Sr.No. | Petition No. | Filed By | Subject Matter | Date of Final Decision | |
---|---|---|---|---|---|
1 | Review Petition No. 01 of 2019 in Petition No. 32 of 2018 | Punjab State Power Corporation Limited | Review Petition/Application under Section 94(1) (f) of the Electricity Act, 2003 read with Section 64 (Chapter XIII) of PSERC (Conduct of Business) Regulations, 2005 and other provisions for reviewing the order dated 29.11.2018 rendered by the Commission in Petition No. 32 of 2018. | 30.09.2019 | |
2 | Review Petition No. 02 of 2019 In Petition No. 14 of 2017 | Photon Suryodaya Pvt. Limited | Review Petition/Application under Section 94(1) (f) of Electricity Act, 2003 read with Regulation 64 of Punjab State Electricity Regulatory Commission (Conduct of Business) Regulation, 2005, for seeking review of order dated February 11, 2019, rendered by this Ld. Commission in Petition No. 14 of 2017. | 01.10.2019 | |
3 | Review Petition No. 03 of 2019 in Petition No.52 of 2017 | Vardhman Special Steels Ltd | Review petition under Section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 64 (Chapter XIII) of the PSERC (Conduct of Business) Regulations, 2005 for review of Order dated 03.01.2018 passed by the Commission in petition No. 52 of 2017 | 15.07.2019 | |
4 | Review Petition No. 04 of 2019 in Petition No.01 of 2018 | Punjab State Power Corporation Limited | Review Petition under Section 94 of the Electricity Act read with Regulation 64 of the Conduct of Business Regulations seeking review of the Order dated 27.05.2019 passed by the Hon’ble Commission in petition No. 01 of 2018. | 30.09.2019 | |
5 | Review Petition No. 5 of 2019 in Petition No. 02 of 2019 | Punjab State Power Corporation Limited | Petition seeking review of the Tariff Order dated 27.05.2019 in Petition No. 02 of 2019 to the extent that the Commission has held that cumulative effect of ToD rebate and Voltage rebate on the Energy Charges (including reduced energy charges for consumption exceeding threshold limit / use of electricity exclusively during night hours) at any time shall be limited to the lowest Energy Charges of Rs. 4.45 per kVAh. | 13.09.2019 | |
6 | Review Petition No. 06 of 2019 In Petition No. 02 of 2019 | Punjab State Power Corporation Limited | Review Petition under Section 94 of the Electricity Act, 2003 against tariff order dated 27.05.2019 for FY 2019-20 (in petition no. 02 of 2019) | 05.12.2019 | |
7 | Review Petition No. 07 of 2019 in Petition No.39 of 2018 | Punjab State Power Corporation Limited | Review petition to be filed against PSERC order dated 05.03.2019 passed in the petition no. 39 of 2018 filed by M/s Green Plant Energy Pvt.Ltd. for redetermination of tariff in respect of 4 MW biogas (Otto Cycle) power plant at Vill. Binjon, Dist. Hoshiarpur. | 08.11.2019 | |
8 | I.A No. 08 of 2019 In Petition No. 32 of 2018 | Punjab State Power Corporation Limited | Petition under Section 86(1)(b) of the Electricity Act, 2003 seeking approval of PPA executed by the petitioner with the Respondent, Shree Ganesh Edibles Private Limited. | 20.01.2020 | |
9 | 01/2019 | Paramount Steels Ltd | Petition under Regulation 10 and 69 of the PSERC (Conduct of Business) Regulations, 2005 and other relevant Regulations framed by the Commission and sections of the Electricity Act, 2003 for determination of rate of voltage surcharge for the period starting from 01.10.2004. | 09.08.2019 | |
10 | 02/2019 | Punjab State Power Corporation Limited | Determination of Tariff for FY 2019-20 | 27.05.2019 | |
11 | 03/2019 | Punjab State Transmission Corporation Limited | Determination of Tariff for FY 2019-20 | 27.05.2019 | |
12 | 04/2019 | Punjab State Power Corporation Limited | Petition for seeking approval of Hon’ble Commission for waiving off interest on arrears, on account of voltage surcharge amount recoverable as per Hon’ble Supreme Court judgements dated 01.03.2017 & 19.06.2017, being non-tariff income. | 30.07.2019 | |
13 | 05/2019 | Punjab State Power Corporation Limited | Petition under Section 23 of the Electricity Act, 2003 seeking regulatory guidance for measures to be taken in case of exigencies leading to power cuts for the Tariff Year 2019-20. | 19.06.2019 | |
14 | 06/2019 | Punjab State Power Corporation Limited | Petition under Section 86(1) (e) of the Electricity Act, 2003 read with Regulation 3,7, Regulation 9 and Regulation 10 of the PSERC (Renewable Purchase Obligation and its compliance) Regulations, 2011 seeking rectification of the quantum of renewable energy procured by the Petitioner, Punjab State Power Corporation Limited as accounted towards the Renewable Purchase Obligation of the Petitioner. | 04.09.2019 | |
15 | 07/2019 | Punjab State Power Corporation Ltd. | Petition for determination of Additional Surcharge under Section 42(4) of the Electricity Act, 2003 read with Regulation 27 of the Punjab State Electricity Regulatory Commission (Terms and Conditions for Intra-State Open Access) Regulations, 2011 to be made applicable upon the open access consumers availing power from the sources other than PSPCL for the period 01.04.2019 to 30.09.2019. | 06.09.2019 | |
16 | 08/2019 | Punjab State Power Corporation Limited (PSPCL) | Petition for approval of Fuel Cost Adjustment (FCA) Surcharge for 3rd Quarter (October, 2018 to December, 2018) of FY 2018-19. | 27.05.2019 | |
17 | 09/2019 | M/S Oswal Denims | Petition under Regulation 68, 69 and 71 and provisions of Chapter XI of PSERC (Conduct of Business) Regulations 2005 as amended up to date, Regulation 43 of Open Access Regulations and other relevant rules and regulations as approved by the Commission read with the relevant provisions of the Electricity Act 2003. | 27.09.2019 | |
18 | 10/2019 (Suo-Motu) |
Punjab State Power Corporation Limited | Petition under section 142 of the Electricity Act, 2003 regarding Non compliance of the order dated 28.02.2018 passed by the Commission in petition no. 47 of 2017 directing PSPCL to either replace all the Trivector ToD meters with LAG plus LEAD Tariff protocol procured against specification no. MQP-95 with LAG only tariff protocol ToD Trivector meters or change the tariff protocol of all the meters procured against MQP-95 from LAG plus LEAD Tariff protocol to LAG only Tariff protocol within three months from the date of issue of the order, further directing PSPCL to ensure that no consumer is charged extra for leading power factor recorded with LAG plus LEAD Tariff protocol meters and that the amounts already charged on account of leading power factor may be refunded to the consumers. | 29.08.2019 | |
19 | 11/2019 | Jain Solvex & Export Industries | Petition under Section 62 (6) of E.A 2003 and General Conditions of Tariff, clause 23 for F.Y 2017-18, against wrong interpretation and hence wrong application of condition 18.5 (iii) of General Conditions of Tariff by the Licensee in case of mixed load industries. | 22.07.2019 | |
20 | 12/2019 | Punjab State Power Corporation Limited (PSPCL) | Petition for approval of Fuel Cost Adjustment (FCA) Surcharge for 4th quarter (January, 2019 to March, 2019) of FY 2018-19. | 09.07.2019 | |
21 | 13/2019 | Sh. Vinod Kumar Dutt | Petition under Regulation 18 of PSERC (Grid Interactive Rooftop Solar Photo Voltaic Systems based on Net Metering) Regulations, 2015. | 06.09.2019 | |
22 | 14/2019 | Punjab State Transmission Corporation Ltd. (PSTCL) | Petition under Regulation-9 of PSERC (Terms and Conditions for Determination of Generation, Transmission, Wheeling and Retail Supply Tariff) Regulations, 2014 and Section 40 of the Electricity Act, 2003- seeking Regulatory Approval for system improvement initiatives to be taken up for 400 KV Transmission Network for the year 2019-20. | 18.10.2019 | |
23 | 16/2019 | Punjab State Power Corporation Limited | Petition regarding Voluntary Disclosure Scheme (VDS) for Domestic (DS), Non Residential (NRS) and Agriculture Tubewell (AP) Consumers under Regulation 47 of PSERC Regulation 2014 and clause 68 & 69 of PSERC (Conduct of Business) Regulation, 2005. | 26.08.2019 | |
24 | 17/2019 | Petition No.17 of 2019(Suo-Motu) | Determination/fixation of levellised generic tariff for Renewable Energy Power Projects for FY2019-20. | 13.09.2019 | |
25 | 18/2019 | Petition No.18 of 2019 | PETITION NO. 18 OF 2019 FILED BY PUNJAB STATE POWER CORPORATION LIMITED FOR BUSINESS PLAN INCLUDING CAPITAL INVESTMENT PLAN FOR MYT CONTROL PERIOD FROM FY 2020-21 TO FY 2022-23. | 03.12.2019 | |
26 | 19/2019 | Petition No.19 of 2019 | PETITION NO. 19 OF 2019 FILED BY PSTCL FOR BUSINESS PLAN INCLUDING CAPITAL INVESTMENT PLAN FOR MYT CONTROL PERIOD FROM FY 2020-21 TO FY 2022-23 FILED BY PUNJAB STATE TRANSMISSION COMMISSION LIMITED BEFORE PUNJAB STATE ELECTRICITY REGULATORY COMMISSION | 03.12.2019 | |
27 | 20/2019 | Punjab State Power Corporation Limited | Petition for the Determination of Additional Surcharge U/S 42 (4) of the Indian Electricity Act-2003 read with Regulation 27 of Punjab State Electricity Regulatory Commission (Terms and Conditions for Intra-State Open Access) Regulations, 2011 to be made applicable on to the open access consumers availing power from the sources other than PSPCL for the period 01.10.2019 to 31.03.2020. | 28.11.2019 | |
28 | 21/2019 | Punjab State Power Corporation Limited | Petition under Regulation 8.1(b) of the Supply Code 2014 by Punjab state Power Corporation Limited for seeking approval of the Commission for extension in time period of release of EHT Connection of 4500 KW Load/5000 KVA contract demand applied by Divisional Railway Manager (Elect./TRD), New Delhi through Senior Divisional Electrical Engineer (TRD) Northern Railway, New Delhi under category Railway Traction in Sub Division Kotshamir under Division Maur. ( RID No. 18246). | 29.10.2019 | |
29 | 22/2019 | Indian Railways | Petition under regulation 86(1)(c) of the Electricity Act, 2003 and Regulations 37 and 45 of the Punjab State Electricity Regulatory Commission (Terms and Conditions for Intra-state Open Access) Regulations, 2011and Regulation 10, of the Punjab State Electricity Regulatory Commission (Conduct of Business) Regulations, 2005, for permitting Indian Railways to submit Reserve Bank of India’s Letter of Mandate as payment security mechanism towards various charges payable for availing open access at its Traction substations situated in the State of Punjab. | 18.10.2019 | |
30 | 23/2019 | Punjab State Power Corporation Ltd | Petition for seeking approval of procurement of 300 MW solar power and 200 MW wind power from NTPC limited on long term basis through PSAs signed on 25.03.2019 & approval of the tariff and trading margin of (seven) 7 paisa/kWh to NTPC under Section 86(1)(b) of the Electricity Act, 2003 | 23.12.2021 | |
31 | 24/2019 | M/s. Green Planet Energy (P) Ltd. | Petition under Section 142 and 146 of the Electricity Act, 2003 read with rule 10 and 69 of the PSERC ( Conduct of Business) Regulations, 2005, for taking necessary action against the respondent and its officials for not complying with the Order dated 05.03.2019 passed by the Commission in petition no. 39 of 2018 titled as M/s Green Plant Energy (P) Ltd. Vs. PSPCL and others and further for issuance of necessary directions to the respondent to execute the amendment No. 2 regarding tariff approved by the Commission in petition No. 39 of 2018, in the PPA executed with the petitioner. | 13.01.2020 | |
32 | 25/2019 | Punjab State Power Corporation Limited | Petition under Section 86(1) (a) read with Section 62 of the Electricity Act, 2003 in regard to the inclusion of the amount payable by the Petitioner to Nabha Power Limited and Talwandi Sabo Power Limited under their respective Power Purchase Agreements as interpreted and implemented by the decision of the Hon’ble Supreme Court and appropriate directions for tariff to be recovered from the consumers. | 24.12.2019 | |
33 | 26/2019 | Punjab State Power Corporation Limited | Petition for seeking permission to extend the time for 9 months from the submission of test report dated 12.06.2019 to 12.03.2020 for the completion of Double Circuit of 66 KV line from 220 KV S/Stn. G-1 MGG to 66 KV S/Stn. Focal Point Mandi-Gobindgarh for release of new LS Induction furnance connection to M/s Dev Bhoomi Casting Pvt. Ltd. Village kumbra road, Transport Nagar, Mandi Gobindgarh. | 16.12.2019 | |
34 | 27/2019 | M/s KK Alloys | Petition under Regulation 68,69 and 71 and provisions of Chapter XIII of PSERC (Conduct of Business) Regulations 2005 as amended up to date and other relevant rules and regulations as approved by the Commission read with the relevant provisions of the Electricity Act, 2003 and for directing the respondent PSPCL to accept the request of the petitioner for processing of one time settlement proposal submitted by the petitioner for the payment of the alleged defaulting amount to be paid by M/s Pact Industries Limited and to take a final decision on the One time Settlement (OTS) Proposal submitted by the Petitioner to determine the final amount to be paid by the Petitioner in terms thereof and for further directing the Respondents to return the cheques submitted by the Petitioner for the approval of the OTS proposal. | 31.12.2019 | |
35 | 28/2019 | Punjab State Power Corporation Ltd. | Approval of the Power Purchase Agreements (PPAs) and the Procurement Process of Punjab State Corporation Limited related to the procurement of power from the Coal/Gas based Conventional Generating Stations. | 01.02.2021 | |
36 | 31/2019 | Nawanshahr Power Private Limited | Petition under Section 61 and 62 read with Section 86(1)(e) of the Electricity Act, 2003 and Section 7 of the CERC RE Regulations 2009 adopted by the Commission for Determination of Project Specific Tariff for IPP of 15 MW capacity on BOOT basis at M/s Nawanshahar Cooperative Sugar Mills Ltd., Village Paniar, District Nawanshahr, Punjab. | 29.03.2022 | |
37 | 32/2019 | GVK Power (Goindwal Sahib) Limited | Petition for True up of Tariff for FY 2016-17 under Sections 62 and 86 of the Electricity Act, 2003 read with (a) Punjab State Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2005; (b) the Central Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2014; and (c) Amended and Restated Power Purchase Agreement dated 26.05.2009 executed between Petitioner (GVK) Limited and Punjab State Power Corporation Limited (formerly known as Punjab State Electricity Board) | 07.09.2020 | |
38 | 33/2019 | Punjab Alkalies and Chemicals Limited | Petition under Regulation 6(2) and Regulation 7 of the PSERC (Renewable Purchase Obligation and its compliance) Regulations, 2011 for permission to carry forward the Renewable Purchase Obligation of the petitioner upto the year 2016-17 to the next Financial Year i.e. 2020-21. | 17.03.2020 | |
39 | 34/2019 | GVK Power (Goindwal Sahib) Limited | Petition for True up of Tariff for the control period (FY 2017-18 and 2018-19) under section 62 and 86 of the Electricity Act 2003 read with (a) Punjab State Electricity Regulatory Commission (Terms and conditions for determination of Generation, Transmission, wheeling and Retail Supply Tariff) Regulations, 2014; and (b) Amended and Restated Power Purchase Agreement dated 26.05.2009 executed between GVK Power (Goindwal Sahib) Limited and Punjab State Power Corporation Limited (formerly known as Punjab State Electricity Board). | 17.09.2020 | |