as discussed in para 3.17, an amount of Rs.67
crore is to be added to the revenue on account of theft of energy. In addition,
there is no justification to deduct Rs.354.87 crore on account of reduced
revenue receipts from consumers availing discount against advance payment of
bills. Moreover, the Board’s revised estimates are based on energy sales of
32341 MUs, whereas, the Commission has determined such sales as 32591 MUs.
Taking these factors into account, the Commission now revises revenue from
existing tariff to Rs.12784.67 crore as given in table 3.16 below.
Table 3.16: Revenue from Existing
Tariff for 2009-10
(Rs.
crore)
Sr. No. |
Category of consumers |
As projected by Board |
As approved by Commission |
||||
Energy sales (MUs) |
Tariff rates (paise/unit) |
Revenue (Rs. in crore) |
Energy sales (MUs) |
Tariff rates (paise/unit) |
Revenue (Rs. in crore) |
||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
1 |
Domestic |
||||||
a) |
Up to 100 units |
2663 |
282 |
751 |
2650 |
282 |
747.30 |
b) |
101-300 units |
2904 |
428 |
1243 |
2890 |
428 |
1236.92 |
c) |
Above 300 units |
1769 |
452 |
799 |
1760 |
452 |
795.52 |
|
Total (a+b+c) |
7336 |
|
2793 |
7,300 |
|
2779.74 |
2 |
NRS |
2135 |
491 |
1048 |
2,178 |
491 |
1069.40 |
3 |
Public lighting |
148 |
482 |
72 |
128 |
482 |
61.70 |
4 |
Industrial
Consumers |
||||||
a) |
SP |
768 |
392 |
301 |
742 |
392 |
290.86 |
b) |
MS |
1607 |
433 |
696 |
1,509 |
433 |
653.40 |
c) |
LS |
8741 |
433 |
3785 |
8,619 |
433 |
3732.03 |
|
Total (a+b+c) |
11116 |
|
4782 |
10,870 |
|
4676.29 |
5 |
Bulk Supply |
||||||
a) |
HT |
462 |
436 |
201 |
451 |
436 |
196.64 |
b) |
LT |
33 |
463 |
15 |
33 |
463 |
15.28 |
|
Total (a+b) |
495 |
|
216 |
484 |
|
211.92 |
6 |
Railway Traction |
149 |
512 |
76 |
132 |
512 |
67.58 |
7 |
Common pool |
302 |
331 |
100 |
302 |
331 |
100 |
8 |
Outside State |
297 |
555 |
165 |
1383 |
555 |
767.57 |
9 |
Total (1 to 8) |
21978 |
|
9252.00 |
22777 |
|
9734.20 |
10 |
AP subsidy |
10363 |
285 |
0.00 |
9,814 |
285 |
2796.99 |
11 |
Total (9+10) |
32341 |
|
9252.00 |
32591 |
|
12531.19 |
12 |
Add: PLEC, MMC.
Other charges |
|
|
186.48 |
|
|
186.48 |
13 |
Add: Recovery on
account of theft of energy |
|
|
67.00 |
|
|
67.00 |
14 |
Less: Revenue Loss
on |
|
|
354.87 |
|
|
|
15 |
Add: Subsidy from
GoP |
|
|
3144.25 |
|
|
|
16 |
Grand Total |
32341 |
|
12294.86 |
32591 |
- |
12784.67 |
The Commission, therefore, approves revenue from existing tariff at
Rs.12784.67 crore for energy sales of 32591 MUs for 2009-10.
3.19 Revenue Requirement
A summary of the review for 2009-10 as discussed
in the preceding paragraphs is given in Table 3.17
Table 3.17:
Revenue Requirement for 2009-10
(Rs.crore)
Sr.
No. |
Item of Expense |
As per Board in ARR 09-10 |
Approved by Commission in |
Revised estimates by Board |
Now Approved by the Commission |
T. O. for 09-10 |
|||||
1 |
2 |
3 |
4 |
5 |
6 |
1 |
Cost of
fuel |
3047.00 |
3195.93 |
3501.75 |
3414.58 |
2 |
Cost of
power purchase |
7264.61 |
4746.59 |
4999.37 |
4969.65 |
3 |
Employee
cost |
3454.68 |
1856.60 |
2734.05 |
2354.48 |
4 |
R&M
expenses |
406.80 |
376.14 |
385.93 |
385.93 |
5 |
Admin
& General Exp |
76.00 |
76.00 |
75.95 |
75.95 |
6 |
Depreciation |
969.99 |
826.02 |
792.96 |
791.10 |
7 |
Interest
charges |
1585.61 |
1048.57 |
1624.54 |
1082.38 |
8 |
Carrying
cost of gap |
|
209.96 |
|
|
9 |
Return on
Equity |
412.46 |
412.46 |
681.56 |
412.46 |
10 |
Fringe
Benefit Tax |
5.51 |
0.00 |
0.00 |
0.00 |
11 |
Other
Debits and Extraordinary items |
4.81 |
0.00 |
0.00 |
0.00 |
12 |
Total
revenue requirement |
17227.47 |
12748.27 |
14796.11 |
13486.53 |
13 |
Less: non
tariff income |
444.03 |
444.03 |
427.30 |
448.60 |
14 |
Net
revenue requirement (12-13) |
16783.44 |
12304.24 |
14368.81 |
13037.93 |
15 |
Revenue
from existing tariff |
12442.00 |
12775.37 |
12294.86 |
12784.67 |
16 |
Gap
for 2009-10 |
(-) 4341.44 |
(+) 471.13 |
(-) 2073.95 |
(-) 253.26 |
17 |
Gap for
the year 2008-09 & 2007-08 |
(-) 4205.00 |
(-) 471.08 |
(-) 1453.54 |
(-) 977.37 |
18 |
Net
gap (16 + 17) |
(-) 8546.44 |
(+) 0.05 |
(-) 3527.49 |
(-) 1230.63 |
Review for 2009-10 indicates that there is now a gap (deficit) of Rs.253.26 crore for 2009-10. After adjustment of
cumulative deficit of Rs.977.37 crore upto 2008-09, against the deficit of
Rs.253.26 crore of 2009-10, the total deficit
works out to Rs.1230.63 crore at the
end of 2009-10. This deficit is being carried forward to the next year for
adjustment.
Annual Revenue Requirement for 2010-11
4.1.1 Metered Energy Sales:
The Board has projected metered energy sales for 2010-11 based on category wise
Compounded Annual Growth Rate (CAGR) of three years from 2005-06 to 2008-09.
The 3 year CAGR has been worked out from audited metered sales for the period
2005-06 to 2008-09 which has then been applied to the revised estimates of
metered sales of respective categories for 2009-10 to arrive at energy sales
projections for 2010-11. The Board has also proposed application of CAGR in
case of Railway Traction category since the Board has observed a significant
increase in consumption during the first half of 2009-10 in comparison to the
sales during the previous year for the same period. Details of the Board’s
projections are in Table 4.1.
Table 4.1: Energy Sales to Metered Categories
as per ARR - 2010-11
(MUs)
Metered Energy Sales |
2008-09 (Actual) |
2009-10
(RE) |
2010-11
(Projections) |
1 |
2 |
3 |
4 |
Domestic |
6695 |
7336 |
7894 |
Non-Residential |
1967 |
2135 |
2355 |
Small
Power |
743 |
768 |
784 |
Medium
Supply |
1556 |
1607 |
1639 |
Large
Supply |
8747 |
8741 |
9212 |
Public
Lighting |
147 |
148 |
157 |
Bulk
Supply |
480 |
495 |
508 |
Railway
Traction |
126 |
149 |
155 |
Total
Sales (within the state) |
20461 |
21379 |
22705 |
The Commission has
estimated category wise sales within the State for 2010-11 for all categories,
including Railway Traction, by applying 3 years CAGR (2005-06 to 2008-09), on
sales for the year 2009-10 now approved in Chapter-3. Actual sales for the
years 2005-06 and 2008-09, 3 year CAGR for 2005-06 to 2008-09 as calculated by
the Commission, sales now approved for 2009-10 and estimated sales in 2010-11
for different metered categories within the State are given in Table 4.2.
Table 4.2: 3- Year CAGR
& Estimated Metered Sales within the State – 2010-11
(MUs)
Sr. No. |
Category |
2005-06 (Actuals) |
2008-09 (Actuals) |
3 year CAGR (2005-06 to 2008-09) |
Sales now approved for 2009-10 |
Estimated sales for 2010-11 |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
1 |
Domestic |
5354 |
6695 |
7.74% |
7300 |
7865 |
2 |
Non-Residential |
1461 |
1967 |
10.42% |
2178 |
2405 |
3 |
Small
Power |
695 |
743 |
2.25% |
742 |
759 |
4 |
Medium
Supply |
1462 |
1556 |
2.10% |
1509 |
1541 |
5 |
Large
Supply |
7450 |
8747 |
5.50% |
8619 |
9093 |
6 |
Public
Lighting |
122 |
147 |
6.41% |
128 |
136 |
7 |
Bulk
Supply |
444 |
480 |
2.56% |
484 |
496 |
8 |
Railway
Traction |
111 |
126 |
4.32% |
132 |
138 |
9 |
Total
Sales within State |
17099 |
20461 |
|
21092 |
22433 |
4.1.2 Sales to common pool consumers and Outside
State sales
The Board has
projected sales to common pool and outside State consumers for the year 2010-11
as below:
Category |
2009-10(RE) ( MUs) |
Projection for
10-11 (MUs) |
Sales to common pool consumers |
302 |
302 |
Sales outside State |
297 |
125 |
The Outside State
sales of 1211 MUs projected by the Board in the ARR for 2010-11 has been
subsequently revised to 125 MUs by the Board (in its letter dated January 28,
2010) owing to change in accounting procedure for sale/purchase of banked power
from 2009-10. The Board further intimated in its letter dated 17th
March, 2010 that it has inadvertently shown Outside State sale of 125 MUs and revenue
of Rs. 69 crore for 2010-11, and clarified that Outside State sale of 125 MUs
includes the free share of 72 MUs of Himachal Pradesh at the rate of 4.6% of
gross generation from RSD hydro electric project (HEP) and royalty of 53 MUs to
HP from Shanan HEP. The expected revenue from royalty of 53 MUs to HP has been
intimated by the Board as Rs. 5.4 crore. The Commission deducts 72 MUs from Outside
State sales as this is a free share of HP from RSD, and accordingly accepts the
Outside State sales of 53 MUs (royalty to HP from Shanan).
The Commission approves Outside State sale at 53 MUs
for the year 2010-11 as also the sale of 302 MUs to common pool consumers.
The total
estimated metered sales for the year 2010-11 depicted by the Board and approved
by the Commission are given in Table 4.3.
Table 4.3: Metered Sales -
2010-11
(MUs)
Sr.
No. |
Metered
Category |
Projected by Board |
Approved by the Commission |
1 |
2 |
3 |
4 |
1 |
Domestic |
7894 |
7865 |
2 |
Non-Residential |
2355 |
2405 |
3 |
Small
Power |
784 |
759 |
4 |
Medium
Supply |
1639 |
1541 |
5 |
Large
Supply |
9212 |
9093 |
6 |
Public
Lighting |
157 |
136 |
7 |
Bulk
Supply |
508 |
496 |
8 |
Railway Traction |
155 |
138 |
9 |
Total
within State |
22704* |
22433 |
10 |
Common
pool |
302 |
302 |
11 |
Outside
State sales |
125 |
53 |
12 |
Total
Sales (9+10+11) |
23131 |
22788 |
* As against 22705 shown in the ARR
The Commission, thus, approves metered sales at 22788
MUs against 23131 MUs projected by the Board.
4.1.3 AP Consumption: The Board, in the ARR of
2010-11, has projected AP consumption at 11245 MUs for 2010-11 by applying CAGR
of last three years (8.51%) over the estimated sales for 2009-10.
The Commission, during the true-up of 2008-09 had approved AP
consumption of 8395 MUs by reducing the Board’s projection of 9349 MUs by
10.20% based on the report of the Agency engaged for estimation of AP
consumption for 2007-08 and first three quarters of 2008-09. As discussed in
para 3.2.3 of this Tariff Order, the Board’s response to the directives given
in Tariff Order of 2009-10 are not conclusive and thus its estimates are not considered
reliable. The Commission decides to estimate AP consumption for the year
2010-11 by applying 5% increase over sales of 9814 MUs approved by the
Commission for 2009-10. AP consumption for the year 2010-11 on this basis works
out to 10305 MUs, which the Commission approves.
4.1.4
Total Energy Demand (Sales)
The total
metered sales, AP consumption, common pool and Outside State sales projected by
the Board and as approved by the Commission are given in Table 4.4
Table 4.4: Total Energy Sales for 2010-11
(MUs)
Sr.No. |
Category |
Projected by the Board |
Approved by the Commission |
1 |
Total metered sales within the state |
22704 |
22433 |
2 |
AP consumption |
11245 |
10305 |
3 |
Total
sales within the State (1+2) |
33949 |
32738 |
4 |
Sales to common pool consumers |
302 |
302 |
5 |
Outside State sales |
125 |
53 |
6 |
Total
sales (3+4+5) |
34376 |
33093 |
The Commission, thus, approves total energy sales to
different categories of consumers at 33093 MUs including common pool and Outside
State sales.
4.2 Transmission
and Distribution Losses (T&D Losses)
The Board has
projected transmission and distribution losses at 18% for 2010-11 which
represents a reduction of 1.5% from losses of 19.5% in 2009-10 and 1.92% from
the loss level of 19.92% in 2008-09. The Board’s estimated T&D losses for
the year 2008-09 and 2009-10 and projections for 2010-11 have been based on AP
consumption of 9349 MUs, 10363 MUs and 11245 MUs respectively. It is, however,
necessary to assess the performance of the Board in reduction of its T&D
losses on the basis of AP consumption actually approved by the Commission. This
is brought out in Table 4.4 (A):
Table 4.4 (A)
(%)
Year |
T&D loss level fixed by the Commission |
T&D loss level reported by the Board |
T&D losses based on AP consumption approved by the Commission |
2004-05 |
23.25 |
24.27 |
24.59 |
2005-06 |
22.00 |
25.07 |
25.38 |
2006-07 |
20.75 |
23.92 |
24.25 |
2007-08 |
19.50 |
22.53 |
25.12 |
2008-09 |
19.50 |
19.92 |
22.21 |
2009-10 |
22.00 |
19.50 |
|
2010-11 |
20.00 |
18.00 |
|
The Commission has
been repeatedly observing that the Board has not been able to achieve the loss
reduction trajectory as was earlier approved by the Commission or even the
adhoc loss levels prescribed by the Commission for the years 2008-09 and
2009-10. The Commission has also been pointing out that there is a need to
identify specific measures that the Board would like to initiate to reduce
these losses in a phased manner and to monitor the implementation thereof in a
quantifiable manner every year. As most of the proposed initiatives of the Successor
Entities are capital intensive, the Commission has also been emphasizing the
need for completing base line surveys and thereafter conducting systematic
energy audits so that comprehensive action in the area of T&D loss
reduction can be taken by the Successor Entities.
These matters have
been discussed with the Board on several occasions consequent upon the issue of
the Tariff Order for 2009-10. Emphasis in those discussions was laid on fixing
year-wise targets in implementing loss reduction measures such as conversion to
HVDS system, replacement of electro-mechanical meters, installation of
capacitors on 11 KV feeders, shifting of meters outside residential premises
and the completion of base line surveys followed by systematic energy audits.
The Board has now intimated the progress achieved in this respect and the
proposed course of action in 2010-11. It was informed that 82000 AP connections
have already been converted into HVDS and a total of 2.50 lac such connections
will also be covered by HVDS by the end of March 2011. The Board has also
indicated that additional 2100 MVAR capacitors will be installed during 2010-11
besides paying greater attention to maintenance to ensure that existing
capacitors including those installed on distribution transformers are
functional. In respect of shifting of meters outside consumer premises, it was
stated that 5 lac such meters have already been shifted and an additional 42
lac are proposed to be shifted by end of March 2011; electronic meters will
replace electro-mechanical meters in parallel with this exercise. Referring to
the completion of base line surveys and initiation of energy audit, the Successor
Entities proposes to implement them as part and parcel of its IT plan for which
the order will be placed shortly and is scheduled to be implemented in 18
months thereafter.
The Commission
appreciates the fact that the Successor Entities has fixed annual performance
targets for specific steps aimed at the reduction of T&D losses. It has
also framed time-lines for the implementation of IT plan which includes
acquisition of data with regard to Regulatory Information Management System
(RIMS) and the undertaking of base line surveys including conducting of energy
audits. The Commission now expects that the Successor Entities will suitably
pursue these measures and ensure their timely implementation. If possible,
priority needs to be assigned to base line surveys and energy audits while
implementing the IT plan.
The targeted
reduction of T&D losses and the actual achievement by the Board has been
brought out in table 4.4 (A). The Commission’s earlier trajectory for loss
reduction targeted that the Board would achieve T&D losses of 19.5% in
2007-08 after which fresh targets were to be prescribed by the Commission.
However, the Board’s consistent inability to achieve reduction in accordance
with the trajectory earlier determined had made it necessary for the Commission
to retain the loss level in the year 2008-09 at 19.5% but the Commission noted
that as against this, the estimated losses of the Board were 22.21% after
taking AP consumption computed by the Commission into account. For reasons
brought out in para 4.2 of the Tariff Order for 2009-10, the Commission had
revised the T&D loss targets for 2009-10 to 22%. It is observed that the Successor
Entities now seems to be approaching the entire issue of T&D loss reduction
in a more comprehensive and systematic manner and for that reason it should be
able to achieve better results. The Abraham Committee envisages a normative
loss reduction of 2% annually where the losses in a particular entity are more
than 20%. Accordingly, the Commission
fixes T&D loss targets for 2010-11 at 20% and taking the recommendations of
this Committee further into account, the loss trajectory for the years 2011-12
and 2012-13 is also determined at 19% and 18%.
4.3 Energy
Requirement (Input)
The total energy
requirement is the sum of estimated energy sales including common pool and Outside
State sales and T&D losses. The projected energy sales, T&D losses and
energy requirement as reported by the Board and approved by the Commission for
the year 2010-11 are given in Table 4.5.
Table 4.5: Energy
Requirement - 2010-11
(MUs) |
|||
Sr.
No. |
Particulars |
As
projected by the Board for 10-11 |
As
approved by the Commission |
1 |
2 |
3 |
4 |
1 |
Metered
Sales within State |
22704 |
22433 |
2 |
AP
consumption |
11245 |
10305 |
3 |
Total
sales within State (1+2) |
33949 |
32738 |
4 |
Common
pool sales |
302 |
302 |
5 |
Outside
State sales |
125 |
53 |
6 |
Total
sales |
34376 |
33093 |
7 |
T&D
losses on item (3) |
18.00% |
20% |
7452 |
8185 |
||
8 |
Total
energy input required (6+7) |
41828 |
41278 |
The
overall energy requirement as shown by the Board is higher by 550 MUs than that
approved by the Commission on account of difference in metered sales, Outside State
sales, AP consumption and T&D losses determined by the Commission. The
energy requirement thus works out to 41278 MUs which has to be met from the Successor Entities’s own generation (thermal & hydel) including share from BBMB and
purchases from Central Generating Stations and other sources. These issues are
discussed in succeeding paras.
4.4.1 Thermal Generation: The Board has
projected generation for the year 2010-11 at 2280 MUs, 9500 MUs and 6565 MUs
for GNDTP, GGSTP and GHTP {4786 MUs for GHTP Units I, II &
Plant Availability
The Board has submitted that -
·
The Plant Availability of GNDTP for 2010-11 has been
projected as 71.22% in the ARR. The reason for reduced availability has been
stated as, scheduled Renovation and Modernization work planned on the two units
(Unit-
·
The Plant Availability for GGSTP for 2010-11 has been
projected at 91.98%, based on the planned maintenance schedule of its units in
2010-11 for a total of 99 days (Unit-1:26 days; Unit-3:43 days and Unit-5:30
days) and also taking into account average forced outages of the plant.
·
The Plant Availability for GHTP (Unit I, II and
·
In the case of GHTP Unit IV, plant availability has been
projected at 92.50% on the basis of plant maintenance schedule of 23 days.
The availability of GNDTP, GGSTP and GHTP – Stage I based on maintenance
schedules (excluding forced outages as projected by the Board) for the year
2010-11, is calculated by the Commission as 75.07%, 95.48% and 88.22%
respectively. Units 3&4 of GHTP Stage-II have been commissioned recently
and data for past three years is not available. The Commission has assumed the
average availability of 90% during 2010-11 for the purpose of calculating gross
generation.
The Commission has assessed availability and generation for the year
2010-11 based on the average of actual availability and generation for the
three years (2006-07 to 2008-09). The actual availability and generation of the
thermal plants for 2006-07, 2007-08 and 2008-09 along with average of three
years generation and availability are as given in Table 4.6.
Table 4.6: Actual Availability and
Generation – 2006-07 to 2008-09
Sr. No. |
Station |
FY 2006-07 |
FY 2007-08 |
FY 2008-09 |
Average of the 3 years |
1 |
GNDTP |
||||
|
Generation
(MUs) |
2221 |
3008 |
2846 |
2692 |
|
Availability (%) |
64.90% |
87.53% |
89.15% |
80.53% |
2 |
GGSTP |
||||
|
Generation (MUs) |
9770 |
9806 |
9611 |
9729 |
|
Availability (%) |
90.20% |
91.64% |
89.92% |
90.59% |
3 |
GHTP Stage I (Units
I&II) |
||||
|
Generation (MUs) |
3443 |
3508 |
3532 |
3494 |
|
Availability (%) |
94.30% |
94.81% |
95.98% |
95.03% |
Considering the projected availability in 2010-11 and the actual
availability/ generation in 2006-07, 2007-08 and 2008-09, gross generation for
2010-11 has been computed in Table 4.7.
Table
4.7:
Availability, Gross Generation and PLF of Existing Thermal Plants
- 2010-11
Sr.No. |
Station |
Three year average availability |
Three year average generation (MUs) |
Assessed by the Commission for
2010-11 |
|||
Availability as per mtc. Schedules
for 2010-11 |
Generation (MUs) (4x5) / 3 |
PLF (Calculated) |
|||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
|
1 |
GNDTP |
80.53% |
2692 |
75.07% |
2509 |
65.09% |
|
2 |
GGSTP |
90.59% |
9729 |
95.48% |
10254 |
92.90% |
|
3 |
GHTP Stage I |
95.03% |
3494 |
88.22% |
3244 |
88.17% |
The Board in the ARR has stated that Unit IV of GHTP will be operational
from December 2009. However, Unit IV has achieved
Table 4.8: Gross Thermal Generation - 2010-11
(MUs)
Sr.No. |
Station |
Approved Generation |
1 |
GNDTP |
2509 |
2 |
GGSTP |
10254 |
3 (a) |
GHTP
Stage I |
3244 |
3 (b) |
GHTP
Stage II (Unit 3) |
1980 |
3 (c) |
GHTP Stage
II (Unit4) |
2052 |
|
Total |
20039 |
Accordingly, the Commission assesses the total gross
Thermal generation as 20039 MUs.
Performance
parameters
The PSERC Tariff Regulations provide that for
determining the cost of generation of each generating station, the Commission
shall be guided, as far as feasible, by the principles and methodology of CERC,
as amended from time to time. This approach has been adopted by the Commission
in its previous Tariff Orders from 2005-06 onwards. CERC has in its notification
No.L-7/145(160)/2008-CERC dated
Auxiliary Consumption
& Net Generation
The Commission has adopted CERC norms for
assessment of net generation of GGSTP and GHTP and considered various issues
and submissions regarding Auxiliary consumption of GNDTP Units in para 2.4.1.
Accordingly, auxiliary consumption for the year 2010-11 has been fixed at
11.00%, 8.50% and 9.00% for GNDTP, GGSTP and GHTP respectively. Auxiliary
consumption and net generation from the three thermal generating stations as
projected by the Board and approved by the Commission for 2010-11 is given in
Table 4.9.
Table 4.9: Generation and
Auxiliary Consumption for Thermal Plants – 2010-11
(MUs)
Sr. No. |
Station |
Projected by the Board |
Approved by the Commission |
||||
Gross Generation |
Auxiliary Consumption |
Net Generation |
Gross Generation |
Auxiliary Consumption |
Net Generation |
||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
1 |
GNDTP |
2280 |
264 |
2016 |
2509 |
276 |
2233 |
Units-I&II |
|||||||
GNDTP |
11.60% |
11.00% |
|||||
Units- |
|||||||
2 |
GGSTP |
9500 |
808 |
8692 |
10254 |
872 |
9382 |
8.50% |
8.50% |
||||||
3 |
GHTP
Stage-I |
6565 |
5974 |
7276 |
655 |
6621 |
|
GHTP
Stage-II |
9.00% |
9.00% |
|||||
4 |
Total |
18345 |
1663 |
16682 |
20039 |
1803 |
18236 |
Net thermal generation approved by the Commission is 18236
MUs against 16682 MUs projected by the Board.
4.4.2 Hydel Generation: In the
ARR for 2010-11, the Board has estimated hydel generation from its own stations
for the year 2010-11 based on the three years’ average of gross generation for
2006-07, 2007-08 and 2008-09 which is also in line with the Commission’s approach
in its earlier Tariff Orders. The generation projected by the Board and the
generation approved by the Commission is given below in Table 4.10.
Table 4.10: Own Hydel
Generation – 2010-11
(MUs)
Sr. No. |
Station |
Generation projected by the Board
for 10-11 |
Actual Generation |
Generation estimated by the
Commission (Based on 3 year average) |
||
06-07 |
07-08 |
08-09 |
||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
1 |
Shanan |
522 |
496 |
540 |
532 |
523 |
2 |
UBDC
Stage 1 |
384 |
162 |
184 |
140 |
162 |
3 |
UBDC
Stage 2 |
223 |
244 |
199 |
222 |
|
4 |
RSD |
1564 |
1679 |
1538 |
1474 |
1564 |
5 |
|
1222 |
1171 |
1362 |
1132 |
1222 |
6 |
ASHP |
688 |
666 |
710 |
689 |
688 |
7 |
Micro
Hydel |
8 |
8 |
7 |
10 |
8 |
8 |
Total
own generation (Gross) |
4388 |
4405 |
4585 |
4175 |
4389 |
The Commission approves estimated gross generation of 4389 MUs from the Successor
Entity’s own hydel stations. The Commission also approves the Successor
Entity’s share and Common Pool share from BBMB as projected by the Board and
depicted in Table 4.11.
Table 4.11: Total Hydel
Generation - 2010-11
(MUs)
Sr. No. |
Station |
Projected by the Board for 10-11 |
Approved by the Commission |
1 |
2 |
3 |
4 |
1 |
Shanan |
522 |
523 |
2 |
UBDC |
384 |
384 |
3 |
RSD |
1564 |
1564 |
4 |
|
1222 |
1222 |
5 |
ASHP |
688 |
688 |
6 |
Micro
Hydel |
8 |
8 |
7 |
Total own generation (Gross) |
4388 |
4389 |
8 |
Total own generation (Net) |
43421 |
42813 |
9 |
BBMB |
|
|
i) |
Successor
Entity share |
41022 |
4102 |
ii) |
Common
Pool share |
302 |
302 |
iv) |
Availability (Net) |
4404 |
4404 |
10 |
Total
Availability (Net) |
8746 |
8685 |
1. Board’s Projection for own generation is net of
auxiliary consumption and transformation losses (46 MUs).
2. Board’s projection of BBMB share is
net of external transmission losses based on the actual level of losses @ 3.7 %
in 2008-09.
3. Commission’s Assessment of own generation is net of:
§
HP
share (free) in RSD @ 4.6% (72 MUs)
§
Auxiliary
consumption @ 0.5% for RSD generation and UBDC stage-1 generation (on previous
year’s pattern) and 0.2% for others (14 MUs)
§
Transformation
losses @ 0.5 % (22 MUs)
The Commission,
thus, approves net hydel generation of 8685 MUs for the year 2010-11.
4.4.3 Total Availability of energy from the Successor
Entity’s own stations and BBMB: The approved net generation from own thermal
and hydel station of the Successor Entity and share from BBMB is given in Table 4.12.
Table 4.12: Net Own
Generation - 2010-11
Sr. No. |
Station |
Energy available |
1 |
2 |
3 |
1 |
Thermal
Stations |
18236 |
2 |
Hydel
Stations (Own) |
4281 |
3 |
Share
from BBMB (including 302 MUs share of common pool consumers) |
4404 |
4 |
Total
own Availability |
26921 |
The Commission approves the total energy available from the Successor Entity’s own generating stations including share from BBMB as
26921 MUs.
4.5 Purchase
of Power
4.5.1 The total energy required to meet the demand during 2010-11
including Common Pool and Outside State sales is 41278 MUs as discussed in para
4.3. The energy available from own generating stations of the Successor Entity including its share from BBMB is 26921 MUs
as approved in para 4.4.
4.5.2 The balance requirement of 14357 MUs (net)
has to be met through purchases from Central Generating Stations and other
sources. This is against a requirement of 16404 MUs (net) projected by the
Board for the year 2010-11.
4.6.1 The energy balance which takes into account
the approved energy sales to different categories of consumers, T&D losses
and energy availability is given in Table 4.13.
Table 4.13: Energy Balance – 2010-11
(MUs)
Sr. No. |
Particulars |
Projected by the Board |
Approved by the Commission |
1 |
2 |
3 |
4 |
A |
Energy
Requirement |
|
|
1 |
Metered
Sales within state. |
22704 |
22433 |
2 |
Sales to
AP consumers |
11245 |
10305 |
3 |
Total sales within state (1+2) |
33949 |
32738 |
4 |
T&D
Losses |
7452 |
8185 |
5 |
Common
pool |
302 |
302 |
6 |
Outside
State sales |
125 |
53 |
7 |
Total
Requirement (3+4+5+6) |
41828 |
41278 |
|
|
|
|
B |
Energy
Availability |
|
|
1 |
Own
generation (ex-bus) |
|
|
a) |
Thermal |
16682 |
18236 |
b) |
Hydel |
4342 |
4281 |
2 |
Share
from BBMB (including share of common pool consumers = 302) |
4404 |
4404 |
3 |
Purchase
(Net) |
16404 |
14357 |
4 |
Total
Availability |
41832* |
41278 |
* Against 41831 shown by the
Board.
4.7.1 Fuel Cost Projected by the Board: The
Board has projected fuel cost of Rs. 3622.83 crore for a total generation of 18345
MUs during the year 2010-11 based on operational parameters and fuel prices as
detailed in Table 4.14.
Table 4.14: Fuel Parameters projected by the Board -
2010-11
Sr.No. |
Station |
PLF (%) |
Station Heat Rate (kcal/kwh) |
Transit loss of coal (%) |
Coal Price including transit loss
(Rs/MT) |
Calorific value of coal (kcal/kg) |
Price of Oil (Rs/KL) |
Specific oil consumption (ml/kwh) |
Calorific Value of oil (kcal/litre) |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
1 |
GNDTP |
59.15 |
3010 |
2.00 |
2775 |
4100 |
29138 |
2.50 |
10000 |
2 |
GGSTP |
86.07 |
2697 |
2.00 |
2924 |
4015 |
27362 |
1.50 |
10000 |
3 |
GHTP |
||||||||
(i) |
Stage-I
(Units-I,II& |
81.54 |
2500 |
2.00 |
2854 |
4025 |
35292 |
2.00 |
9400 |
(ii) |
Stage-II
(Unit- IV) |
81.2 |
2500 |
2.00 |
2950 |
4025 |
35000 |
2.00 |
9400 |
4.7.2 The Board has submitted that the performance parameters and coal transit
loss of all the three stations as submitted by the Board may be approved
without any disallowance in the light of the following:
·
The Station Heat
Rate (SHR) for GHTP – Stage I and Stage II has been taken as 2500 Kcal/kWh as
per CERC norms. For GGSTP, the SHR has been taken at 2697 Kcal/kWh on the basis
of previous year’s data which is lower than the SHR of Badarpur Thermal Station
as allowed by CERC and is reasonable considering the fact that two of the six
units at GGSTP are more than 22 years old.
·
The price of oil
has been projected by considering an escalation of 10% on the actual average
price for the respective generating stations till Sept. 2009.
·
The price of coal
for FY10-11 has been projected by considering an escalation of 5% on the actual
average coal prices for the respective stations till Sept’09 and keeping in
view the recent coal price hike by Coal India Limited (CIL).
4.7.3 Fuel Cost approved by the Commission
Gross Generation
The gross
generation of thermal plants for the year 2010-11 has been discussed in para
4.4.1 and summarized in Table 4.8.
Station Heat Rate
The CERC has laid down norms of gross SHR for coal based thermal power
generating stations as given in Table 4.15.
Table 4.15:
CERC Norms for Gross Station Heat Rate
Sr. No. |
Unit size / Plant |
SHR norm (kcal/kwh) |
1 |
2 |
3 |
1 |
200/210/250
MW sets |
2500 |
2 |
500 MW
and above sets |
2425 |
3 |
Talcher
Thermal Power Station |
2950 |
4 |
Tanda
Thermal Power Station |
2825 |
On the above basis,
the Commission approves SHR at 2500 kcal/kWh for GGSTP and GHTP. As CERC has
not specified any norm for units installed at GNDTP, the Commission has decided
in para 4.4.1 to allow SHR of 2825 kcal/kwh for GNDTP Unit I & II based on
the CERC norms for Tanda TPS. In case of GNDTP Units
Coal Transit Loss
The Commission has
permitted Transit Loss of 2% for all power plants in its earlier orders. However, no such loss is taken into account in
the case of PANAM coal which is priced on F.O.R. destination basis.
Price and Calorific
Value of Coal & Oil
Fuel cost being a
major item of expense, the actual calorific value, price and transit loss of
coal and oil for the first six months of 2009-10 were verified and the results
are given in Table 4.16.
Table 4.16: Validated Calorific
Value & Price of Coal & Oil and Transit Loss of Coal – 2009-10
Sr. No. |
Station |
Calorific value of coal (kCal/Kg) |
Calorific Value of Oil (K.cal/Ltr) |
Price of Oil (Rs/KL) |
Price of coal including transit
loss (Rs./MT) |
Transit loss |
Price of coal excluding transit
loss |
1 |
|
1 |
2 |
3 |
4 |
5 |
6 |
1(a) |
GNDTP (Unit I & II) |
4102 |
10000 |
24081 |
2517 |
1.84% |
2471 |
1(b) |
GNDTP
(Unit |
4102 |
10000 |
24081 |
2517 |
1.84% |
2471 |
2 |
GGSTP |
3979 |
10000 |
22613 |
2652 |
0.74 *% |
2633 |
3 |
GHTP |
4023 |
9400 |
29167 |
2589 |
1.22% |
2558 |
* Upto Oct 2009
In working out the
cost of coal for the year 2010-11, the Commission has considered the price and
calorific value of coal as validated for the first six months of 2009-10. The
price and calorific value of coal indicated above are the weighted average
values of coal, including PANAM coal.
Specific Oil
Consumption & Calorific Value of Oil
The Board has
projected the Specific Oil Consumption at GNDTP, GGSTP and GHTP as 2.50, 1.50
and 2.0 ml/kwh respectively.
The Commission has
adopted CERC norms for oil consumption as in the case of other performance
parameters of thermal plants. As per CERC Regulations effective from 1.4.2009,
the Commission approves 1 ml/kwh specific oil consumption for GNDTP Unit I
& II, GHTP and GGSTP. In case of
GNDTP Units
Based on the above, the fuel cost assessed for the year 2010-11 is as
given in Table 4.17.
Table 4.17: Fuel cost (Coal and Oil) – 2010-11
Sr. No. |
Item |
Derivation |
Unit |
Approved for 2010-11 |
||||
GNDTP (I&II) |
GNDTP (III&IV) |
GGSTP |
GHTP |
Total |
||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
8 |
1 |
Generation |
A |
MU |
1534* |
975* |
10254 |
7276 |
20039 |
2 |
Heat Rate |
B |
k.cal/kWh Generated |
2825 |
3000 |
2500 |
2500 |
|
3 |
Specific
oil consumption |
C |
Milli litre/kwh |
1.00 |
3.50 |
1.00 |
1.00 |
|
4 |
Calorific
value of oil |
D |
k.cal/litre |
10000 |
10000 |
10000 |
9400 |
|
5 |
Calorific
value of coal |
E |
k.cal/kg |
4102 |
4102 |
3979 |
4023 |
|
6 |
Overall
heat |
F = (A x B) |
G.cal |
4333550 |
2925000 |
25635000 |
18190000 |
|
7 |
Heat from
oil |
G = (A x C x D) / 1000 |
G.cal |
15340 |
34125 |
102540 |
68394 |
|
8 |
Heat
from coal |
H = (F-G) |
G.cal |
4318210 |
2890875 |
25532460 |
18121606 |
|
9 |
Oil
Consumption |
I=(Gx1000)/D |
KL |
1534.00 |
3412.50 |
10254.00 |
7276.00 |
|
10 |
Transit
loss of coal |
J |
% |
2 |
2 |
2 |
2 |
|
11 |
Total Coal
Consumption excluding transit loss |
K=(H*1000)/E |
MT |
1052708 |
704748 |
6416545 |
4504500 |
|
12 |
Quantity
of PANAM coal |
L |
MT |
733679 |
466321 |
2221100 |
2000000 |
|
13 |
Quantity
of coal other than PANAM coal excluding transit loss. |
M=K-L |
MT |
319030 |
238426 |
4195445 |
2504500 |
|
14 |
Quantity
of coal other than PANAM coal
including transit loss |
N=M/(1-J) |
MT |
325540 |
243292 |
4281067 |
2555613 |
|
15 |
Total
Quantity of coal required |
O=L+N |
MT |
1059219 |
709614 |
6502167 |
4555613 |
|
16 |
Price of
Coal without transit loss |
P |
Rs. /M T |
2471 |
2471 |
2633 |
2558 |
|
17 |
Price of
Oil |
Q |
Rs./KL |
24081 |
24081 |
22613 |
29167 |
|
20 |
Total cost
of oil |
R=Q x I / 107 |
Rs.crore |
3.69 |
8.22 |
23.19 |
21.22 |
|
21 |
Cost of
coal |
S=O x P/107 |
Rs.crore |
261.70 |
175.32 |
1711.73 |
1165.33 |
|
22 |
Total
Fuel cost |
T= R+S |
Rs.crore |
265.39 |
183.54 |
1734.92 |
1186.55 |
3370.40 |
23 |
Fuel Cost per unit |
U= T/A |
Paise |
173 |
188 |
169 |
163 |
168 |
* Gross generation of 2509 MUs apportioned on
the basis of plant availability of 91.78% and 58.36% of GNDTP unit I&II and
GNDTP unit III and IV respectively.
Based on the generation and operational parameters,
approved by the Commission above, cost of fuel for the year 2010-11 works out
to Rs. 3370.40 crore for thermal generation of 20039 MUs (gross) as detailed in
Table 4.17, which the Commission approves.
Fuel Cost Adjustment (FCA)
Any change in the fuel cost from the level approved by the Commission is
to be passed on to the consumers as FCA. Punjab State Electricity Regulatory Commission
(Conduct of Business) Regulations, 2005 contain the FCA formula according to
which any change in fuel cost would be passed on to the consumers with the
prior approval of the Commission.
4.8 Power Purchase
4.8.1 Projection by the
Board: The Board has projected
a cost of Rs.5137.61 crore for purchase of 17322 MUs (gross) in 2010-11 in its
letter dated 28.01.2010. It has
submitted that in 2010-11, the total energy requirement within the state is
expected to increase approximately by 6.96%, whereas the net thermal
availability is expected to go down by 6.56% on account of the maintenance
schedule of a number of units while the net hydel availability (Own stations
and BBMB) is expected to increase by 17.76% during the year FY10-11 as compared
to FY09-10. In order to assess power purchase requirement, the Board has taken
the following into account:
·
Availability projections from old stations (stations in existence for last
3 years) are based upon the average of energy received in the years 2006-07 to 2008-09.
For Unchahar-III, Dulhasti, Tala and Tehri stations, energy has been projected
based on average energy availability in FY07-08 & FY08-09.
·
Modified accounting procedure of purchase and sale of power under banking
arrangement w.e.f. 1.04.09. Under the earlier system, power received under
banking arrangement was treated as power purchased and power returned was
considered as sale of power. Under the new accounting procedure implemented
from 1.04.09, only the net sale/purchase of power under banking arrangement is
being accounted for.
·
The following new power stations
have been considered commercially operational:
§
Unit I of Malana-II from June 2010 & Unit 2
from July 2010. The Successor Entity has
entire 100 MW share in this plant.
§
Unit 3 of Kahalgaon stage-II (3x500 = 1500 MW) from
October 2009. Successor Entity has considered its share as 18 MW.
§
Unit 1 of Maithon Power Project (2x525 = 1050 MW)
from December, 2010. Out of a total of 300 MW share of Successor Entity, 150 MW
has been considered, accordingly.
§
RAPP 5 (220 MW) from Dec. 2009 and RAPP 6 (220 MW)
from Feb. 2010. Successor Entity share has accordingly been considered as 45 MW.
§
Unit 1 of SEWA-II (3x40 = 120 MW) from January
2010, Unit 2 from February 2010 and Unit 3 from March 2010. The overall share
of Successor
Entity has been considered as 17 MW.
§
Four modules of Bawana Gas based Project (1370 MW)
from April 2010, May 2010, July 2010 and September 2010 respectively. Successor Entity’s share
has been considered as 137 MW.
§
Unit 1 of Durgapur Thermal Project (2x500 = 1000
MW) (DVC) from December, 2010 and Unit 2 from February 2011. Accordingly,
energy corresponding to Successor Entity share of 200 MW has been considered.
§
Unit 1 of Raghunathpur Thermal Project (2x600 = 1200
MW) (DVC) from March 2011. Energy corresponding to Successor Entity share of
75 MW (total share 150 MW) has been considered.
§
Unit 1 of Nagarjuna Thermal Project (2x507.5 = 1015
MW) from April 2010 and Unit 2 from July 2010. Successor Entity share
has been considered as 102 MW.
§
Unit 1 of Koteshwar HEP (4x100 = 400 MW) from
October 2010, Unit 2 from December 2010, Unit 3 from February 2011 & Unit 4
from March 2011. Successor Entity share has been considered as 25.5 MW.
§
Unit 1 of Parbati-III HEP (4x130 = 520 MW) from
January 2011, Unit 2 from February 2011 and Unit 3 from March 2011. Successor Entity has
total share of 80 MW in the project.
§
Unit I of Chamera-III HEP (3x77 = 231 MW) from
December 2010, Unit 2 from January 2011 & Unit 3 from February 2011. Successor Entity has a
total share of 23 MW.
§
Unit 1 of Uri-II HEP (4x60 = 240 MW) from November
2010, Unit 2 from December 2010, Unit 3 from January 2011 & Unit 4 from
February 2011. Successor Entity has a total share of 39 MW.
4.8.2 Requirement of Energy
through Purchase: As discussed
in para 4.5.2, the requirement of 14357 MUs (net) has to be met through
purchases from Central Generating Stations and other sources. The transmission
loss external to the Successor Entity’s system has to be added to arrive at the total quantum of energy to be
purchased.
4.8.3 Transmission Loss
External to Successor Entity System: For net
purchase of 16404 MUs, the Board has shown gross purchase of 17322 MUs after
adding average transmission loss of 5.30% as external to its system.
The Commission has, however, considered external loss at a weighted average
of 4.73% based on the actual such loss in the year 2008-09. The gross energy to
be purchased, thus, works out to 15070 MUs (14357 MUs + external transmission
losses 713 MUs) instead of 17322 MUs projected by the Board.
Table 4.18: Successor Entity’s Entitlement from NTPC stations – 2010-11
Sr. No |
Station |
Capacity |
Firm Allocation |
Energy entitlement based on 3 year
average |
Actual Share allocation based on 3
year average (%) |
|
|
|
MW |
% |
MW |
MUs |
% |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
1 |
Anta (GF) |
419 |
11.69 |
49 |
297 |
13.59 |
|
Anta
(RF)* |
|
|
|
20 |
11.40 |
|
Anta
(LF)* |
|
|
|
42 |
14.48 |
2 |
Auriya
(GF) |
663 |
12.52 |
83 |
468 |
13.52 |
|
Auriya
(RF)* |
|
|
|
29 |
8.83 |
|
Auriya
(LF)* |
|
|
|
62 |
15.18 |
3 |
Dadri
(GF) |
830 |
15.90 |
132 |
684 |
16.60 |
|
Dadri
(RF))* |
|
|
|
31 |
11.06 |
|
Dadri
(LF)* |
|
|
|
179 |
15.27 |
4 |
Singrauli |
2000 |
10.00 |
200 |
1619 |
11.49 |
5 |
Rihand I |
1000 |
11.00 |
110 |
917 |
12.45 |
6 |
Rihand II |
1000 |
10.20 |
102 |
914 |
11.70 |
7 |
Unchahar
I |
420 |
8.57 |
36 |
284 |
9.02 |
8 |
Unchahar
II |
420 |
14.28 |
60 |
500 |
15.77 |
9 |
Unchahar
III* |
210 |
8.10 |
17 |
156 |
9.59 |
10 |
Farrakka
(ER)* |
1600 |
|
|
296 |
9.73 |
11 |
Kahalgaon
I (ER)* |
840 |
|
|
588 |
14.33 |
12 |
Kahalgaon
2 (ER)** |
1000 |
8.31 |
83 |
701 |
8.31 |
* Due to
unavailability of data for three years (2006-07 to 2008-09), energy entitlement
and actual share allocation has been calculated based on the data for two years
(2007-08 and 2008-09)
** Energy
entitlement and share allocation taken as projected by Board for 2010-11 in the
ARR as the past data is unavailable.
Table 4.19: Successor Entity’s Entitlement from NHPC stations – 2010-11
Sr. No. |
Station |
Capacity |
Firm Allocation |
Energy entitlement based on 3 year
average |
Share allocation based on 3 year
average |
|
|
|
MW |
% |
MW |
(MUs) |
(%) |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
1 |
Bairasul |
180 |
46.50 |
84 |
302 |
47.33 |
2 |
Salal |
690 |
26.60 |
184 |
854 |
26.63 |
3 |
Tanakpur |
94 |
17.93 |
17 |
67 |
16.17 |
4 |
Chamera I |
540 |
10.20 |
55 |
223 |
11.04 |
5 |
Chamera II |
300 |
10.00 |
30 |
168 |
12.85 |
6 |
Uri |
480 |
13.75 |
66 |
382 |
12.95 |
7 |
Dhauliganga* |
280 |
10.00 |
28 |
138 |
12.16 |
8 |
Dulhasti* |
390 |
8.28 |
32 |
248 |
11.43 |
9 |
URI-II-** |
240 |
16.25 |
39 |
50 |
|
10 |
Sewa-II** |
120 |
14.17 |
17 |
76 |
|
11 |
Parbati-III** |
390 |
20.51 |
80 |
15 |
|
12 |
Chamera-III** |
231 |
9.96 |
23 |
11 |
|
* Due to
unavailability of data for three years (2006-07 to 2008-09), energy entitlement
and actual share allocation has been calculated based on the data for two years
(2007-08 and 2008-09)
** Energy
entitlement and share allocation taken as projected by Board for 2010-11 in the
ARR as the past data is unavailable.
Table
4.20: Successor Entity’s Entitlement from NPC stations
– 2010-11
Sr. No |
Station |
Capacity
|
Firm Allocation |
Energy
entitlement based on 3 year average |
Share
allocation based on 3 year average* |
|
|
MW |
% |
MW |
MUs |
% |
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
1 |
NAPP |
440 |
11.59 |
51 |
87 |
12.82 |
2 |
RAPP 3 |
220 |
22.73 |
50 |
229 |
23.95 |
3 |
RAPP 4* |
220 |
22.73 |
50 |
233 |
24.83 |
4 |
RAPP
5&6** |
440 |
10.20 |
45 |
296 |
|
* Due to
unavailability of data for three years (2006-07 to 2008-09), energy entitlement
and actual share allocation has been calculated based on the data for two years
(2007-08 and 2008-09)
** Energy
entitlement and share allocation taken as projected by Board for 2010-11 in the
ARR as the past data is unavailable.
4.8.5 Cost of Power Purchase
(a)
Central Generating Stations (CGS)
Terms and Conditions of Tariff Regulations issued by CERC in January 2009
are applicable for all Central Generating Stations from April 1, 2009 onwards.
However, CERC is yet to issue Tariff Orders for individual Central Generating
Stations. The Board has submitted in the ARR petition that pending final
determination of station wise tariff, all Central Generating Companies (except
NPCIL for NAPP/ RAPP plants, whose tariffs are governed by the guidelines of
Deptt. of Atomic Energy) are provisionally raising the bills at the tariff
approved by CERC for the year 2008-09. In this Order, therefore, the Commission
has decided to take fixed charges as per bills for Sept. 2009. These fixed
charges will be reviewed in the subsequent Orders of the Commission once CERC
issues tariff orders for the Central Generating Stations based on the new
Tariff Regulations.
NTPC Stations
Fixed Cost
As per CERC Regulations, fixed cost is payable in proportion to the share
allocation of the Successor Entity in each of the
Central Generating Stations and the Commission has accepted this principle. The
annual fixed charges (AFC) in the case of NTPC stations have been considered as
per bills for Sept., 2009.
Variable Cost
The Commission has assessed variable cost for 2010-11 as per NTPC bills for
Sept., 2009 for different stations. In cases where the bills are not available
(Auriya R/F), the Commission has decided to approve the charges projected by
the Board for 2009-10.
Incentive and Other Charges
The incentive and other charges are provisionally approved as projected by
the Board for the year 2010-11.
NHPC Stations
Fixed Cost
CERC Regulations provide that fixed cost is payable in proportion to the
share allocation of the Successor Entity in each of the
Central Generating Stations and the Commission has accepted this principle. AFC
in the case of NHPC stations have been considered as per bills for Sept.,
2009.
Variable Cost
The Commission has assessed variable cost for 2010-11 as per NHPC bills for
Sept., 2009 for different Central Generating Stations. In case of URI-II, Sewa-II, Parbati-III and
Chamera-III where the bills are not available, variable cost has been taken as
projected by the Board in the ARR for 2010-11.
Incentive and Other Charges
The incentive and other charges are provisionally approved as projected by
the Board for the year 2010-11.
NPC Stations
The power purchase rate for NAPP and RAPP-3 & 4 stations has been
considered by the Commission as per bills for Sept., 2009. For RAPP-5&6
stations, the power purchase rate as of RAPP-3&4, has been considered by
the Commission.
(b) Power Purchase Tariff for NRSE Plants (including Jalkheri) and
Short Term Power Purchase within the State and rate of power purchase from NJPC
and Tehri
Quantum and the cost of power purchase from New & Renewable Sources of
Energy (NRSE) Plants (including Jalkheri) and short term power purchases within
the state are provisionally approved as per the Board’s projections.
The energy entitlement and the actual power allocation for NJPC and Tehri
have been taken on the basis of data for two years (2007-08 and 2008-09) as
data for earlier years is not available. The annual fixed charges and variable
charges for NJPC and Tehri are based on the bills for Sept., 2009.
(c) Power Purchase Rates for Banking
The Board has intimated net power purchase under banking from HPSEB,
Rajasthan, UPCL, J&K and through traders as (-) 95 MUs, (-) 10 MUs, 10MUs, (-) 33 MUs and 205 MUs respectively. It has
been clarified by the Board that net power purchase figures have been reflected
in the ARR on account of a change in accounting procedure for sale/purchase of
banked power from 2009-10 and the figures reflected are net of purchase and
sale of power from each source during 2010-11. The rate of banked power taken
by the Board is tentative and the actual rate/amount will be reflected as per
the contract agreement, at the time of review/true-up. The Commission does not
approve the revised methodology proposed by the Board. However, the Commission provisionally
accepts the net power purchase and its rate/cost under banking from HPSEB,
J&K, UPCL and Rajasthan and through traders as per Board’s projections. The
Successor
Entity is directed to submit the source wise power purchase and
sale figures under banking as were being submitted in its previous ARRs, at the
time of review for the year 2010-11. The copies of the contracts entered with
various States/Utilities /Traders are also to be submitted along with the ARR.
(d) Rates for Power Purchase
from New Plants
Quantum and the cost of power purchase from new
plants (Koteshwar, Durgapur TPS, Raghunathpur TPS, Bawana Gas and Nagarjuna
TPS) has been provisionally approved as projected by the Board.
(e) Power Purchase from Traders and through
UI
The power available from all Central Generating
Stations and other sources including banking is 15619 MUs. Taking into account
the gross power purchase requirement of 15070 MUs, there is a surplus of 549
MUs which is proposed to be priced at the average rate of power purchase in
2010-11 (250 paise per unit). On this basis the surplus power purchase of 549
MUs will fetch a revenue amounting to Rs.137.25 crore which is proposed to be
adjusted as revenue earned by the Board.
However, the Commission notes that the average rate
of power purchased through traders as also the UI power purchase rate is
increasing every year. Additional power purchased through traders or UI at high
cost and supplied in increasing quantities to any category of consumers is not
commercially viable. In these circumstances, the Successor Entity has little option but to undertake Demand Side Management
practices and effect power purchases in a judicious manner. Keeping in mind the
escalating cost of power purchase in each successive year, the Commission deems
it necessary that such purchases be kept within the costs approved.
Accordingly, the Commission decides that the cost of power purchase from
traders/UI, if required, will be admissible only at an average rate of
realization per unit of 427.31 paise of 2010-11. The Successor Entity may, in case of purchases effected owing to
emergent circumstances, approach the Commission for any relaxation when the
costs of 2010-11 come up for review/true-up.
The Commission
reiterates that the Successor Entity needs to
purchase power in a judicious and economic manner and also resort to demand
management practices, if necessary, to maintain its commercial viability.
(f) Transmission Charges
The Board has projected transmission charges
payable in 2010-11 to PGCIL as Rs.276.05 crore which the Commission approves.
In addition, the Commission also approves Open Access charges (for banked
energy) of Rs 6.95 crore for 2010-11. The Board has also projected the open
access charges (long term and short-term traders) at Rs.36.28 crore. The
Commission approves Rs.14.35 crore on proportionate basis for traded power of
1351 MUs against 3415 MUs projected by the Board because short term purchases
are not required as per the energy balance.
Based on the above, the cost of power purchase for
the year 2010-11 is worked out as detailed in Table 4.21.
Table 4.21: Power Purchase Cost - 2010-11
Sr. No. |
Source |
Purchase (MUs) |
AFC (Rs. crore) |
PSEB share (%) |
VC (Ps/ Unit) |
FC (Rs. crore) |
VC (Rs.crore) |
Others (Rs.crore) |
Total (Rs.crore) |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
I |
NTPC |
|
|
|
|
|
|
|
|
1 |
ANTA
(G/F) |
297 |
91.16 |
13.59 |
100.98 |
12.39 |
29.99 |
2.04 |
44.42 |
2 |
ANTA
(R/F) |
20 |
|
11.40 |
322.05 |
|
6.44 |
|
6.44 |
3 |
ANTA
(L/F) |
42 |
|
14.48 |
760.73 |
|
31.95 |
|
31.95 |
4 |
AURAIYA
(G/F) |
468 |
136.87 |
13.52 |
124.53 |
18.51 |
58.28 |
5.46 |
82.25 |
5 |
AURAIYA
(R/F) |
29 |
|
8.83 |
374.05 |
|
10.85 |
|
10.85 |
6 |
AURAIYA
(L/F) |
62 |
|
15.18 |
883.96 |
|
54.81 |
|
54.81 |
7 |
DADRI GAS
(G/F) |
684 |
185.40 |
16.60 |
123.18 |
30.78 |
84.26 |
10.73 |
125.77 |
8 |
DADRI
(R/F) |
31 |
|
11.06 |
398.61 |
|
12.36 |
|
12.36 |
9 |
DADRI
(L/F) |
179 |
|
15.27 |
724.41 |
|
129.67 |
|
129.67 |
10 |
SINGRAULI |
1619 |
352.49 |
11.49 |
108.75 |
40.50 |
176.07 |
12.78 |
229.34 |
11 |
RIHAND –I |
917 |
344.02 |
12.45 |
99.78 |
42.83 |
91.50 |
15.07 |
149.40 |
12 |
RIHAND
-II |
914 |
526.68 |
11.70 |
104.65 |
61.60 |
95.65 |
10.14 |
167.40 |
13 |
UNCHAHAR-I |
284 |
142.46 |
9.02 |
155.41 |
12.85 |
44.14 |
4.88 |
61.87 |
14 |
UNCHAHAR-II |
500 |
177.87 |
15.77 |
156.49 |
28.04 |
78.25 |
7.37 |
113.65 |
15 |
UNCHAHAR-III |
156 |
148.10 |
9.59 |
156.49 |
14.20 |
24.41 |
2.04 |
40.65 |
16 |
FARAKKA |
296 |
518.33 |
9.73 |
174.52 |
50.41 |
51.66 |
2.89 |
104.95 |
17 |
KAHALGAON
– I |
588 |
316.79 |
14.33 |
149.40 |
45.40 |
87.85 |
5.32 |
138.57 |
18 |
KAHALGAON
–II |
701 |
515.38 |
8.31 |
144.15 |
42.83 |
101.05 |
0.02 |
143.90 |
|
Sub Total |
7787 |
|
|
|
400.33 |
1169.16 |
78.74 |
1648.23 |
II |
NHPC |
|
|
|
|
|
|
|
|
19 |
BAIRA
SIUL |
302 |
52.87 |
47.33 |
38.80 |
14.22 |
11.72 |
0.84 |
26.78 |
20 |
SALAL |
854 |
176.74 |
26.63 |
32.90 |
26.74 |
28.10 |
2.63 |
57.47 |
21 |
TANAKPUR |
67 |
46.82 |
16.17 |
59.40 |
4.30 |
3.98 |
0.33 |
8.61 |
22 |
CHAMERA-I |
223 |
199.53 |
11.04 |
68.90 |
12.52 |
15.36 |
1.28 |
29.16 |
23 |
CHAMERA-II |
168 |
347.37 |
12.85 |
133.20 |
25.36 |
22.38 |
1.52 |
49.26 |
24 |
URI |
382 |
274.26 |
12.95 |
61.00 |
20.18 |
23.30 |
3.32 |
46.81 |
25 |
DHAULIGANGA |
138 |
177.02 |
12.16 |
89.70 |
12.23 |
12.38 |
1.19 |
25.79 |
26 |
DULHASTI |
248 |
497.40 |
11.43 |
150.00 |
32.30 |
37.20 |
4.95 |
74.45 |
27 |
URI-II |
50 |
|
|
280.30 |
|
14.02 |
|
14.02 |
28 |
SEWA-II |
76 |
|
|
280.30 |
|
21.30 |
|
21.30 |
29 |
PARBATI-III |
15 |
|
|
280.30 |
|
4.20 |
|
4.20 |
30 |
CHAMERA-III |
11 |
|
|
280.30 |
|
3.08 |
|
3.08 |
|
Sub Total |
2534 |
|
|
|
147.86 |
197.02 |
16.06 |
360.93 |
III |
NPC |
|
|
|
|
|
|
|
|
31 |
NAPP |
87 |
|
12.82 |
203.97 |
|
17.75 |
|
17.75 |
32 |
RAPP-3 |
229 |
|
23.95 |
286.62 |
|
65.64 |
|
65.64 |
33 |
RAPP-4 |
233 |
|
24.83 |
286.62 |
|
66.78 |
|
66.78 |
34 |
RAPP-5&6 |
296 |
|
|
286.62 |
|
84.84 |
|
84.84 |
|
Sub
Total |
845 |
|
|
|
|
235.00 |
|
235.00 |
IV |
Other
Sources |
|
|
|
|
|
|
|
|
35 |
Co-Gen.
incl. Jalkheri |
203 |
|
|
383.46 |
|
77.84 |
|
77.84 |
36 |
Short
term power purchase within |
152 |
|
|
415.88 |
|
63.21 |
|
63.21 |
37 |
NJPC |
706 |
1312.43 |
14.63 |
114.10 |
109.13 |
80.55 |
9.67 |
199.36 |
38 |
Tehri* |
253 |
657.00 |
8.86 |
250.00 |
33.06 |
63.25 |
1.69 |
98.00 |
|
Sub-total |
1314 |
|
|
|
142.19 |
284.86 |
11.37 |
438.41 |
V |
Net
Banking |
|
|
|
|
|
|
|
|
39 |
HPSEB |
-95 |
|
|
290.00 |
|
-27.55 |
|
-27.55 |
40 |
Rajasthan |
-10 |
|
|
290.00 |
|
-2.90 |
|
-2.90 |
41 |
UPCL |
10 |
|
|
290.00 |
|
2.90 |
|
2.90 |
42 |
J&K |
-33 |
|
|
290.00 |
|
-9.57 |
|
-9.57 |
43 |
Net
Banking Through Traders |
205 |
|
|
290.00 |
|
59.45 |
|
59.45 |
44 |
Open Access
Charges of Banking (39 to 43) |
|
|
|
|
|
|
6.95 |
6.95 |
|
Sub
Total |
77 |
|
|
|
|
22.33 |
6.95 |
29.28 |
VI |
New
Plants |
|
|
|
|
|
|
|
|
45 |
Koteshwar
(THDC) |
30 |
|
|
262.50 |
9.59 |
7.88 |
0.22 |
17.69 |
46 |
|
367 |
|
|
262.70 |
|
96.41 |
|
96.41 |
47 |
Raghunathpur
TPS (DVC) ER |
47 |
|
|
262.70 |
|
12.35 |
|
12.35 |
48 |
Bawana
Gas (NR) |
827 |
|
|
309.05 |
|
255.58 |
|
255.58 |
49 |
Nagarjuna
TPS (SR) |
440 |
|
|
262.70 |
|
115.59 |
|
115.59 |
|
Sub
Total |
1711 |
|
|
|
9.59 |
487.81 |
0.22 |
497.62 |
VII |
Traders
(Long Term) |
|
|
|
|
|
|
|
|
50 |
Tala |
106 |
|
|
184.00 |
|
19.50 |
|
19.50 |
51 |
Baghlihar |
624 |
|
|
369.00 |
|
230.26 |
|
230.26 |
52 |
Malana-II |
251 |
|
|
264.00 |
|
66.26 |
|
66.26 |
53 |
Maithon
(TATA) |
370 |
|
|
258.00 |
|
95.46 |
|
95.46 |
|
Sub-total |
1351 |
|
|
|
|
411.48 |
|
411.48 |
VIII |
Traders
(Short Term) |
|
|
|
|
|
|
|
|
54 |
Short-term
purchase |
0 |
|
|
|
|
0.00 |
|
0.00 |
55 |
Open
Access Charges (Traders) |
|
|
|
|
|
|
14.35 |
14.35 |
VII |
Other
Charges |
|
|
|
|
|
|
|
|
56 |
PGCIL |
|
|
|
|
|
276.05 |
|
276.05 |
|
Total |
15619 |
|
|
|
699.97 |
3083.72 |
127.68 |
3911.37 |
* - Fixed Charges as per bill are Rs.18000/MW/day and computed as Rs.657
crore per year taking plant capacity as 1000 MW.
The Commission approves power
purchase cost at Rs.3774.12 (3911.37-137.25) crore for power purchase of 15070 MUs
(gross).
4.9 Employee Cost
4.9.1 The Board, in the ARR, has projected
net employee cost at Rs.3566.57 crore for 2010-11, net of capitalization of
Rs.126.00 crore. This is inclusive of Rs.525 crore for the first instalment of
arrears of pay and also includes Rs.450 crore on account of pay revision for
2010-11. The details are tabulated below:
Table 4.22: Employee cost projected by
the Board
(Rs. crore)
Employee Cost |
FY 08-09 (Actual) |
FY 09-10 |
FY 10-11 (Projected) |
RE (As per ARR) |
|||
1 |
2 |
3 |
4 |
Gratuity |
100.48 |
109.99 |
122.47 |
Pension + Commuted pension |
418.24 |
561.71 |
604.86 |
Leave encashment |
59.2 |
73.93 |
81.83 |
Any other expense |
81.28 |
81.97 |
86.07 |
BBMB |
58.18 |
70.92 |
74.47 |
Terminal benefits – Total (1) |
717.38 |
898.52 |
969.70 |
Salaries & other expenses |
|
|
|
Basic salaries |
911.88 |
1162.65 |
1364.63 |
Overtime |
9.39 |
11.52 |
12.10 |
DA |
468.35 |
459.04 |
408.49 |
Bonus/generation incentive |
50.82 |
90.86 |
113.94 |
Payment under Workmen’s Compensation Act |
0.24 |
0.17 |
0.18 |
Ex-gratia |
-0.12 |
0 |
0 |
Other allowances
(Fixed Medical, others) allowances, Medical Reimbursement) |
161.92 |
243.97 |
298.53 |
Sub-Total (2) |
1602.48 |
1968.21 |
2197.87 |
Gross Employee cost (1+2) |
2319.86 |
2866.73 |
3167.57 |
Less: Capitalization |
117.82 |
120 |
126 |
Net Employee cost |
2202.04 |
2746.73 |
3041.57 |
Pay Commission arrears |
|
|
525 |
Net Employee cost |
2202.04 |
2746.73 |
3566.57 |
Clarifying the basis on which these costs have been
worked out, the Board has stated that:
·
It has not considered WPI indices for projecting the expenses in 2010-11.
Instead, an increase of 5% has been considered for making such projections.
However, for making the projections, the base year (2009-10) expenses were
considered as inclusive of Rs.450.00 crore being the annual recurring liability
on account of pay revision.
·
Impact of pay arrears is considered to be disbursed in two equal yearly
instalments starting from 2010-11. The one time liability has been estimated to
be around Rs.525.00 crore in 2010-11 and a similar amount will be considered in
the tariff petition for 2011-12.
·
The aforementioned assumptions have also been used to project the
escalation in terminal benefits as also the expenses of staff on deputation to
the BBMB.
4.9.2
The Board has submitted that the
initial report on manpower study (for determining manpower requirements across different
functions such as Generation, Transmission, Distribution, Accounts, Finance,
Secretariat, Vigilance and all other departments) has recently been submitted
by the consultants. It has been further stated that the Board is currently in
the process of analyzing the findings of the reports based on which it will
consider proceeding to the second phase. The final report of the study will be
shared with the Commission, once it is available.
4.9.3
The Board has also intimated that
it plans to roll out a pilot project in Patiala city to rationalize manpower.
The project involves reorganization of the distribution staff under a refined
two tier system wherein the existing staff will be reorganized on functional basis
to handle technical and commercial functions separately. The project does not
involve any additional financial liability and would lead to a reduction of
around 10-12% in the deployed workforce. If successful, the project will be
replicated in the entire State.
The Board has
admitted that there may not be any measure to right size the manpower of the
utility immediately but it would implement firm measures to control the
manpower costs in the medium and long term. Reference has also been made to a
host of other measures being undertaken to control employee cost including
freezing fresh recruitment, complete ban on creation of new posts, outsourcing
of security works, reduction in generation incentive by 10%, withdrawal of
compassionate appointments to dependents of deceased employees, getting current
or new expansion projects executed through the existing manpower which has
enhanced the employee productivity etc. The Board has also clarified that new
technical personnel have been inducted to ensure high standards of employee
productivity.
4.9.4
The amended provisions of the PSERC Tariff Regulations, provide for
determination of employee cost in two parts:
·
Terminal benefits including BBMB share on actual basis.
·
Increase in other expenses limited to increase in Wholesale Price
Index.
The Board has claimed net employee cost of
Rs.3041.57 crore for 2010-11 inclusive of terminal benefits of Rs.969.70 crore
which includes
impact of pay revision. The Commission also
notes that the terminal benefits pertaining to employees who were to retire in
the period January 2010 to 31st March 2010 would become payable in
the current year. Accordingly the terminal benefits of Rs.31.72 crore, as
reported by the Board, pertaining to the period January 2010 to March 2010 are
also allowed. Thus, the Commission allows terminal benefits of Rs.1001.42
(969.70 + 31.72) crore.
As per amended
regulations, increase in other employee cost is to be limited to average
4.9.5 The Commission also
observes that the Board has claimed Rs.375 crore on account of pay revision
(other than terminal/pension benefits) in the year 2010-11. The Commission has
already decided in para 3.10.5 of this Order to reduce the amount claimed on
account of pay revision by 28.48%. Applying the same rationale to the claimed
enhancement of Rs.375 crore in 2010-11, the Commission disallows an amount of
Rs.106.80 crore. The allowable cost on this account, therefore, comes to
Rs.268.20 crore.
4.9.6 The Board has also claimed Rs.525 crore in 2010-11
as arrears of pay based on the recommendations of the 5th Pay
Commission. As decided in para 4.9.5 above, the Commission disallows an amount
of Rs.149.52 crore, being 28.48% of the total claim of the Board. Accordingly,
the claim of arrears of pay is restricted to Rs.375.48 crore.
4.9.7 The Commission notes that in
para 4.9.4 of the Tariff Order for 2009-10, the employee cost allowed to the
Board in that year was approved at Rs.1856.60 crore against a cost of Rs.2113.36 crore worked out as per the
amended Tariff Regulations. This deduction was effected on account of the continuing
failure of the Board to conclude the study reportedly commissioned for
determining manpower norms afresh and taking further action on that basis. Even
though, it is now reported that a preliminary report of the study has since
been submitted, the fact remains that the position remains substantially the
same even now as no final conclusions of the study are available nor has any
policy decision been taken in this respect. For these reasons, the Commission
deems it appropriate that a further disallowance needs to be made in the
employee cost allowable to the Successor Entities till such time as the study
is concluded and action based thereon initiated. However, taking into account
the fact that disallowances have already been made on the Board’s claim on
account of pay revision and arrears, the Commission limits further disallowance
to only Rs.100 crore as discussed in para 3.10.6.
The Commission, therefore,
approves employee cost of Rs.2989.83 (2446.15+268.20+375.48-100) crore for 2010-11 to the
Successor Entities.
4.10 Repair
and Maintenance (R&M) Expenses
4.10.1 The Board has projected net R&M expenses
at Rs.429.24 crore inclusive of Rs.56.00 crore for additional assets likely to
be added during the year for 2010-11. The Board has clarified that additional
R&M expenses have been calculated taking into account the additional assets
likely to be added during the year as envisaged in Regulation 28 (6) of the
PSERC Tariff Regulations. Further, the Board has considered 5% escalation on the
revised estimates of R&M expenses for 2009-10 to project R&M expenses
for 2010-11.
4.10.2 The
Board has stated that although the expenses for 2010-11 are projected with 5%
escalation but the assets created by PSEB relating to generation, transmission
and distribution are largely old assets which require significant amount of
repair and maintenance. The Board submitted that with ageing, the quantum of such expenses is
bound to increase in future which is further influenced by a number of other
factors such as overloading of equipments leading to
equipment failures, availability of time for system maintenance, timely availability of raw materials etc. According to the Board, while allowance of such
expenditure based on increase in WPI indices may cover part of such expenses,
the same may not be able to address the other factors leading to increase in
the overall quantum of such expenses.
4.10.4 As
regards claim of Rs.56 crore of the Board towards R&M expenses for additional
assets of Rs.2778.28
crore likely to be added during 2010-11 in terms of the PSERC Tariff Regulations, the Commission is of the view that the increase in R&M expenses demanded
on this account cannot be allowed at this stage and will be considered at the
time of review next year.
As
the claim of the Board of Rs.373.24 (429.24-56.00) crore for the existing
assets is within the allowable limit, R&M expenses are allowed at Rs.373.24
crore to the Successor Entities.
The Commission,
therefore, approves Rs.373.24 crore as R&M expenses for 2010-11.
4.11 Administration and General (A&G) Expenses
4.11.1 The Board has projected Administration and General
expenses at Rs.79.75 crore, net of capitalization of Rs.21.00 crore, for the
year 2010-11.
4.11.2 The Board has submitted that it has been consistently making efforts to
reduce the A&G costs. This has resulted in an increase of only 1.81% under
this head from Rs.69.92 crore in FY 07-08 to Rs.70.96 crore in FY 08-09. The
Board has stated that it has not considered the WPI increase for projections of
the said expenses as it believes that these expenses are incidental to
governing the entire power system operations in the State.
4.11.3 Regulation 28 (4) (b) of the PSERC Tariff Regulations provides for
allowing annual increase in the approved O&M expenses (which include
A&G expenses) based on average increase in WPI over the year. The base
A&G expenses for 2010-11 work out to Rs.78.84 (75.95+2.89) crore which
include approved A&G expenses of Rs.75.95 crore for 2009-10 and an amount
of Rs.2.89 crore being A&G expenses allowed for six months on fixed assets
approved as additions during the year. As discussed in para 4.9.4, the WPI
increase for the year 2010-11 is not available, therefore, the Commission
allows an adhoc increase of 5% over the base A&G expenses. Accordingly,
Rs.82.78 crore is determined as allowable A&G cost for assets worth
Rs.19934.20 crore as on April 1, 2010.
4.11.4 However, the Board has claimed A&G
expenses of Rs.79.75 crore for 2010-11. The Commission notes that the claim of
the Board is within the permissible norms prescribed in Regulation 28 of the
PSERC Tariff Regulations and is, therefore, allowed.
The Commission accordingly, approves the A&G expenses of Rs.79.75 crore for 2010-11 to the Successor Entities.
4.12 Depreciation Charges
4.12.1 The Board has estimated depreciation
charges of Rs.952.44 crore for the year 2010-11 based on the assets of Rs.21591.16
crore as on April 1, 2010. However, as discussed in para 3.11.3 of this Order,
the value of total assets as on April 1, 2010 is determined at Rs.19934.20
crore. The Board has projected additions of Rs.3159.40 crore to the fixed
assets against which the Commission has approved additions of Rs.1444.08 crore
which are apportioned under different categories in the same ratio as projected
by the Board in the ARR.
4.12.2 The Commission
applies the average percentage rates of depreciation (net) for 2010-11 which
are derived from the audited accounts for 2008-09. By applying these rates,
depreciation for 2010-11 works out to Rs.863.68
crore
for assets of Rs.19934.20 crore as on April 1, 2010. Details of function-wise
depreciation charges are given in Table 4.23.
Table-4.23: Depreciation charges
Sr. No. |
Item |
Assets as on April 1, 2009 |
Rate (%) |
Depreciation charges for 2009-10 |
Assets as on April 1, 2010 |
Rate (%) |
Depreciation charges for 2010-11 |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
1 |
Thermal
|
4319.19 |
4.543% |
196.22 |
4879.64 |
4.543% |
221.68 |
2 |
Hydro
|
5957.44 |
2.281% |
135.89 |
5964.37 |
2.281% |
136.05 |
3 |
Internal
Combustion |
2.68 |
0.00% |
0.00 |
2.68 |
0.00% |
0.00 |
4 |
Transmission
|
2040.46 |
4.884% |
99.66 |
2340.25 |
4.884% |
114.30 |
5 |
Distribution
|
5975.25 |
5.971% |
356.78 |
6506.38 |
5.971% |
388.50 |
6 |
Others |
195.10 |
1.306% |
2.55 |
240.88 |
1.306% |
3.15 |
|
Total
|
18490.12 |
|
791.10 |
19934.20 |
|
863.68 |
The Commission accordingly approves depreciation
charges of Rs.863.68 crore for 2010-11 to the Successor Entities.
4.13 Interest and Finance Charges
4.13.1 The Board has
claimed interest and finance charges of Rs.1923.01 crore (net) as per details
given in Table 4.24 below.
Table- 4.24: Projected Interest & Finance charges
Sr. No. |
Source of loan |
FY 2010-11 (Rs. crore) |
1 |
Institutional
loans |
1169.66 |
2 |
GoP Loans |
0.00 |
3 |
GPF |
120.00 |
4 |
Lease rentals |
0.04 |
5 |
Interest to
Consumers |
176.00 |
6 |
Total |
1465.70 |
7 |
Working
Capital Loans |
596.90 |
8 |
Grand Total |
2062.60 |
9 |
Less:
Capitalization |
154.59 |
10 |
Net Interest |
1908.01 |
11 |
Finance charges |
15.00 |
12 |
Total Interest
and Finance charges |
1923.01 |
The Interest and
Finance charges allowed to the Successor Entities are discussed in
the ensuing paragraphs.
4.13.2 Investment Plan
The Board has
proposed an investment plan of Rs.4944.22 crore in the ARR for 2010-11 which
includes an investment of Rs.227.50 crore under R&M of GNDTP Bathinda unit
III & IV based on an RLA study. With
a view to reduce T&D losses (including APDRP Schemes) and improve its power
system performance, the Board has also proposed to spend Rs.2906.76 crore in
2010-11 under Transmission & Distribution head. Further, the Board has
included the investment of Rs.600 crore for Gidderbaha Thermal Plant which is
being privately developed on BOO basis. In the past Tariff Orders, the
Commission has not considered the investment on private projects developed on
BOO basis to determine the capital Investment Plan. After excluding capital
expenditure towards Gidderbaha Thermal Plant, net investment requirement of the
Successor Entities works out to Rs. 4344.22(4944.22-600)
crore.
It is noted that for
2009-10, an Investment Plan of Rs.2724.55 crore was projected by the Board in
the ARR for 2010-11 against which actual expenditure reported by the Board till
January 2010 is Rs.1476.44 crore. The Commission has approved Investment Plan
of Rs.1800 crore for 2009-10 based on the actual expenditure incurred by the
Board upto January 2010. The Commission observes that the Board invariably
proposes an ambitious Investment Plan every year but actual capital expenditure
is no where near the proposed plan. However, considering the need of the Successor Entities to make substantial investments in transmission and
distribution network for providing uninterrupted and reliable power supply to
the consumers and considering the level of approved investments in previous
years, the Commission now allows an investment plan of Rs.2500 crore for
2010-11. However,
increase in actual capital investment, if any, will be considered by the
Commission during review. After adjustment of consumers’ contribution of
Rs.362.65 crore considered at the level of 2009-10, the actual loan requirement
works out to Rs.2137.35 (2500-362.65) crore.
In the recent past, the
Commission has been accepting the opening balance of loans as projected by the
Board to work out interest on proportionate basis for the loans allowable. This
methodology was adopted since the loans estimated by the Commission were close
to the figures claimed by the Board. However, during processing of ARR for
2010-11, it was observed that the closing balance of outstanding loans of the Board
as on 31st March, 2010 was Rs.9091.15 crore against which the
Commission had worked out the closing balance at Rs.6672.77 crore. The
difference between the two figures being very high, the Commission deems it
prudent to adopt the balance of loans as per its own estimation depicted in
Table 3.13 for calculation of interest for the year 2010-11. Accordingly, interest
on loans other than WCL & GoP loans works out to Rs.764.33 crore on
proportionate basis (considering net receipt of loans for six months on an
average during the year) as given in Table 4.25.
Table 4.25 Interest
and Finance charges
(Rs. crore)
Sr. No. |
Particulars |
Loans as on 31.3.10 |
Receipt of loans |
Repayment of loans |
Loans as on 31.3.11 |
Amount of interest |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
1 |
As per data furnished by Board (other than WCL & GoP loans) |
9091.15 |
4889.70 |
1172.23 |
12808.62 |
1169.66 |
2 |
Approved by Commission (other than WCL & GoP loans) |
6672.77 |
2137.35 |
1172.23 |
7637.89 |
764.33 |
4.13.3 Interest on GoP Loans
The Board has shown outstanding GoP loans of Rs.1660.52 crore as on April
1, 2010. However, as per GoP letter dated March 10, 2010, loans of Rs.1140.43
crore have been adjusted by the GoP against the unpaid subsidy. Thus,
outstanding GoP loans as on April 1, 2010 are reduced to Rs.520.09 crore. By
applying an average rate of 13.20% per annum, interest payable on outstanding
loans works out to Rs.68.65 crore for the year 2010-11. An amount of Rs.162.34
crore is disallowed on account of diversion of capital funds for revenue
purposes and attributed to the GoP as discussed in para 4.13.11. After
adjusting the interest of Rs.68.65 crore against disallowed interest of
Rs.162.34 crore, the GoP is liable to pay Rs.93.69 (162.34-68.65) crore to the
Successor Entities. This amount is carried forward to para 5.4.
4.13.4 Interest on Loans taken to replace the GoP Loans
As decided earlier in para 2.14.5 of this Order, interest on loans of Rs.1362 crore raised to replace re-called GoP loans
adjusted against unpaid subsidy by the GoP is allowed at an average rate of
9.58% per annum as claimed by the Board for commercial loans for 2010-11. Thus,
interest of Rs.130.48 crore is approved on this account.
Besides
this, the GoP has also adjusted loans of Rs.1140.43 crore against unpaid
subsidy vide letter dated March 10, 2010. The Commission is of the considered
view that the Successor Entities will have to raise loans of equivalent
amount from the market to meet shortage of funds on this account. Therefore,
the Commission allows interest of Rs.109.25 crore @ Rs.9.58% per annum for 2010
-11 on this account.
Thus,
Rs.239.73 (130.48+109.25) crore is allowed as interest on loans taken to
replace the recalled/adjusted GoP loans.
The
Commission observes that the recall/adjustment of GoP loans, results in the
Board raising money at lower rates of interest as compared to the interest
presently payable. However, the Board has currently been obtaining considerable
relief from the payment of interest to GoP as a substantial amount of interest
otherwise payable is being disallowed on account of diversion of capital loans
towards revenue purposes. As will be evident from para 3.14.3 of this Order,
the interest payable against GoP loans before adjustment would be Rs.210.46
crore against the actual interest liability of Rs.48.12 crore. Given the
financial position, GoP needs to seriously consider compensating the Successor
Entities to the extent they are disadvantageously placed on account of
adjustment of GoP loans against subsidy payable.
4.13.5 Interest on G.P. Fund
The Board has claimed
interest of Rs.120 crore on GP Fund accumulations. The interest on GP Fund
being statutory payment is allowed.
4.13.6 Lease Rental
The Board has
claimed lease rental of Rs.0.04 crore which is allowed for 2010-11.
4.13.7 Interest on Consumers’ Security Deposits
According to
Regulation 17 of the PSERC (Electricity Supply Code & Related Matters),
Regulations, 2007, the consumers of the Board are to be paid interest on their
security deposits with the Board w.e.f. January 1, 2008. Accordingly, the Commission
in its Tariff Order for 2009-10 approved the interest on security deposits
payable during the year. Further, interest on consumers’ deposits of Rs. 164.21
crore has been allowed for 2009-10 as discussed in para 3.14.8.
As regards the
Board’s claim of interest of Rs.176 crore due for the year 2010-11, the same
will be payable during the year 2011-12 and will be considered by the Commission
in the Tariff Order for the subsequent year.
4.13.8 Finance Charges
The Board has claimed
finance charges of Rs.15 crore which works out to 0.31% of the proposed fresh
borrowings of Rs.4889.70 crore. The Commission has, however, approved actual loan
requirement of Rs.2137.35 crore for investment purposes. The finance charges on
this loan requirement at a rate of 0.31% work out to Rs. 6.63 crore which are
approved for 2010-11.
4.13.9 Capitalization of Interest
and Finance Charges
In its previous Tariff
Orders, the Commission allowed capitalization of interest, excluding interest
charges on working capital, in the ratio of net works in progress to total
capital expenditure. Based on the same principle, the Commission approves
capitalization of interest and finance charges of Rs.170.22 crore for the year
2010-11.
4.13.10 Working
Capital
The
Board has projected a working capital requirement of Rs.1982.90 crore and
estimated the interest charges at Rs.242.91 crore by applying a rate of 12.25%
based on the short term
Table 4.26: Working
Capital Requirement
(Rs.crore)
Particulars |
Approved by Commission |
Two
months Fuel Cost |
561.73 |
One
month Power Purchase Cost |
314.51 |
One
month Employee Cost |
249.15 |
One
month Administration and General Expenses |
6.65 |
One
month Repair and Maintenance Expenses |
31.10 |
Maintenance spares @ 15% of
O&M Expenses (2989.83+373.24+79.75) |
516.42 |
Total
requirement for working capital |
1679.56 |
Interest
Rate |
12.25% |
Interest |
205.75 |
Accordingly, the
Commission approves interest of Rs.205.75 crore on working capital requirement
for 2010-11.
4.13.11 Diversion of Capital
funds
The Commission, in para
2.14.11 of this Order has re-determined the diversion of capital funds for
revenue purposes at Rs.2624.76 crore based on the Boards’ audited accounts for
2008-09. Net diversion carrying interest
bearing liability of Rs.1987.41 crore is estimated on this basis for the year
2010-11. Applying an interest @ 13.20% (being average rate of interest on GoP
loans) on diverted funds of Rs.1987.41 crore works out to Rs.262.34 crore for
2010-11, which is disallowed.
In this regard, the
Commission retains its decision to disallow interest cost of Rs.100 crore of
the Successor Entities and further decides that the balance
disallowance of interest of Rs.162.34 crore is to the account of the GoP.
Accordingly, after adjustment of this disallowed interest of Rs.162.34 crore
against the interest due on GoP loans amounting to Rs.68.65 crore worked out in
para 4.13.3, interest payable by the GoP to the Successor
Entities
works out to Rs.93.69 crore. This is being carried forward to para 5.4.
Table 4.27:
Interest and Finance charges
(Rs.
crore)
Sr. No. |
Particulars |
Loans as on 31.3.10 |
Receipt of loans |
Repayment of loans |
Loans as on 31.3.11 |
Amount of interest |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
1 |
Approved by Commission (other than WCL & GoP
loans) |
6672.77 |
2137.35 |
1172.23 |
7637.89 |
764.33 |
2 |
GoP loans |
520.09 |
0 |
0 |
520.09 |
68.65 |
3 |
Int. on loans taken to replace GoP loans of
Rs.1362 crore and for
adjusted loans of Rs.1140.43 crore |
|
|
|
|
239.73 |
4 |
Interest on GPF |
|
|
|
|
120 |
5 |
Lease rental |
|
|
|
|
0.04 |
6 |
Interest to consumers |
|
|
|
|
0 |
7 |
Total (1+2+3+4+5+6) |
7192.86 |
2137.35 |
1172.23 |
8157.98 |
1192.75 |
8 |
Add Finance charges |
|
|
|
|
6.63 |
9 |
Total gross Interest & Finance charges |
|
|
|
|
1199.38 |
10 |
Less capitalization |
|
|
|
|
170.22 |
11 |
Net Interest and Finance charges (9-10) |
|
|
|
|
1029.16 |
12 |
Interest on working capital |
|
|
|
|
205.75 |
13 |
Total Interest (11+12) |
|
|
|
|
1234.91 |
14 |
Less: Disallowed on a/c
of diversion: a) Board - Rs.100 crore b) GoP - Rs.162.34
crore |
|
|
|
|
262.34 |
15 |
Balance Interest and Finance charges (13-14) |
|
|
|
|
972.57 |
Accordingly, the Commission approves net Interest and
Finance charges of Rs.972.57 crore for 2010-11.
4.14
Interest Cost of
the Approved Gaps for 2008-09 and 2009-10
4.14.1 In the ARR of
2010-11, the Board submitted that it has to raise short term loans from the
market for meeting the gap on account of revenue deficits. The Commission,
accordingly, allows interest on the approved gaps determined during review and
true up.
4.14.2 In the Tariff Order of 2009-10,
the Commission allowed interest of Rs.209.96 crore for the year 2009-10 for the
approved consolidated gaps of Rs.439.51 crore upto the year 2006-07, Rs.803.31 crore for the year 2007-08 and Rs.471.08 crore for the year 2008-09.
4.14.3 The Commission
notes that on the basis of review for the year 2008-09 in the Tariff Order of
2009-10, there was a revenue surplus of Rs.332.23 crore for the year 2008-09.
However, in the true up of 2008-09 which forms a part of this Order, there is
an approved gap (deficit) of Rs.174.06 crore which would be available to the Successor Entities as revenue only after the tariff of 2010-11 is revised and
hence there is justification for allowing carrying costs for this gap for a
total period of two years consisting of six months for 2008-09, one year for
2009-10 and six months for 2010-11. Accordingly, by applying a rate of 12.25%,
being the short term
4.14.4 The Commission
notes that on the basis of review for 2009-10, the Commission has determined a
gap (deficit) of Rs.253.26 crore. Accordingly, by applying a rate of 12.25%,
being the short term
The Commission accordingly approves total carrying cost of Rs.73.66 (42.64+31.02) crore for the approved gaps of Rs.
174.06 crore of 2008-09 and Rs.253.26
crore of 2009-10.
4.15 Return on Equity
In the ARR for
2010-11, the Board has claimed ROE @ 15.5 % (pre-tax) to be grossed up to
23.48% as provided in the CERC Regulations. The PSERC Tariff Regulations
stipulate that CERC Regulations be followed ‘as far as possible’. The
Commission notes that the Board has been unable to effect requisite
improvements in critical performance parameters such as T&D losses and
employee cost. On account of aforementioned reasons, the Commission finds no
justification to allow ROE as per CERC Regulations. The Commission, thus,
retains ROE at 14% and allows ROE at Rs.412.46 crore.
The Commission, therefore, approves Return on Equity of
Rs.412.46 crore for 2010-11 to the Successor Entities.
4.16 Non-Tariff
Income
The Board has projected non-tariff
income of Rs.519.01 crore for 2010-11. This is inclusive of Rs.70.35 crore on
account of theft of energy which is being considered towards Revenue of the Successor Entities. Therefore, the non-tariff income of the Successor Entities works out to Rs.448.66 (519.01-70.35) crore.
The Commission, therefore, approves the Non-Tariff
Income of Rs.448.66 crore for 2010-11.
4.17 Revenue from Existing Tariff
The Revenue from
existing tariff projected by the Board for the year 2010-11 is Rs.13119.24
crore including revenue from AP consumption. As discussed in para 4.16 above,
an amount of Rs.70.35 crore on account of theft of energy is to be counted
towards Revenue of the Successor Entities. Therefore, as per
Board’s estimates, Revenue from existing tariff works out to Rs.13189.59
(13119.24+70.35) crore. However, the
expected revenue from existing tariff on the basis of sales approved by the
Commission works out to Rs.12740.82 crore as given in Table 4.28.
Table 4.28:
Revenue from Existing Tariff
Sr. No. |
Category of consumers |
Approved by the Commission |
||
Energy sales (MUs) |
Tariff rates (paise/unit) |
Revenue (Rs. in crore) |
||
1 |
2 |
3 |
4 |
5 |
1 |
Domestic |
|||
a) |
Up to 100 units |
2855 |
282 |
805.11 |
b) |
101-300 units |
3115 |
428 |
1333.22 |
c) |
Above 300 units |
1895 |
452 |
856.54 |
|
Total (a+b+c) |
7865 |
|
2994.87 |
2 |
NRS |
2405 |
491 |
1180.86 |
3 |
Public lighting |
136 |
482 |
65.55 |
4 |
Industrial Consumers |
|||
a) |
SP |
759 |
392 |
297.53 |
b) |
MS |
1541 |
433 |
667.25 |
c) |
LS |
9093 |
433 |
3937.27 |
|
Total (a+b+c) |
11393 |
|
4902.05 |
5 |
Bulk Supply |
|||
a) |
HT |
463 |
436 |
201.87 |
b) |
LT |
33 |
463 |
15.28 |
|
Total (a+b) |
496 |
|
217.15 |
6 |
Railway Traction |
138 |
512 |
70.66 |
7 |
Common pool |
302 |
|
100.00 |
8 |
Outside State |
53 |
|
5.40 |
9 |
Total (1 to 8) |
22788 |
|
9536.54 |
10 |
AP |
10305 |
285 |
2936.93 |
11 |
Total (9+10) |
33093 |
|
12473.47 |
12 |
Add: PLEC, MMC, Other charges |
|
|
197.00 |
13 |
Add: Recovery on account of theft of
energy |
|
|
70.35 |
14 |
Grand Total |
33093 |
|
12740.82 |
Note: The
slab-wise energy sales for domestic supply & Bulk Supply are taken in the
same ratio as for 2009-10.
The Commission, as such, approves revenue from existing
tariff at Rs.12740.82 crore for 2010-11.
4.18 Revenue requirement
The summary of the revenue
requirement of the Successor Entities for the year
2010-11 as analyzed in the preceding paragraphs is given in Table 4.29.
Table 4.29: Revenue
Requirement for 2010-11
(Rs. crore)
Sr. No. |
Item of expense |
Proposed by the
Board |
Approved by the
Commission |
1 |
2 |
3 |
4 |
1 |
Cost of fuel |
3622.83 |
3370.40 |
2 |
Cost of power
purchase |
5137.61 |
3774.12 |
3 |
Employee cost |
3566.57 |
2989.83 |
4 |
R&M expenses |
429.24 |
373.24 |
5 |
A&G expenses |
79.75 |
79.75 |
6 |
Depreciation |
952.44 |
863.68 |
7 |
Interest charges |
1923.01 |
972.57 |
8 |
Return on Equity |
681.56 |
412.46 |
9 |
Total revenue
requirement |
16393.01 |
12836.05 |
10 |
Add consolidated
gap for 2009-10 |
3527.49 |
1230.63 |
11 |
Gross revenue
requirement (9+10) |
19920.50 |
14066.68 |
12 |
Less Non-Tariff
income |
448.66 |
448.66 |
13 |
Less Revenue from
existing tariff |
13189.59 |
12740.82 |
14 |
Net Gap for
2010-11 |
(-)6282.25 |
(-)877.20 |
15 |
Add carrying cost
of Gaps |
|
73.66 |
16 |
Total gap for
2010-11 |
(-)6282.25 |
(-)950.86 |
17 |
Energy sales
(MUs) |
34376 |
33093 |
The total cumulative gap (deficit) for 2010-11 is
determined at Rs.950.86 crore. The Annual Revenue Requirement for 2010-11 is
assessed at Rs.12836.05 crore with energy
sales of 33093 MUs. The average cost of supply with this revenue requirement
comes to 387.88 paise/unit. The combined average cost of supply works out to 427.29 paise/unit (14140.34 /33093 MUs) after taking
into account the ARR of Rs. 12836.05 crore for
2010-11, approved gap of Rs.1230.63 crore for 2009-10 and carrying cost of
Rs.73.66 crore for the approved gaps.
Chapter 5
Determination of
Tariff
5.1 Annual Revenue Requirement
5.1.1 The Commission has
determined the ARR of the Successor Entities for the year 2010-11 at Rs.12836.05
crore. It has simultaneously undertaken a true up of the year 2008-09
consequent upon the availability of audited accounts which has resulted in a cumulative
revenue gap (deficit) of Rs.977.37 crore. The review of 2009-10 indicates a deficit
of Rs.253.26 crore, resulting in a consolidated gap of Rs.1230.63 crore at the
end of 2009-10.
5.1.2 The combined impact
of these exercises and the approved carrying cost of gaps indicate a gross
revenue requirement of Rs.14140.34 crore for the year 2010-11 of the Successor
Entities. After making adjustment on account of non-tariff income and revenue
from tariff at the existing level, the revenue gap accepted by the Commission for
2010-11 is Rs.950.86 crore.
5.2 Determination of
Retail tariff
5.2.1 In determining
tariff, the Commission is guided by the principles laid down in Section 61 of
the Act as well as its own Regulations which provide the framework for working
out the ARR of a Power Utility and tariff for different categories of
consumers. The Commission has also kept in mind the relevant aspects of the
National Electricity Policy, National Tariff Policy, the norms adopted by it in
earlier Tariff Orders and inputs received from consumers during the process of
public hearings.
5.2.2 Income from tariff
at existing rates taken into account for working out the percentage increase in
tariff required to cover the gap, does not include income from sales to common
pool consumers, Outside State sales and Peak Load Exemption Charges (PLEC).
5.2.3 The consolidated
revenue gap of Rs.950.86 crore for the year 2010-11 of the Successor Entities
is, thus, required to be covered with an increase of 7.58% in the existing
tariff including MMC and theft of energy charges across all categories, except
common pool consumers, Outside State sales and PLEC.
5.2.4 The provisions of
the Act, Tariff Policy and the Commission’s own Regulations require that there
be a gradual reduction of cross-subsidies. Therefore, with this end in view,
the Commission decides to increase the tariff of Domestic Supply consumers with
consumption upto 100 unit, by 29 paise/unit. In the case of AP consumers, the
increase will be 35 paise/unit, being the highest subsidized category. The
tariff for other consumer categories and MMC will increase by 5.72% and 7.58%
respectively. There will be no change in PLEC. The existing and revised tariffs
are indicated in Table 5.1.
Table 5.1: Existing and Revised
Tariff for the Year 2010-11
Sr. No. |
Category of consumers |
Existing Tariff |
Revised Tariff approved by the
Commission |
||
Energy Rate (paise/kwh) |
|
Energy Rate (paise/kwh) |
MMC(Rs) |
||
A) |
PERMANENT
SUPPLY |
|
|
||
1 |
Domestic |
|
|
||
a) |
Upto 100
units |
282 |
35 |
311 |
Loads
upto 100 KW Rs.38/KW, loads exceeding 100 KW Rs.34/KVA |
b) |
101 to
300 units |
428 |
452 |
||
c) |
Above 300
units |
452 |
478 |
||
2 |
Non-Residential |
491 |
126 |
519 |
Loads
upto 100 KW Rs.136/KW, loads exceeding 100 KW Rs.122/KVA |
3 |
Public lighting |
482 |
As per 8 hrs / Day |
510 |
As
per 8 hrs / Day |
4 |
Agricultural
Pumpsets |
i)
Without Govt. subsidy 285 Ps / kwh or
Rs.283/ |
NA |
i) Without Govt. subsidy 320 Ps / kwh or
Rs.273/ |
NA |
ii) With
Govt. subsidy 0 |
ii) With Govt. subsidy Rs.50/ |
||||
5 |
Industrial |
|
|
||
a) |
Small
power |
392 |
104 |
414 |
112/KW |
b) |
Medium |
433 |
138 |
458 |
148KW |
c) |
Large |
|
|
|
|
i) |
General
industry |
433 |
124 / |
458 |
133
/ |
ii) |
PIU |
433 |
326 / |
458 |
351/ |
iii) |
Arc
Furnace |
433 |
326 / |
458 |
351
/ |
6 |
Bulk
Supply (including MES) |
||||
|
HT |
436 |
204 / |
461 |
219/ |
LT |
463 |
204 /KW |
489 |
||
7 |
Railway
Traction |
512 |
208 / |
541 |
224/ |
B)
SEASONAL INDUSTRY : COTTON GINNING, PRESSING |
|||||
a) |
During
Season (From 1st Sept to 31st May next year) |
||||
|
SP |
392 |
381 |
414 |
410/KW |
|
MS |
433 |
381 |
458 |
410/KW |
|
LS |
433 |
343 / |
458 |
369
/ |
b) |
Off
season |
||||
|
SP |
464 |
NA |
491 |
NA |
|
MS |
497 |
NA |
525 |
NA |
|
LS |
497 |
NA |
525 |
NA |
C) ICE
FACTORY & ICE CANDIES |
|||||
a) |
Season
(April to July) |
||||
|
SP |
392 |
519 |
414 |
558/KW |
|
MS |
433 |
519 |
458 |
558/KW |
|
LS |
433 |
468 / |
458 |
503/ |
b) |
Off
Season |
||||
|
SP |
392 |
104 |
414 |
112/KW |
|
MS |
433 |
104 |
458 |
112/KW |
|
LS |
433 |
93 / |
458 |
100/ |
D) |
|||||
a) |
First
2000 units |
Free |
N.A. |
Free |
N.A. |
b) |
Beyond
2000 units |
349 |
N.A. |
369 |
N.A. |
E)
TEMPORARY SUPPLY |
|||||
i) |
Domestic |
771 |
Rs.640 or Rs.127/KW whichever is
higher |
815 |
Rs.689
or Rs.137/KW whichever is higher |
ii) |
NRS |
771 |
Rs.1281 or Rs.321/KW whichever is
higher |
815 |
Rs.1378
or Rs.345/KW whichever is higher |
iii) |
Industrial
(SP,MS & LS) |
As per tariff approved at A(5)
above for permanent supply + 100% |
Rs.513/KW of sanctioned load for SP and MS and Rs. 461/ |
As
per tariff approved at A(5) above for permanent supply + 100% |
Rs.552/KW
of sanctioned load for SP and MS and
Rs. 496/ |
iv) |
Wheat
Thresher |
-do- |
-do- |
-do-
|
-do-
|
v) |
Fairs,
exhibition & melas Congregations |
Bulk supply tariff as at A(6) +
50% |
Rs.5128 per service |
Bulk
supply tariff as at A(6) + 50% |
Rs.5517
per service |
vi) |
Touring
Cinemas |
|||||
a) |
Lights
and fans |
771 |
For (a) and (b) Rs. 1281 or Rs.
321/KW of sanctioned load whichever is higher |
815 |
For
(a) and (b) Rs. 1378 or Rs. 345/KW of sanctioned load whichever is higher |
|
b) |
Motive
load |
Rate for Industrial permanent
supply as at A(5) + 100% |
Rate
for Industrial permanent supply as at A(5) + 100% |
|||
Notes:
i. SC and non SC BPL, Domestic consumers
with connected load upto 1000 watts will be given 100 units of free power per
month in view of Govt subsidy;
ii) AP
consumers and consumers mentioned in (i) above will not be charged service
charges and meter rentals in view of Govt subsidy;
iii). All other charges including rentals and deposits which were being
collected by the Board as per Schedule of General Charges, Supply Code and
General Conditions of Tariff & Schedules of Tariff approved by the
Commission, will be continued to be charged by the Successor Entities at the
existing rates till these are reviewed by the Commission;
iv) Operating conditions of MMC will continue to
be as specified in the relevant Schedule of Tariff;
v) Consumers obtaining one point supply for
providing electricity to ultimate users in the Co-operative Group Housing
Societies/Residential Colonies/Commercial Complexes/Shopping Malls/Industrial
Estates etc. will be eligible for rebate as specified in the Conditions of
supply approved by the Commission;
vi. Checking of load of DS consumers will continue to be suspended.
Table 5.2: Aggregate
quantum of cross subsidy for the year 2009-10
(Combined average cost
of supply = 402.76 paise/unit)
Sr. No |
Category |
Energy Sales (MUs) |
Existing tariff (paise / unit) |
Revenue with existing tariff (Rs.
crore) |
PLEC + |
Non tariff income (Rs. crore) |
Total Revenue (Rs. crore) (5+6+7) |
Expected Revenue with average cost
|
Cross Subsidy generated (+)
Utilised (-) (8-9) |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
1 |
Domestic
|
|
|
|
|
|
|
|
|
a) |
Upto 100 |
3902 |
282 |
1100.36 |
29.53 |
54.99 |
1184.88 |
1571.57 |
-386.69 |
b) |
101-300 |
2016 |
428 |
862.85 |
15.26 |
28.40 |
906.51 |
811.96 |
94.55 |
c) |
>300
units |
1042 |
452 |
470.98 |
7.89 |
14.68 |
493.55 |
419.68 |
73.87 |
|
Total |
6960 |
|
2434.19 |
52.68 |
98.07 |
2584.94 |
2803.21 |
|
2 |
NRS |
2145 |
491 |
1053.20 |
16.23 |
30.22 |
1099.65 |
863.92 |
235.72 |
3 |
Public
Lighting |
148 |
482 |
71.34 |
1.12 |
2.09 |
74.55 |
59.61 |
14.94 |
4 |
Industrial
|
|
|
|
|
|
|
|
|
a) |
SP |
722 |
392 |
283.02 |
5.46 |
10.17 |
298.65 |
290.79 |
7.86 |
b) |
MS |
1522 |
433 |
659.03 |
11.52 |
21.44 |
691.99 |
613.00 |
78.99 |
c) |
LS |
9278 |
433 |
4017.37 |
194.34 |
130.72 |
4342.43 |
3736.81 |
605.61 |
|
Total |
11522 |
|
4959.42 |
211.32 |
162.33 |
5333.07 |
4640.60 |
|
5 |
Bulk
Supply |
|
|
|
|
|
|
|
|
a) |
HT |
449 |
436 |
195.76 |
3.40 |
6.33 |
205.49 |
180.84 |
24.65 |
b) |
LT |
51 |
463 |
23.61 |
0.39 |
0.72 |
24.72 |
20.54 |
4.18 |
|
Total |
500 |
|
219.37 |
3.79 |
7.05 |
230.21 |
201.38 |
|
6 |
Railway
Traction |
123 |
512 |
62.98 |
0.93 |
1.73 |
65.64 |
49.54 |
16.10 |
7 |
Common
Pool |
303 |
|
84.00 |
0.00 |
4.27 |
88.27 |
122.04 |
-33.77 |
8 |
Outside
State |
1307 |
|
798.00 |
0.00 |
0.00 |
798.00 |
526.41 |
271.59 |
9 |
AP |
9814 |
285 |
2796.99 |
0.00 |
138.27 |
2935.26 |
3952.69 |
-1017.43 |
10 |
Total |
32822 |
|
12479.49 |
286.07 |
444.03 |
13209.59 |
13219.40 |
1428.06 |
-1437.89 |
Table 5.3: Aggregate
quantum of cross subsidy
for the year 2010-11
at revised tariff
(Combined average cost of supply = 427.29
paise/unit)
Category |
Approved Energy Sales (MUs) |
Proposed Tariff (paise / unit) |
Revenue with Proposed Tariff (Rs.
crore) |
PLEC + |
Non tariff income (Rs. crore) |
Total Revenue (Rs. crore) (5+6+7) |
Expected Revenue with average cost
(Rs. crore) |
Cross Subsidy generated (+)
Utilised (-) (8-9) |
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
1 |
Domestic
|
|
|
|
|
|
|
|
|
a) |
Upto 100 |
2855 |
311.00 |
887.91 |
21.80 |
38.77 |
948.47 |
1219.91 |
-271.44 |
b) |
101-300 |
3115 |
452.00 |
1407.98 |
23.78 |
42.30 |
1474.06 |
1331.01 |
143.05 |
c) |
>300
units |
1895 |
478.00 |
905.81 |
14.47 |
25.73 |
946.01 |
809.71 |
136.30 |
|
Total |
7865 |
|
3201.70 |
60.05 |
106.80 |
3368.54 |
3360.64 |
|
2 |
NRS |
2405 |
519.00 |
1248.20 |
18.36 |
32.66 |
1299.21 |
1027.63 |
271.58 |
3 |
Public
Lighting |
136 |
510.00 |
69.36 |
1.04 |
1.85 |
72.25 |
58.11 |
14.13 |
4 |
Industrial
|
|
|
|
|
|
|
|
|
a) |
SP |
759 |
414.00 |
314.23 |
5.79 |
10.31 |
330.33 |
324.31 |
6.01 |
b) |
MS |
1541 |
458.00 |
705.78 |
11.77 |
20.93 |
738.47 |
658.45 |
80.01 |
c) |
LS |
9093 |
458.00 |
4164.59 |
155.42 |
123.48 |
4443.49 |
3885.35 |
558.14 |
|
Total |
11393 |
|
5184.60 |
172.98 |
154.71 |
5512.29 |
4868.11 |
|
5 |
Bulk
Supply |
|
|
|
|
|
|
|
|
a) |
HT |
463 |
461.00 |
213.44 |
3.53 |
6.29 |
223.27 |
197.84 |
25.43 |
b) |
LT |
33 |
489.00 |
16.14 |
0.25 |
0.45 |
16.84 |
14.10 |
2.74 |
|
Total |
496 |
|
229.58 |
3.79 |
6.74 |
240.11 |
211.94 |
|
6 |
Railway
Traction |
138 |
541.00 |
74.66 |
1.05 |
1.87 |
77.59 |
58.97 |
18.62 |
7 |
Common
Pool |
302 |
0.00 |
100.00 |
|
4.10 |
104.10 |
129.04 |
-24.94 |
8 |
Outside
State |
53 |
0.00 |
5.40 |
|
0.00 |
5.40 |
22.65 |
-17.25 |
9 |
AP |
10,305 |
320.00 |
3297.60 |
23.82 |
139.93 |
3461.36 |
4403.22 |
-941.87 |
10 |
Total |
33093 |
|
13411.09 |
281.09 |
448.66 |
14140.84 |
14140.31 |
1256.03 |
-1255.50 |
The cross subsidy
likely to be generated at the revised level of tariff comes to Rs.1256.03 crore
against which Rs.1255.50 crore cross subsidy is required leaving a surplus of Rs.0.53
crore.
Table 5.4: Aggregate quantum of cross
subsidy – comparison
Average Cost of supply 402.76 paise/unit
for the year 2009-10
Average cost of supply 427.29 paise/unit
for the year 2010-11
Sr. No. |
Consumer categories |
Quantum of Cross Subsidy in
absolute terms |
|||
2009-10 |
2010-11 |
||||
Energy Sales (MUs) |
Cross Subsidy (Rs crore) |
Energy Sales (MUs) |
Cross Subsidy (Rs crore) |
||
1 |
2 |
3 |
4 |
5 |
6 |
1 |
Domestic
|
|
|
|
|
a) |
Upto 100 |
3902 |
-386.69 |
2855 |
-271.44 |
b) |
101-300 |
2016 |
94.55 |
3115 |
143.05 |
c) |
>300
units |
1042 |
73.87 |
1895 |
136.30 |
|
Total |
6960 |
|
7865 |
|
2 |
NRS |
2145 |
235.72 |
2405 |
271.58 |
3 |
Public
Lighting |
148 |
14.94 |
136 |
14.13 |
4 |
Industrial
|
|
|
|
|
a) |
SP |
722 |
7.86 |
759 |
6.01 |
b) |
MS |
1522 |
78.99 |
1541 |
80.01 |
c) |
LS |
9278 |
605.61 |
9093 |
558.14 |
|
Total |
11522 |
|
11393 |
|
5 |
Bulk
Supply |
|
|
|
|
a) |
HT |
449 |
24.65 |
463 |
25.43 |
b) |
LT |
51 |
4.18 |
33 |
2.74 |
|
Total |
500 |
|
496 |
|
6 |
Railway
Traction |
123 |
16.1 |
138 |
18.62 |
7 |
Common
Pool |
303 |
-33.77 |
302 |
-24.94 |
8 |
Outside
State |
1307 |
271.59 |
53 |
-17.25 |
9 |
AP |
9814 |
-1017.43 |
10305 |
-941.87 |
10 |
Grand
Total |
32822 |
1428.06 |
33093 |
1256.03 |
-1437.89 |
-1255.50 |
Sr. No. |
Consumer Category |
Exiting Tariff |
Revised Tariff |
||||||
Combined Average Cost of supply 402.76 paise/unit |
Combined Average Cost of supply 427.29 paise/unit |
||||||||
2009-10 |
2010-11 |
||||||||
Energy Sales (MUs) |
Total Revenue (Rs crore) |
Realisation per unit (Paise per
unit) |
Cross Subsidy levels (%) |
Energy Sales (MUs) |
Total Revenue (Rs crore) |
Realisation per unit (Paise per
unit) |
Cross Subsidy levels (%) |
||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
1 |
Domestic
|
|
|
|
|
|
|
|
|
a) |
Upto 100 |
3902 |
1184.88 |
303.66 |
-24.61% |
2855 |
948.47 |
332.21 |
-22.25% |
b) |
101-300 |
2016 |
906.51 |
449.66 |
11.64% |
3115 |
1474.06 |
473.21 |
10.75% |
c) |
>300
units |
1042 |
493.55 |
473.66 |
17.60% |
1895 |
946.01 |
499.21 |
16.83% |
|
Total |
6960 |
2584.94 |
371.4 |
|
7865 |
3368.54 |
428.30 |
|
2 |
NRS |
2145 |
1099.65 |
512.66 |
27.29% |
2405 |
1299.21 |
540.21 |
26.43% |
3 |
Public
Lighting |
148 |
74.55 |
503.72 |
25.07% |
136 |
72.25 |
531.25 |
24.33% |
4 |
Industrial
|
|
|
|
|
|
|
|
|
a) |
SP |
722 |
298.65 |
413.64 |
2.70% |
759 |
330.33 |
435.22 |
1.86% |
b) |
MS |
1522 |
691.99 |
454.66 |
12.89% |
1541 |
738.47 |
479.21 |
12.15% |
c) |
LS |
9278 |
4342.43 |
468.04 |
16.21% |
9093 |
4443.49 |
488.67 |
14.37% |
|
Total |
11522 |
5333.07 |
462.86 |
|
11393 |
5512.29 |
483.83 |
|
5 |
Bulk
Supply |
|
|
|
|
0 |
|
|
|
a) |
HT |
449 |
205.49 |
457.66 |
13.63% |
463 |
223.27 |
482.22 |
12.86% |
b) |
LT |
51 |
24.72 |
484.71 |
20.35% |
33 |
16.84 |
510.30 |
19.43% |
|
Total |
500 |
230.21 |
460.42 |
|
496 |
240.11 |
484.09 |
|
6 |
Railway
Traction |
123 |
65.64 |
533.66 |
32.50% |
138 |
77.59 |
562.25 |
31.58% |
7 |
Common
Pool |
303 |
88.27 |
291.32 |
|
302 |
104.10 |
344.70 |
|
8 |
Outside
State |
1307 |
798 |
610.56 |
|
53 |
5.40 |
101.89 |
|
9 |
AP |
9814 |
2935.26 |
299.09 |
-25.74% |
10305 |
3461.36 |
335.89 |
-21.39% |
|
Grand
Total |
32822 |
13209.59 |
402.46 |
|
33093 |
14140.84 |
427.31 |
|
As per Regulations
framed by the Commission, tariff is to be determined in such a way that it
progressively reflects combined average unit cost of supply. The Commission
observes that, in consonance with the PSERC Tariff Regulations, there is a
reduction in the cross subsidy levels of both the subsidized and subsidizing categories
as compared to 2009-10.
5.4.1 After determining the ARR
and tariff for the year 2010-11, the Commission in its letter
No.248/PSERC/Dir/T-110 dated 07.04.2010 (Annexure-IX),
solicited the views of the GoP regarding its intention to extend subsidy to any
consumer or class of consumers under Section 65 of the Act. The said letter
indicated the implications if GoP continued its present policy of subsidizing
AP consumers, SC DS consumers and Non-SC BPL DS consumers as under:
·
In its ARR for the year 2010-11, the Board has projected AP
consumption of 11245 MUs against which the Commission has estimated the same to
be 10305 MUs in para 4.1.3 of this Tariff Order. The revenue from AP
consumption of 10305 MUs @ 320 paise/unit (which translates into Rs.
273/BHP/Month) works out to Rs.3297.60 crore.
·
Total connected load of AP sets as intimated by the Board is
7061970 (Metered 79273 + Unmetered 6982697) KW as on January 1, 2010. This
connected load is inclusive of 87393 KW on account of two bulbs of 40 watts
each allowed free of charge to each of the 1092412 AP consumers. After reducing
this load of 87393 KW, the net AP connected load works out to 6974577 (7061970
– 87393) KW or 9349299 BHP as on January 1, 2010. The Commission notes that in
the past there has been an annual increase of approximately 10% in the AP
connected load. By applying the average rate of increase of 2.5% for three
months, the connected load as on 31st March, 2010 comes to 7148941
KW. Further, by assuming a mean average increase of 5% in the year, the
connected load during the first six months (April to September, 2010) works out
to 7506388 KW or 10062182 BHP.
The
Commission notes that the GoP has recently decided to charge an amount of
Rs.50/BHP per month which will be recoverable from AP consumers
bi-annually. With a connected load of
10062182 BHP, as indicated above, an amount of Rs.603.73 crore will become
payable by AP consumers for the year 2010-11. After adjustment of this amount,
AP subsidy will work out to Rs.2693.87 (3297.60 – 603.73) crore.
·
Meter Rental and
Service Charges: In addition, subsidy of Rs.9.00 crore on account of meter
rentals and service charges in respect of AP consumers is also payable by the
GoP for the year 2010-11.
Accordingly, the total AP subsidy of Rs.2702.87 (2693.87 + 9.00) crore will be payable by the GoP for the year
2010-11.
·
Scheduled Castes
(SC) Domestic Supply (DS) consumers: As per recent GoP decision of 22-01-2010
subsidy allowable to this category with connected load upto 1000 watts has been
reduced to 100 units per month. The Board has indicated an annual consumption
of 973.83 MUs by such consumers on which basis an amount of Rs.302.86 crore @
311 paise/unit will be the subsidy payable by the GoP. Besides, meter rentals
and service charges of Rs.15.03 crore as claimed by the Board are also liable
to be paid by GoP. Accordingly, total subsidy of Rs.317.89 crore will be
payable by the GoP for the year 2010-11 on this account.
·
Non-SC Below
Poverty Line (BPL) DS consumers: GoP has also decided that subsidy to non
SC BPL DS consumers with a connected load upto 1000 watts has been reduced to
100 units per month. The Board has claimed consumption of 8.29 MUs for these
consumers which results in subsidy payable by the GoP amounting to Rs.2.58
crore @ 311 paise/unit. Besides, meter rentals and service charges of Rs.0.20 crore
are also payable by GoP which makes the total subsidy under this head to
Rs.2.78 crore in 2010-11.
Thus, total requirement of subsidy for the year 2010-11
is Rs.3023.54 crore.
5.4.2 For the year 2009-10, the
Commission has determined a subsidy of Rs.3204.27 crore inclusive of interest
of Rs.60.02 crore on delayed payment of
subsidy as discussed in para 3.15 of this Tariff Order. However, an amount of
Rs.108.57 crore will be recoverable from AP consumers for the period January
22, 2010 to March 31, 2010. After adjustment of this amount against payable
subsidy of Rs.3204.27 crore, net subsidy for 2009-10 is Rs.3095.70 crore.
Against this amount, the GoP has paid/adjusted an amount of Rs.3144.25 (1733.60
+ 1140.43 + 270.22) crore during the year. Thus, the GoP has paid excess
subsidy of Rs.48.55 crore in 2009-10.
5.4.3 For the year 2008-09, the
Commission has trued up payable subsidy at Rs.2420.28 crore against which GoP
has paid Rs.2601.73 crore which resulted in excess payment of subsidy of
Rs.181.45 crore, as discussed in para 2.16 of this Tariff Order.
5.4.4 The Commission in para
6.4.2 of the Tariff Order of 2009-10 specified the manner of payment of subsidy
in advance monthly instalments. As the Tariff Order for the current year is
being issued in the month of April 2010, the subsidy amount of Rs.230 crore
paid in excess by the GoP is being adjusted as part payment towards first
instalment of subsidy for the month of April 2010. After this adjustment, the
GoP will be required to pay subsidy of Rs.2793.54 crore in advance monthly
instalments during the year 2010-11 of which Rs.21.96 crore is payable in the
month of April 2010.
On the above basis,
subsidy payable by GoP during 2010-11 is detailed in Table 5.6.
Table 5.6 : Requirement of Subsidy for 2010-11
(Rs. crore)
Subsidy
payable by the GoP |
AP
+Meter rentals and service charges |
SC DS +
Meter rentals and service charges |
Non-SC
BPL + Meter rentals and service charges |
Total |
2010-11 |
||||
Subsidy payable for AP consumption (@ 320 paise/unit) and
SC/non SC BPL DS consumers (@ 311 paise/unit) |
3297.60 (+) 9.00 3306.60 |
302.86 (+)15.03 317.89 |
2.58 (+)0.20
2.78 |
3627.27 |
Less Recovery from AP consumers @ Rs.50/BHP/month on
estimated connected load of 10062182 BHP determined after allowing increase @
5% over previous year load |
603.73 |
- |
- |
603.73 |
Total subsidy payable
by the GoP for 2010-11 |
2702.87 |
317.89 |
2.78 |
3023.54 |
2009-10 |
|||||
Subsidy payable as determined in para 3.15 |
2796.99 (+)8.00 2804.99 |
335.62 |
3.64 |
3144.25 |
|
Add : interest payable for delayed payment of subsidy |
|
|
|
60.02 |
|
Total subsidy payable |
|
|
|
3204.27 |
|
Less amount recoverable @ Rs.50/ BHP/month from AP
consumers for the period January to March, 2010 as determined in para 3.15
(to be firmed up on actual basis) |
108.57 |
||||
Net subsidy payable for 2009-10 |
3095.70 |
||||
Less subsidy already paid / adjusted |
i) Amount paid Rs. 1733.60 ii) Adjusted against GoP loans Rs. 1140.43 iii)
Adjusted against ED Rs. 270.22 3144.25 |
||||
Subsidy paid in
excess |
48.55 |
- |
|||
2008-09 |
|
||||
Amount of subsidy
paid in excess as determined in para 2.16 |
181.45 |
- |
|||
Total subsidy paid in
excess |
230.00 |
- |
|||
Excess paid subsidy adjusted against first instalment
payable for April 2010 |
Subsidy
Instalment for April
2010 251.96 Amount
adjusted 230.00 Balance
amount payable
for April 21.96 2010 |
(-) 230.00 |
|||
Balance total subsidy
and interest payable by the GoP upto March 31, 2011. |
2793.54* |
||||
* exclusive of
amount refundable by GoP.
The GoP in its letter
dated 13.4.2010 (Annexure-X) has accorded approval for the grant of subsidy for
the current year. Keeping this decision of GoP in view, the Commission has
incorporated the same in the tariff structure in Table 5.1.
5.4.5 GoP
in its letter No. 11/120/2008-PE2/971 dated 26.03.2010 and letter
No.11/120/2008/Energy Branch 2/1033 dated 1.4.2010 has decided to absorb the
increase in tariff of consumers (all sections) for the period 1.4.2009 to
8.9.2009. It has also agreed to refund the increased tariff consequent upon
issue of Tariff Order for 2009-10 and the same amount is to be paid to the
Successor Entities by GoP in six equated advance monthly instalments. The
amount of subsidy calculated in the preceding paras does not include the impact
of the refundable amount on account of increased tariff for the said period.
The Commission, therefore, approves a total subsidy of
Rs.2793.54 (3023.54 – 230) crore payable by the GoP to the Successor Entities for the year
2010-11.
The Commission has also determined an amount of
Rs.228.11 crore as excess interest refundable by the GoP to the Successor Entities as discussed in
para 3.15 of this Tariff Order. In addition, an amount of Rs.93.69 crore is
payable by the GoP to the Successor
Entities being the unadjusted amount disallowed for diversion of capital
funds as discussed in para 4.13.11 of this Tariff Order. Cumulatively thus,
Rs.321.80 (228.11 + 93.69) crore is payable by the GoP to the Successor Entities during the year
2010-11.
5.5 Tariff for purchase of NRSE Power
As per NRSE
Policy–2006, notified by the Govt. and adopted by the Commission in its order
dated 13/12/07, the rates for purchase of power from such projects during the
year 2010-11 are as under:-
Biomass, Urban/Municipal/Industrial liquid/solid waste to
energy and Wind power projects |
423
Paise/Unit |
Mini/Micro
Hydel, Bagasse/Biomass based Co-generation |
392 Paise/Unit |
Solar energy |
852
Paise/Unit |
5.6 Separate tariff for each Function
5.6.1 Separate tariffs have been determined for generation, transmission &
distribution in compliance with the directions of the Appellate Tribunal for
Electricity (ATE) by segregating the ARR of 2010-11 based on the information
furnished by the Board in its letter dated 23/02/2010 and the audited accounts
of 2008-09.
The allocation under each head (generation, transmission and
distribution) is detailed at Annexure-V and ROE is trifurcated proportionately
on the value of fixed assets of each function. In addition, the consolidated
gap and carrying cost of gaps upto 2009-10 has been computed in proportion to
the revenue requirement (in Table 5.7) of each function.
5.6.2 The segregated ARR on the above basis is given in Table 5.7. The generation
function has also been further divided into thermal and hydel taking into
account the fact that the Regulations for determining the tariff for these are
different.
Table 5.7: Segregation
of ARR for 2010-11
(Rs.
crore)
Sr. No. |
Item of expense |
Generation |
Transmission |
Distribution |
Total |
||
Hydel |
Thermal |
Total |
|||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
1 |
Cost of
fuel |
0.00 |
3,370.40 |
3,370.40 |
0.00 |
0.00 |
3,370.40 |
2 |
Cost of
power purchase |
0.00 |
0.00 |
0.00 |
0.00 |
3,774.12 |
3,774.12 |
3 |
Employee
cost |
148.59 |
417.08 |
565.68 |
252.64 |
2,171.81 |
2,989.83 |
4 |
R&M
expenses |
102.12 |
149.26 |
251.38 |
41.02 |
80.84 |
373.24 |
5 |
A&G
expenses |
3.88 |
5.57 |
9.45 |
14.48 |
55.82 |
79.75 |
6 |
Depreciation |
168.59 |
173.08 |
341.67 |
123.07 |
398.85 |
863.68 |
7 |
Interest
charges |
418.98 |
132.95 |
551.93 |
110.39 |
310.15 |
972.57 |
8 |
Return on
Equity |
134.30 |
97.42 |
231.72 |
45.99 |
134.71 |
412.46 |
9 |
Total
revenue requirement |
976.47 |
4,345.76 |
5,322.23 |
587.59 |
6,926.30 |
12,836.05 |
10 |
Add:
Consolidated Gap and carrying cost of gap ending 2009-10 |
99.22 |
441.58 |
540.80 |
59.71 |
703.79 |
1,304.29 |
11 |
Gross
revenue requirement (9+10) |
1,075.69 |
4,787.34 |
5,863.03 |
647.30 |
7,630.09 |
14,140.34 |
5.7
Generation tariff
5.7.1
The PSERC Tariff
Regulations specify that the generation tariff will have the same components as
laid down in the Central Electricity Regulatory Commission (Terms and
Conditions of Tariff) Regulations 2004 as amended from time to time. CERC by
its notification dated
5.7.2
As per CERC Regulations, generation tariff comprises
of:
(i)
Annual Fixed
Charges (
(ii)
Energy
(variable) charges (for recovery of primary fuel cost).
These charges are recoverable on the basis of norms for thermal plants
and hydel plants and are specific for each power plant.
5.7.3 In the case of thermal plants,
5.7.4 The Commission has assessed plant
wise
Table - 5.8: Annual Fixed Charges – Generation – 2010-11
Sr. No. |
Plant |
Annual Capacity Charges ( Rs. in
crore) |
Net Generation (MUs) |
Fixed Charges (paise/unit) |
1 |
2 |
3 |
4 |
5 |
A |
Thermal Plants |
1,473.26 |
|
|
1 |
GGSTP |
688.16 |
9382 |
73 |
2 |
GNDTP |
254.19 |
2233 |
114 |
3 |
GHTP |
530.90 |
6621 |
80 |
|
|
|
|
|
B |
Hydel Plants |
1,075.71 |
|
|
1 |
RSD |
684.67 |
1475 |
464 |
2 |
Mukerian |
83.27 |
1212 |
69 |
3 |
UBDC |
47.22 |
380 |
124 |
4 |
Shanan |
22.11 |
522 |
42 |
5 |
Anandpur
Sahib |
49.64 |
684 |
73 |
6 |
Micro
Hydel |
2.25 |
8 |
282 |
7 |
Bhakra
Complex |
67.91 |
|
NA |
8 |
Dehar
& Pong |
118.63 |
|
NA |
The
Accordingly, the total
i) Thermal - Rs.1,473.26 crore
ii) Hydel - Rs.1,075.71 crore
5.7.5 The
5.7.6
Variable (energy) charges for thermal plants
The variable (energy) charges for a thermal plant are the primary fuel
cost to be paid to the generators and are computed as cost per unit of ex-bus
energy (energy sent out). As per approved ARR for 2010-11, the total fuel cost,
excluding the cost of secondary fuel oil, for all the three thermal plants
(including GHTP Stage - II) is Rs.3314.08 crore. These costs have been worked
out plant wise and the variable charges per unit of energy for each plant are
given in Table 5.9.
Table 5.9: Variable (energy) charges – 2010-11
Sr. No. |
Particulars |
GNDTP |
GGSTP |
GHTP |
1 |
2 |
3 |
4 |
5 |
1 |
Primary
Fuel Cost (Rs. In crore)* |
437.02 |
1711.73 |
1165.33 |
2 |
Net
Generation (MUs) |
2,233 |
9,382 |
6,621 |
3 |
Variable
Charge per unit (Rs./kWh) |
1.96 |
1.82 |
1.76 |
*
The plant wise fuel cost has been taken as approved by the Commission in
Chapter - 4 instead of
as apportioned in Annexure – VIII.
5.7.7
Total Energy charges for generating plants
The total energy charges (fixed and variable) for generating plants as determined
by the Commission are given in Table 5.10.
Table 5.10: Total energy charges – 2010-11
Sr. No. |
Plant |
Fixed Charges (paise/unit) |
Variable Charges (paise/unit) |
Total Charges (paise/unit) |
|
1 |
2 |
3 |
4 |
5 = 3 + 4 |
|
A |
Thermal Plants |
|
|
|
|
1 |
GGSTP |
73 |
182 |
255 |
|
2 |
GNDTP |
114 |
196 |
310 |
|
3 |
GHTP |
80 |
176 |
256 |
|
|
|
|
|
|
|
B |
Hydel Plants |
|
|
|
|
1 |
RSD |
464 |
- |
464 |
|
2 |
Mukerian |
69 |
- |
69 |
|
3 |
UBDC |
124 |
- |
124 |
|
4 |
Shanan |
42 |
- |
42 |
|
5 |
Anandpur
Sahib |
73 |
- |
73 |
|
6 |
Micro
Hydel |
282 |
- |
282 |
5.8 Transmission
Tariff
5.8.1 The PSERC Tariff Regulations specify that transmission tariff
will have the following components:
i)
Operation charges
ii)
Reactive energy charges
iii)
Charges for use of the network
5.8.2 The Board has not supplied the
State Load Despatch Centre (SLDC) costs to arrive at the SLDC Operation
charges. The reactive energy charges for Intra-State Open Access are to be
realized from the customers as per the Regulations already notified by the
Commission. Hence, only the charges for use of network are being assessed.
5.8.3 Charges for use of
network are to be calculated in accordance with the methodology specified in
the PSERC Tariff Regulations. The revenue requirement for transmission for
2010-11 works out to Rs.647.30 crore as given in Table 5.7 and the transmission
capacity as furnished by the Board in the ARR for 2010-11 is 7009 MW. However,
as per PSERC Tariff Regulations, the transmission capacity for working out the
transmission charges shall be the sum of generating capacities connected to the
transmission system and contracted capacities of other long term transactions
handled by the system of the transmission licensee. Accordingly, on the basis
of such information furnished by the Board in the ARR for 2010-11, the
transmission capacity works out to 7790.50 MW. On this basis, the Commission determines the charges for use of the
transmission network at Rs.2276/MW/Day.
5.9 Distribution / Wheeling
The revenue requirement for distribution for 2010-11 as per Table 5.7 is
Rs.3855.97 crore (excluding the power purchase cost) while the distribution
capacity is 6978 MW as furnished by the Board. However, as per PSERC
Tariff Regulations, the distribution capacity for working out the wheeling
charges shall be the sum of import of power at each interface point of exchange
of power at electrical boundary of distribution licensee and generation from
captive plants and cogeneration plants (to the extent fed into the grid) and
plants generating electricity from renewable sources of energy located in the
area of such licensee. The distribution capacity thus works out to 7859.50 MW
(7790.50 + 69.00). Accordingly, the
Commission determines wheeling charges as Rs.13441/MW/Day.
5.10 Open Access Charges
As per the
Open Access Regulations notified by the Commission, the Open Access charges for
the year 2010-11 are computed in Table 5.11.
Table 5.11:
Open Access Charges – 2010-11
Sr. No. |
Open Access Charges |
|
1 |
Transmission
charges |
Rs. 2276/MW/Day |
2 |
Wheeling charges |
Rs. 13441/MW/Day |
3 |
Transmission
+ |
Rs. 5238/MW/Day |
4 |
Transmission
+ |
Rs. 3143/MW/Day |
5 |
Transmission
+ |
@ 2% of energy injected to the State grid irrespective of
the distance |
6 |
T&D losses |
|
|
(i) For
voltages at 66 kv and above @ 30% of normative T&D losses |
6% |
|
(ii) For
voltages below 66 kv @ 50% of
normative T&D losses |
10% |
7 |
Surcharge |
Nil |
8 |
Other charges such as additional surcharge, operation
charges, UI charges, reactive energy charges shall be levied as per the Open
Access Regulations/Tariff Regulations notified by the Commission. |
Note: Examples of computation of Open Access
Charges are provided in Annexure XI
5.11 Cost of supply and Cross
subsidy
In compliance with the Order of the ATE dated 26.5.2006, the Board was
asked in the Tariff Order for 2007-08 to initiate a study for determination of
cost of supply of electricity to different classes and categories of consumers.
The Board, in its letter dated 17.02.2010 has intimated that limited tenders have
been floated to five firms for submitting the bids to engage consultants which
will be opened on 02.03.2010. In the light of ATE’s directions, the Successor Entity needs to ensure that the process of engaging consultants for carrying
out the proposed study is expedited and the findings of the study as well as
its own views thereon are submitted to the Commission as early as possible.
5.12 Date of Effect
The Commission notes that the
ARR of the Successor Entities for the year
2010-11 covers the complete financial year. The recovery of tariff, therefore,
has to be such that total revenue requirement of the Successor Entities for the year 2010-11 is recovered in this
period.
The Commission,
therefore, decides to make the revised tariffs applicable from April 01, 2010
and the tariff structure determined above shall remain operative till March 31,
2011.
Date: April 23, 2010
Place: CHANDIGARH
Sd/- |
Sd/- |
Sd/- |
(VIRINDER
SINGH) |
(S.S.
PALL) |
(JAI
SINGH GILL) |
MEMBER |
MEMBER |
CHAIRMAN |
CERTIFIED
Sd/-
(NAMITA
SEKHON)
SECRETARY