List of Commission orders/ judgments passed in various cases.
S.No. |
Petition
No. |
Filed
by |
Subject
matter |
Date of final decision.
|
|
1. |
1/2014 |
Punjab State Transmission Corporation Limited (PSTCL) |
Petition for amendment of the Aggregate Revenue Requirement (ARR) and Transmission Tariff / SLDC charges pursuant to Section 62 (4) of the Electricity Act, 2003 read with Regulation 5 of the Punjab State Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2005, and its subsequent amendments thereof for FY 2013-14 as approved by the Commission in the Tariff Order dated 10th April, 2013 |
31.01.2014 | |
2. |
2/2014 |
Divisional Railway Manager (Elect./TRD) |
Petition under clause no.5 & 6 of the Regulations on Electricity Supply Code for extension of compliance period for registration of A&A forms beyond 60 days of Railways Traction Sub Stations at Sujanpur and Dasua. |
26.02.2014 | |
3. |
3/2014 |
Punjab State Power Corporation Limited, The Mall, Patiala. |
Petition under Section 94 (f) of the Electricity Act, 2003 for review of the Order dated 13.12.2013 passed by the Commission in Petition No.53 of 2013 regarding procurement of power from 7.52 MW Rooftop Solar PV Power Project at Radha Soami Satsang Beas, District Amritsar. |
20.03.2014 | |
4. |
59/2013 |
Shri Gurnek Singh Brar |
Petition on the subject of outsourced meter reading / spot billing |
28.11.2014 | |
5. |
5/2014 |
Indus Towers Ltd. |
Petition under section 142 and 146 of the Electricity Act for non-compliance by PSPCL in the mater directives given to it by the Commission in Petition No.21 of 2013 regarding late payment surcharge on electricity bills. |
19.03.2014 | |
6. |
6/2014 |
Punjab State Federation of Co-operative House Building Societies Ltd. (HOUSEFED PUNJAB) |
Petition under section 142 of the Electricity Act, 2003 for taking necessary action against the respondents for not complying with the Order dated 24.10.2013 passed by the Commission in Petition No.46 of 2013 |
29.04.2014 | |
7. |
7/2014 |
Punjab State Power Corporation Limited |
Petition regarding Voluntary Disclosure Scheme (VDS) for Domestic Supply / Non-residential Supply (DS/NRS), Small Power/Medium Supply (SP/MS) and AP consumers. |
24.02.2014 Amendment (24.02.2014) |
|
8. |
8/2014 |
Punjab State Power Corporation Limited |
Regarding action under Section 142 of the Electricity Act, 2003 for contravening the directions of the Commission issued vide Order dated 28.10.2013 passed in Petition No.3 of 2012 filed by M/s Ludhiana Hand Tools Association, D-90, Phase-5, Focal Point Ludhiana U/S 86/94 of Electricity Act 2003 regarding treatment to be meted to Billet / Induction heating load by PSPCL and quashing of CC 38/2009 dated 29.10.2009. |
09.06.2014 | |
9. |
9/2014 |
Punjab State Power Corporation Limited |
Regarding action under Section 142 of the Electricity Act 2003 on account of non-compliance of the PSERC (Electricity Supply Code and Related Matters) (5th Amendment) Regulations, 2013 |
04.04.2014 | |
10. |
10/2014 |
Punjab Energy Development Agency (PEDA) |
Petition under Section 62 and 86 and other applicable provisions of the Electricity Act, 2003 for supply of electricity to PSPCL from 2nos. of 1MW each demonstration solar power projects being set up by PEDA in the State of Punjab. |
24.03.2014 | |
11. |
11/2014 |
Punjab State Power Corporation Limited |
Petition for approval of Fuel Cost Adjustment (FCA) Surcharge for 3rd Quarter (October 2013 to December 2013) of FY 2013-14. |
28.03.2014 26.08.2014 |
|
12. |
12/2014 |
suo-motu |
Audit of power purchase/sale/surrender, including power purchase/sale under UI by Punjab State Power Corporation Limited from 01.04.2010 to 31.03.2013 |
Click here for Publice Notice Click here for Report |
|
12.(a). |
12/2014 |
suo-motu |
Audit of power purchase/sale/surrender including power purchase/sale under UI by Punjab State Power Corporation Limited from 01.04.2010 to 31.03. 2013. |
10.10.2014 | |
13. |
13/2014 |
Punjab Energy Development Agency (PEDA) |
Petition under Section 62 and 86 and other applicable provisions of the Electricity Act, 2003 for supply of electricity to PSPCL from total aggregate capacity of 6MW demonstration solar power projects being set up by PEDA on the rooftops of Punjab Govt. Buildings. |
24.03.2014 | |
14. |
14/2014 |
Punjab State Power Corporation Limited |
Petition under Section 23 of the Electricity Act, 2003 seeking regulatory guidance for measures to be taken in case of exigencies leading to power cuts for the Tariff year 2014-15. |
25.04.2014 | |
15. |
15/2014 |
Punjab State Power Corporation Limited |
Petition for approval of capital expenditure for the distribution schemes to be executed by PSPCL for T&D loss reduction and system improvement. |
28.07.2014 | |
16. |
16/2014 |
Punjab State Transmission Corporation Limited |
Regulation 22 of the Punjab State Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2005 as amended by Punjab State Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff), second amendment Regulations, 2012 notified vide Notification dated 17th September, 2012. |
09.05.2014 | |
17. |
17/2014 |
Armaan Steels (A unit of M/s Goyal Exports) |
Petition under regulation 5.5, 5.6 and 6 of Electricity Supply Code (or amendment thereof) & Related Matters Regulations & Conditions of Supply, read with Section 142 of the Electricity Act, 2003 And Against decision dated 05.06.2013 of Feasibility Clearance Committee of the Punjab State Power Corporation Limited in respect of M/s Armaan Steels, A-07, Industrial Focal Point, Mandi Gobindgarh, forfeiting the earnest money deposit.
|
11.09.2014 | |
18. |
18/2014 |
Punjab Cotton Factories & Ginner’s Association |
Petition against clause No.18.4 (i) of the General Conditions of Tariff as amended and approved by Punjab State Electricity Regulatory Commission vide Order dated 23.10.2012 and adopted by Punjab State Power Corporation Limited (PSPCL) vide Circular No.40/2012 dated 05.11.2012. |
21.11.2014 | |
19. |
19/2014 |
G.N.General Mills |
Petition under clause 23 (interpretation of Tariff) of General Conditions of Tariff approved by PSERC and directing the respondents to refund excess charges deposited by the petitioner with the respondent PSPCL under protest and grant of any other relief, order or directions which the Commission may deem fit and proper in the facts and circumstances of the case. |
14.10.2014 | |
20. |
20/2014 |
ESS JAY Card Board |
Petition under Section 142 of the Electricity Act 2003 read with relevant Rules and Regulations of Electricity Supply Code, for setting aside Bill cum Assessment order vide letter no.47 dated 13.01.2014 vide which compensation on account of theft of electricity of Rs.41,69,434/- and compounding charges of Rs.7,90,000/- have been imposed on the applicant, being contrary to Rules and Regulations of the Electricity Code and The Electricity Act, 2003 AND After setting aside the same, to order restoration of the electric connection of the applicant. |
06.05.2014 | |
21. |
21/2014 |
Hotel Sepal Private Limited |
Petition under clause 23 (Interpretation of Tariff) of General Conditions of Tariff issued by the PSERC and for directing the respondents to refund the amount of Rs. 5,76,454/- recovered from the petitioner on account of 7.5% H.T. Rebate earlier allowed to the petitioner for the period from August 2006 to December 2009 and for further issuance of a direction to the respondents to pay 7.5% H.T. rebate upto 31.3.2010 as per Tariff Order for the year 2009-2010 and further for taking necessary action under Section 142 of the Electricity Act, 2003 |
05.05.2014 | |
22. |
22/2014 |
Punjab State Power Corporation Limited |
Petition for approval of capital investment plan for construction of multistoried office complex with corporate culture at PSPCL land at Badungar for offices of PSPCL. |
20.06.2014 | |
23. |
23/2014 |
Green Energy Association |
Petition for non-compliance of Solar RPO by obligated entities for FY 2011-12 to FY 2013-14 and in the matter of an application under Section 142 of the Electricity Act 2003 and Section 146 of the Electricity Act 2003, for non-compliance of Regulation 6 (1) & (2) of the PSERC (Renewable Purchase Obligation and its compliance) Regulations, 2011 and non-compliance of Order dated 12.08.2013 in Petition No.36 of 2013. |
30.07.2014 | |
24. |
24/2014 |
Punjab State Power Corporation Limited |
Petition regarding Voluntary Disclosure Scheme (VDS) for Domestic / Non-Residential Supply (DS/NRS), Small Power / Medium Supply (SP/MS) and A.P. Consumers. |
15.05.2014 | |
25. |
25/2014 and 26/2014 |
Turboatom-TPS (Punjab) Projects Limited |
Petition under Section 86 of the Electricity Act, 2003 for revision of rates in view of the latest order passed by this Commission determining the generic levellised tariff for renewal energy Power Projects and also the latest directions of Central Electricity Regulatory Commission, New Delhi for the year 2014-15 onwards (10 MW at Village Jhok Tehal Singh, Tehsil & District Ferozepur). |
28.07.2014 | |
26. |
27/2014 |
Punjab State Transmission Corporation Limited |
Petition – Incorporating provisions of charges for Over-Injection / Under-Injection by Independent Power Producers (IPPs) selling power to distribution licensee in Punjab under Long Term Power Purchase Agreement, by making consequent amendments in PSERC (Terms & Conditions for Intra-state Open Access) Regulations, 2011 and State Grid Code, 2013. |
28.11.2014 | |
27. |
28/2014 |
Nabha Power Limited |
Petition (Suo-Motu) to comply with Judgment dated 23.04.2014 passed by the Hon’ble APTEL in Appeal No.207 of 2012 impugning Order dated 01.10.2012 in Petition No.38 of 2011. |
09.04.2021 | |
28. |
29/2014 |
Punjab State Power Corporation Limited |
Petition for approval under Section 86 (1) (b) of the Electricity Act, 2003 for the power procurement plan on short term basis for the year 2014-15 read with the public notice issued by the Punjab State Electricity Regulatory Commission dated 23.10.2012 |
29.09.2014 | |
29. |
30/2014 |
Punjab State Transmission Corporation Limited(PSTCL) |
Aggregate Revenue Requirement (ARR) & Determination of Tariff for FY 2014-15 under Section 62, 64 and 86 of the Electricity Act, 2003 read with the Regulation 13 of PSERC (Terms and Conditions for Determination of Tariff) Regulations, 2005 (including its amendments) and other applicable relevant Regulations and Guidelines of the Commission for the Electricity Business of Punjab State Transmission Corporation Limited (PSTCL) and State Load Despatch Centre (SLDC) |
05.09.2014 | |
30. |
31/2014 |
Talwandi Sabo Power Limited |
Petition under applicable provisions of Section 63 and 86 (f) of The Electricity Act, 2003 read with statutory framework governing procurement of power through competitive bidding for approval for modalities of landed cost of washed coal to be included as part of landed fuel cost for computing the tariff as per the provisions of the Power Purchase Agreement - 3x660 MW Talwandi Sabo Thermal Power Project. |
23.11.2015 06.05.2019 |
|
31. |
32/2014 |
Punjab State Power Corporation Limited |
Petition for approval of capital expenditure for the distribution schemes to be executed by PSPCL for reduction of AT & C losses in towns below 15% under R-APDRP (Part-B) scheme of MOP/GOI. |
10.10.2014 | |
32. |
33/2014 |
Punjab State Power Corporation Limited |
Petition for approval of Fuel Cost Adjustment (FCA) Surcharge for 4th Quarter (Jan. 2014 to Mar. 2014) of FY 2013-14. |
26.08.2014 | |
33. |
34/2014 |
Punjab State Power Corporation Limited |
Petition under clause 94 (1) (f) of Electricity Act 2003 & clause 6 (2) of the PSERC (RPO & its compliance) Regulations, 2011 issued vide notification no. PSERC / Secy / Reg / 55 dated 03.06.2011 for carrying forward targets of Renewable Purchase Obligation (RPO) for FY 2013-14 to FY 2014-15 specified in clause 3 (1). |
05.09.2014 | |
34. |
35/2014 |
Shri Rajesh Kumar |
Petition under Section 43 of the Electricity Act 2003 read with Regulation 5, 6, 7 and 49 of the Electricity Supply Code for directing PSPCL to release connection under NRS category and impose penalty as per Regulation 7 of the Supply Code for failure to supply electricity within the period specified in Regulation 6 of the Supply Code. |
22.07.2014 | |
35. |
36/2014 |
Jagdish Soap Factory |
Petition U/S 142 / 146 of the Electricity Act, 2003 for punishment to the respondents, for their failure to adhere to time schedule for shifting of electric connection as provided in regulation 11.4 of the Electricity Supply Code and Related Matters Regulations 2007 AND For setting aside illegal, arbitrary, beyond jurisdiction demand for deposit of Monthly Minimum Charges for the period the connection under transfer was disconnected till reconnection at the new site. AND Suitable Order / directions directing the respondents to shift the LS connection of 300 KVA from Tappa Mandi (Barnala) to Hambran in Ludhiana Circle AND To direct respondents to pay suitable compensation for unnecessary and illegal delay in shifting of Industrial Connection and also damages for unauthorized and illegal demand of Minimum Monthly Charges. |
16.10.2014 | |
36. |
37/2014 |
Everest Power Private Limited |
Petition for approval of annual fixed cost of 100 MW Malana II Hydro-Electric Project for the period from 01.04.2014 to 31.03.2015; truing up of expenses for FY 2012-13 and FY 2013-14 under Section 62 of The Electricity Act, 2003 read with Regulation 56 (2), (3) and (4) of Punjab State Electricity Regulatory Commission (Conduct of Business) Regulations, 2005. |
31.08.2015
13.11.2024 On Remand by the Hon’ble APTEL |
|
37. |
38/2014 |
Punjab State Transmission Corporation Limited |
Regulation 22 of the Punjab State Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2005 as amended by Punjab State Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff), second amendment Regulations, 2012 notified vide Notification dated 17th September, 2012.
|
21.08.2014 | |
38. |
39/2014 |
Punjab State Transmission Corporation Limited |
Petition – Non-implementation of Automatic Demand Management Scheme resulting in violation of regulation 5.4.2 (d) of the Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2010. |
28.08.2014 | |
39. |
40/2014 |
Talwandi Sabo Power Limited |
Petition under Section 86 (1) (f) of the Electricity Act, 2003 read with Articles 12 and 17 of the Power Purchase Agreement dated 01.09.2008 seeking:- |
18.11.2014 | |
40. |
41/2014 |
Punjab State Power Corporation Limited |
Petition under Regulation 22 of PSERC (Terms and Conditions for Determination of Tariff), Regulations, 2012 for approval of capital expenditure for the implementation of Smart Grid Pilot Project at Sahibzada Ajit Singh Nagar |
28.08.2014 | |
41. |
42/2014 |
Suo-Motu |
Determination of generic levellised generation tariff for Renewable Energy Power Projects for FY 2014-15. |
05.09.2014 | |
42. |
43/2014 |
Shri Gurnek Singh Brar |
Petition under Section 86 (1) (a) of the Electricity Act 2003 and PSERC Regulations on Terms and Conditions for determination of tariffs and PSERC Conduct of Business Regulations regarding non issue of Tariff Order for 2014-15. |
05.09.2014 | |
43. |
44/2014 |
Vardhman Industries Ltd. and another |
Petition under regulation 47 to 50 of PSERC (Electricity Supply Code and Related Matters), Regulations, 2007, read with clause 51 of the Conditions of supply and clause 69 of the Punjab State Electricity Regulatory Commission (Conduct of Business) Regulations, 2005, for seeking interpretation / clarification regarding Service Connection Charges demanded by the respondent from the petitioners, having electricity connections in Cluster Scheme of the respondent., as the total load of the cluster would remain same as prayed by the petitioners and further as the existing line is able to cater the increase load and the whole line cost has already been paid by the petitioners. |
21.10.2014 | |
44. |
45/2014 |
GNA Udyog Limited |
Petition in the matter of extension of Load of GNA Udyog Limited A/c No.N36-RK01-00007 GT Road Distt. Jalandhar – Violation of Sec 47.4 Electricity Act 2003 |
17.09.2014 | |
45. |
46/2014 |
Regional Spinal Injuries Centre (RSIC) |
Petition under clause 23 (Interpretation of Tariff) of General Conditions of Tariff issued by the Commission read with regulation 5.8 of the Supply Code for modification of the General Conditions of Tariff and Schedule of Tariff to charge lowest tariff applicable to any category from the petitioner. |
31.10.2014 | |
46. |
47/2014 |
Punjab State Power Corporation Limited |
Petition regarding Voluntary Disclosure Scheme (VDS) for Domestic / Non-Residential Supply (DS/NRS), Small Power / Medium Supply (SP/MS) and A.P. Consumers. |
26.08.2014 | |
47. |
48/2014 |
Punjab State Power Corporation Limited |
Petition for approval under Section 86 (1) (b) of the Electricity Act, 2003 for power procurement on long term basis in terms of the Power Sale Agreement dated 1.9.2006 for 200 MW power from 1000 MW Karcham Wangtoo Hydel Project set up by Jaypee Karcham Hydro Corporation Limited (transferred to Himachal Baspa Power Company Limited). |
01.03.2018 | |
48. |
49/2014 |
Nabha Power Limited |
Petition under Section 86 (1) (f) of the Electricity Act, 2003 in relation to disputes arising under the Power Purchase Agreement (PPA) dated 18.01.2010 between the Petitioner herein – Nabha Power Limited (NPL) and the Punjab State Electricity Board (PSEB), which stands substituted by Punjab State Power Corporation Limited (PSPCL) as the successor entity on unbundling of PSEB (2x700 MW Rajpura Thermal Power Project). |
20.05.2015 | |
49. |
50/2014 |
A.K. Concast Private Limited |
Petition under clause 5.1, clause 5.5 and clause 6.3 (b) of Regulation 5 of Electricity Supply Code, praying for issuance of direction to the respondents to erect 11 kV line at the earliest as the same has already been sanctioned by the respondents and in pursuance of sanction, the requisite amount has already been deposited by the present petitioner with the respondent. |
20.10.2014 | |
50. |
51/2014 |
Atlantic Power Private Ltd. |
Petition under Section 86 (1) (a) of the Electricity Act, 2003 for determination of tariff in the case of the petitioner which is a small hydro project of 650 KW. |
26.05.2015 | |
51. |
52/2014 |
Nabha Power Limited |
Petition under section 86(1)(b) and 86(1)(f) of The Electricity Act, 2003 seeking: |
01.02.2016 | |
51 (a). |
52/2014 |
Nabha Power Limited |
Petition under section 86(1)(b) and 86(1)(f) of The Electricity Act, 2003 seeking: |
07.06.2017 | |
52. |
53/2014 |
Waterman Plastic Industries |
Petition under clause 10 of Electricity Supply Instructions Manual for directing the respondents to consider – 9% i.e. minimum permissible voltage drop and to reconsider the application of the petitioner for the supply of electric connection through 11 kV feeder. |
18.12.2014 | |
53. |
54/2014 |
Suo-Motu |
Technical audit of works executed by PSTCL and PSPCL for development of transmission/sub-transmission system from 01.04.2010 to 31.03.2013. |
04.12.2014 | |
54. |
55/2014 |
Suo-Motu |
Compliance of Judgment dated 11.09.2014 of Appellate Tribunal for Electricity in Appeal No.174 of 2012 filed by Punjab State Power Corporation Limited Versus PSERC impugning the Tariff Order dated 16.07.2012 passed by the Commission for the year 2012-13 in ARR Petition No.69 of 2011 |
14.05.2015 | |
55. |
56/2014 |
Suo-Motu |
Compliance of APTEL Judgment dated 12.09.2014 in Appeal No.245, 176, 237 and 191 of 2012 filed by Steel Furnace Association of India, Mawana Sugars Limited, Open Access Users Association and Mandi Gobindgarh Induction Furnace Association Versus Punjab State Electricity Regulatory Commission and Punjab State Power Corporation Limited against the Tariff Order dated 16.07.2012 passed by the Commission for FY 2012-13 in ARR Petition No.69 of 2011 |
07.05.2015 | |
56. |
57/2014 |
Surindera Cycles Pvt. Ltd. |
Petition under clause 47, 48, 49 and 50 of the Punjab State Electricity Regulatory Commission (Electricity Supply Code and Related Matters) Regulations, 2007 and other relevant sections of the Electricity Act, 2003 read with clause 9 of the Punjab State Electricity Regulatory Commission (Conduct of Business) Regulations, 2005, seeking clarification / modification / interpretation of the proviso of clause 9.1.2 (i) (c) of the Punjab State Electricity Regulatory Commission (Electricity Supply Code and Related Matters), Regulations, 2007; |
10.10.2014 | |
57. |
58/2014 |
Punjab Biomass Private Limited |
Petition under Section 61 and 86 of the Electricity Act, 2003 for redetermination / grant of revised generic / preferential tariff for purchase of power from petitioner’s 12 MW Rice Straw / Biomass based Power Plant at village Bhagaura, District Patiala on long term basis at tariff to be determined as per amendment No.1 of CERC RE Regulations 2012 with normative parameter for Rice Straw and travelling grate boiler base plant in order to promote generation of electricity from renewable sources of energy as envisaged under the Electricity Act, 2003, National Electricity Policy, National Tariff Policy and the NRSE Policies of GoP. |
25.06.2015 | |
58. |
59/2014 |
Punjab State Power Corporation Limited |
Petition for seeking approval regarding import of coal for PSPCL Thermal Power Stations. |
05.11.2014 | |
59. |
60/2014 |
JITF Urban Waste Management (Bathinda) Limited |
Petition under Regulation 7 of the CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2012 requesting the Commission to determine the project specific tariff under the Provisions of the said Regulations with respect to the upcoming Municipal Solid Waste to Energy Plant of the Petitioner (12 MW). |
19.04.2018 | |
60. |
61/2014 |
Suo-Motu |
Single Point Supply to Residential Colonies/Building Complexes/Shopping Malls / Commercial Complexes/ Industrial Estates. |
09.06.2015 | |
61. |
62/2014 |
Shri Jaspreet Singh |
Petition under clause 9 sub clause 1 of Code of Business (PSERC) against order of denial of new electricity connection by Assistant Executive Engineer, Sub-Division (Front end), Punjab State Power Corporation Limited, Patiala (NRS). |
22.10.2014 | |
62. |
63/2014 |
Punjab State Power Corporation Limited |
Petition under Section 23 of the Electricity Act, 2003 for the approval of regulatory measures taken in emergent grid operating conditions during the Tariff Year 2014-15. |
18.12.2014 | |
63. |
64/2014, |
Biomass Power Producers Association |
Petition under Section 94(1)(f) of Electricity Act, 2003 read with Section 64 (Chapter XIII) of PSERC Business Conduct regulations for Review of Generic levelised generation tariff for Renewable Energy Biomass based Power Projects for FY 2014-15 decided by the Commission vide Order dated 05.09.2014 (Petition No.42 of 2014 – Suo Motu) whereby the tariff of Bio-mass based Power Projects has been fixed as Rs.6.95 (Fixed Tariff Rs.2.54, Variable Tariff Rs.4.41).
|
02.02.2015 | |
64. |
67/2014 |
Suo-motu |
Approval of New Schedule Of Tariff For Charitable Hospitals set-Up under Persons with Disabilities (Equal Opportunities, Protection of Rights and Full Participation) Act, 1995. |
02.12.2014 | |
65. |
68/2014 |
COSMAS Research Lab Ltd |
Petition in the matter of demand of variable charges in addition to per KW/KVA charges for release of electricity connection of M/s COSMAS Research Lab Ltd A/c no U12-HB01-00049. Violation of Reg.9.1.1 (b) and Reg.6.1(e) of Supply Code. |
02.03.2022 | |
66. |
69/2014 |
G.N.General Mills |
Petition for removing of difficulty in grant of general category status for G.N.General Mills, Banga account number CB02/0180 vide CC No.44/2014 dated 27.08.2014 and grant of any other relief, order or directions which the Commission may deem fit and proper in the facts and circumstances of the case. |
13.07.2015 | |
67. |
70/2014 |
Ladhar Paper Mills |
Petition in the matter of computing the actual cost of 66 kV line and bay and refund of excess amount of security works deposited for releasing the electricity connection of M/s Ladhar Paper Mills, A/C No.X58-LS42-00002 – Violation of Reg. 19.7 Supply Code. |
22.04.2015 | |
68. |
71/2014 |
Punjab State Power Corporation Limited |
Petition for Aggregate Revenue Requirement and Determination of Tariff for FY 2015-16 filed by Punjab State Power Corporation Limited. |
30.03.2015 | |
69. |
72/2014 |
Punjab State Transmission Corporation Limited |
Petition for Aggregate Revenue Requirement and Determination of Tariff for FY 2015-16 filed by Punjab State Transmission Corporation Limited. |
30.03.2015 |