List of Commission orders/ judgments passed in various cases.
S.No. |
Petition
No. |
Filed
by |
Subject
matter |
Date of final decision.
|
|
1. |
1/2011 |
A.P. Multimetals Pvt. Ltd |
Petition for non issuance of permission/NOC and not deciding the application moved by the petitioners to the respondents for allowing Open Access for purchase of power to the applicants/petitioners, in violation of Punjab State Electricity Regulatory Commission (Open Access) Regulations, 2005, Electricity Policy of India and provisions of Electricity Act, 2003 |
28.04.2011 | |
2. |
2/2011 |
Punjab State Power Corporation Limited |
Petition regarding converting existing & newly applied power connections of cellular mobile phone tower sites from ‘NRS’ to ‘Industrial’ category. |
25.01.2011 | |
3. |
3/2011 |
Bedi Steel Pvt. Ltd. and another |
Petition under Reg. 31 of Open Access Regulations for issuing directions to the respondents to grant permission and ‘No Objection Certificate’ (NOC) / standing clearance to the petitioners for purchase of power under short term open access, as per provisions of PSERC Open Access Regulations-2005 amended up to date. |
28.04.2011 | |
4. |
VDS Order |
- |
Implementation of Govt. of Punjab directive issued under Section 108 of the Electricity Act 2003 for compliance of Policy notified by the State Govt. for regularization of unauthorized extension in load by AP consumers. |
16.02.2011 | |
5. |
4/2011 |
M/s Waryam Steel Castings (P) Ltd |
Petition for determination of the cost of supply and surcharge as directed by the Hon’ble Appellate Tribunal for Electricity vide its Order dated 16.7.2010 in Appeal No.192 of 2009. |
29.03.2011 | |
6. |
5/2011 |
Indian Acrylics Limited |
Petition under Section 86 read with Section 94(f) of the Electricity Act, 2003 for revision of rates of tariff of Bio-mass based power project ( Plants capacity 6.5 MW + 1.25 MW = 7.75 MW ) |
20.06.2013 | |
7. |
6/2011 |
M/s Siel Chemical Complex ( a unit of Mawana Sugars Ltd.) |
Petition under Sec. 142 and Sec. 23, 57 and 86(1)(i) of Electricity Act, 2003 r/w Reg.9 of PSERC (Conduct of Business) Regulations, 2005 for setting aside PR Circular No.1/2011 dated 19.01.2011 and for implementing the directions given by the Commission vide Order dated 30.4.2010 in Petition No.3 of 2010. |
15.02.2011 | |
8. |
7/2011 |
M/s. Vardhman Industries Ltd. |
Petition under Section 86(1) (c) of the Electricity Act 2003 read with Reg.31 of Punjab State Electricity Regulatory Commission (Open Access) Regulations, 2005 for grant of Open Access. |
19.05.2011 | |
9. |
8/2011 (Suo motu) |
Punjab State Power Corporation Limited |
Petition regarding converting existing & newly applied power connections of cellular mobile phone tower sites from ‘NRS’ to ‘Industrial’ category. |
11.08.2011 | |
10. |
9/2011 |
M/s Siel Chemical Complex ( a unit of Mawana Sugars Ltd.) |
Petition under Sec. 142 and Sec. 23, 57 and 86(1)(i) of Electricity Act, 2003 r/w Reg.9 of PSERC (Conduct of Business) Regulations, 2005 for setting aside PR Circular No.4/2011 dated 21.01.2011 and for implementing the directions given by the Commission vide Order dated 30.4.2010 in Petition No.3 of 2010. |
19.04.2011 | |
11. |
10/2011 |
M/s Siel Chemical Complex ( a unit of Mawana Sugars Ltd.) |
Petition under Sec. 142 and Sec. 23, 57 and 86(1)(i) of Electricity Act, 2003 r/w Reg.9 of PSERC (Conduct of Business) Regulations, 2005 for setting aside telephone messageNo.403/11 dated 02.02.2011 and for implementing the directions given by the Commission vide Order dated 30.4.2010 in Petition No.3 of 2010. |
5.4.2011 | |
12. |
11/2011 |
Mahaluxmi Steels |
Petition under Reg. 31 of PSERC Open Access Regulations 2005, read with Section 42 of the Electricity Act 2003 for issuing directions to the respondents to grant permission and ‘No Objection Certificate’ (NOC) / standing clearance to the petitioner for purchase of power under short term open access and renew the agreement for open access as per provisions of PSERC (Open Access) Regulations 2005 amended up to date and further for taking necessary action against the respondents under section 142 of the Electricity Act 2003. |
28.04.2011 | |
13. |
12/2011 |
Shree Ganesh Alloys |
Petition under Reg. 31 of PSERC Open Access Regulations 2005, read with Section 42 of the Electricity Act 2003 for issuing directions to the respondents to grant permission and ‘No Objection Certificate’ (NOC) / standing clearance to the petitioner for purchase of power under short term open access and renew the agreement for open access as per provisions of PSERC (Open Access) Regulations 2005 amended up to date and further for taking necessary action against the respondents under section 142 of the Electricity Act 2003. |
28.04.2011 | |
14. |
13/2011 |
M/s Mukesh Steels Limited and another |
Review petition under Section 64 of the PSERC (Conduct of Business) Regulations 2005 praying for reviewing the order dated 19.1.2011 passed by PSERC in petition No.31 of 2010 regarding redetermination of the cost of supply and surcharge as directed by the Hon’ble Appellate Tribunal for Electricity vide its Order dated 16.7.2010 in Appeal No.192 of 2009. |
28.10.2011 | |
15. |
14/2011 |
Punjab State Power Corporation Limited |
Petition regarding Determination of Seniority for Release of Connections. |
22.03.2011 | |
16. |
15/2011 |
Punjab State Power Corporation Limited |
Petition for approval of Fuel Cost Adjustment (FCA) Surcharge for 3rd Quarter (Oct. 10 to Dec. 10) FY 2010-11 |
09.05.2011 | |
17. |
16/2011 |
Punjab State Power Corporation Limited |
Petition for review of order of PSERC dated 6.1.2011 in Petition No.34 of 2010 regarding installation of CT/PT metering equipment by Open Access customers. |
20.04.2011 | |
18. |
17/2011 |
Antarctic Industries Limited |
Petition for determination of the surcharge as directed by the Hon’ble Appellate Tribunal for Electricity vide its order dated 10.12.2010 in Appeal No.180 of 2010. |
13.05.2011 | |
19. |
18/2011 |
M/s B.T. Steels Limited and others |
Petition under Reg. 31 of PSERC Open Access Regulations, 2005, for issuing necessary directions to the respondents to not to charge any amount from the petitioners on account of voltage surcharge on the electricity purchased in open access, in violation of the PSERC Open Access Regulations, 2005, and tariff order for the year 2010-2011 and agreement entered into between the parties and provisions of Electricity Act, 2003 and u/s 142 of Electricity Act, 2003, for taking necessary action against the respondents for violating the provisions of Electricity Act, 2003, PSERC Open Access Regulations and tariff order for the year 2010-11, by charging surcharge on the electricity purchased in Open Access. |
26.05.2011 | |
20. |
19/2011 |
Punjab State Power Corporation Limited |
Petition under Section 23 of the Electricity Act, 2003 for authorizing the PSPCL to impose power cuts, Peak Load Hours Restrictions and taking other Power Regulatory Measures for the year 2011-12. |
31.05.2011 | |
21. |
20/2011 |
M/s Lalru Industries Association C/o Rainbow Denim Limited |
Petition under Section 86 (1) (K) of Electricity Act, 2003 r/w Reg. 49 and 50 of PSERC (Electricity Supply Code and Related Matters) Regulations, 2007 (as amended upto date) for removal of difficulty pertaining to security deposit based on average monthly consumption charges as per Reg.15. |
29.03.2011 | |
22. |
21/2011 |
Viom Networks Limited |
Petition in the matter of Application of Industrial Tariff to Telecommunication Sector as per Industrial Policy-2009 of Govt. of Punjab. |
21.08.2012 | |
23. |
22/2011 |
Indus Towers Limited |
Petition in the matter of Late Payment Surcharge on electricity bills – Amendment to existing Clause 22.2 of General Conditions of Tariff. |
13.05.2011 | |
24. |
23/2011 |
M/s Northern India Steel Rolling Mills and another |
Petition under Reg.31 of PSERC Open Access Regulations, 2005 for issuing necessary directions to the respondents not to charge any amount from the petitioners on account of voltage surcharge on the electricity purchased in open access, in violation of PSERC Open Access Regulations, 2005 and Tariff Order for the Year 2010-11 and agreement entered into between the parties and provisions of Electricity Act, 2003 and u/s 142 of Electricity Act, 2003. |
26.05.2011 | |
25. |
24/2011 |
Indus Towers Limited |
Petition for clarification/ modification in the General Conditions of Tariff and Schedule of Tariff and for issuance of necessary directions to the respondent for application of Industrial Tariff to petitioner company/Telecommunication Sector as per Industry Policy-2009 of Government of Punjab. |
30.08.2012 | |
26. |
25/2011 |
Punjab State Power Corporation Limited |
Petition for continuation of tariff as revised by the Commission vide its order dated 23.04.2010 after 31.3.2011 till the time to ARR/Tariff for 2011-12 is determined by the Commission |
31.03.2011 | |
27. |
26/2011 |
M/s Mithila Malleables Pvt. Ltd |
Petition under clause 51 of Conditions of Supply under Reg.3.2 of PSERC (Electricity Supply Code & Related Matters) Regulations, 2007 regarding peak load exemption charges. |
30.06.2011 | |
28. |
27/2011 |
Universal Bio-mass Energy Pvt. Ltd. |
Petition for review order dated 26.11.2010 passed by the Commission in Petition No.11 of 2009 under Section 94 (1) (f) of the Electricity Act, 2003 |
16.8.2011 | |
29. |
28/2011 |
Punjab State Power Corporation Limited |
Petition regarding clause No.47 of PSERC ‘Conditions of Supply’ - Provision of 11 KV independent feeder for consumers |
07.09.2011 | |
30. |
29/2011 |
M/s Vallabh Steel Ltd |
Petition under Section 86(1) © of the Electricity Act 2003 read with Regulation 31 of PSERC (Open Access) Regulations, 2005 |
19.05.2011 | |
31. |
30/2011 |
Satguru Partap Singh Apollo Hospitals |
Petition for quashing Chief Engineer (Commercial), PSPCL Circular No.7 dated 01.02.2010 |
16.02.2012 | |
32. |
31/2011 |
M/s Aar Kay Industries |
Petition for grant of No Objection Certificate(NOC)/ Standing clearance and permission to the petitioner to purchase and get power/electricity under Open Access system as per provisions of Punjab State Electricity Regulatory Commission (Open Access) Regulations, 2005, Electricity Policy of India and provisions of Electricity Act, 2003. |
12.7.2011 | |
33. |
32/2011 |
M/s Chopra Steels Strips and others |
Petition for grant of No Objection Certificate(NOC)/ Standing clearance and permission to the petitioners to purchase and get power/electricity under Open Access system as per provisions of Punjab State Electricity Regulatory Commission (Open Access) Regulations, 2005, Electricity Policy of India and provisions of Electricity Act, 2003. |
12.7.2011 | |
34. |
33/2011 |
Punjab State Power Corporation Limited |
Petition regarding Conditions of Supply – Change of Name in Case of Tubewell Consumers. |
8.7.2011 | |
35. |
34/2011 |
PTC India Limited |
Petition under Reg. 69 of PSERC (Conduct of Business) Regulations, 2005 and Sections 86(1)(b) and 86(1)(k) of the Electricity Act, 2003 - for approval to allow Respondent No.1 to purchase electricity in accordance with the tariff calculated as per CERC Tariff Regulations, 2009. |
17.08.2012 | |
36. |
35/2011 |
Malwa Power Private Limited |
Petition under Section 86 read with Section 94(f) of the Electricity Act, 2003 for revision of rates of tariff of Biomass based power project with an aggregate capacity of 6 MW. |
26.03.2013 | |
37. |
36/2011 |
M/s Antarctic Industries Limited and others |
Petition for grant of No Objection Certificate (NOC)/Standing clearance and permission to the petitioners to purchase and get power/electricity under Open Access system as per provisions of Punjab State Electricity Regulatory Commission (Open Access) Regulations, 2005, Electricity Policy of India and provisions of Electricity Act, 2003. |
12.7.2011 | |
38. |
37/2011 |
Nabha Power Limited and another |
Petition under Section 86(1)(f) of the Electricity Act, 2003 in relation to disputes arising under the PPA dated 18.01.2010 between the petitioner herein – Nabha Power Limited and the Punjab State Electricity Board (PSEB), which stands substituted by Punjab State Power Corporation Limited (PSPCL) as the successor entity on unbundling of PSEB (2x700 MW Rajpura Thermal Power Project). |
23.04.2012 | |
39. |
38/2011 |
Nabha Power Limited and another. |
Petition under Section 86(1)(f) of the Electricity Act, 2003 in relation to disputes arising under the Power Purchase Agreement dated 18.01.2010 (PPA) between the petitioner herein – Nabha Power Limited and the Punjab State Electricity Board (PSEB), which stands substituted by Punjab State Power Corporation Limited (PSPCL) as the successor entity on unbundling of PSEB AND Failure and/or refusal of PSPCL to accept the petitioner’s claim for ‘Change in Law’ under Article 13 of the PPA on account of change in the applicable seismic zone of the Project site from zone III to zone IV and allow consequential adjustment in the tariff and extension of time for achieving the Scheduled Commercial Operation Date (SCOD) under the terms of the PPA. AND Failure and/or refusal of PSPCL to accept the petitioner’s claim for ‘change in law’ under Article 13 of the PPA on account of change in earlier approved location of the railway siding and other related railway infrastructure for the Project after the execution of the PPA and allow consequential adjustment in the tariff under the terms of the PPA. |
1.10.2012 | |
40. |
39/2011 |
M/s Siel Chemical Complex |
Petition under Section 86 R/W Regulation 31 of Open Access Regulations, 2005 as amended upto date. |
12.7.2011 | |
41. |
40/2011 & 52/2011 |
Punjab State Power Corporation Limited |
Petition for approval of Fuel Cost Adjustment (FCA) Surcharge for 4th Quarter (Jan. 2011 to March, 2011) of FY 2010-11 (Petition No.40 of 2011) |
18.10.2011 | |
42. |
41/2011 |
M/s A.K.Alloys Pvt. Ltd |
Petition for grant of No Objection Certificate (NOC)/Standing clearance and permission to the petitioner to purchase and get power/electricity under Open Access system as per provisions of Punjab State Electricity Regulatory Commission (Open Access) Regulations, 2005, Electricity Policy of India and provisions of Electricity Act, 2003. |
18.8.2011 | |
43. |
42/2011 |
Punjab State Power Corporation Limited |
Petition regarding release of Electric Connection to domestic consumers in the unapproved colonies in the State of Punjab. |
12.7.2011 | |
44. |
43/2011 |
M/s A2Z Maintenance & Engineering Services Ltd |
Petition for determination of project specific Tariff for the Co-generation based Power Projects of 15 MW capacity each at Cooperative sector Sugar Mills at Morinda , Nakodar and Fazilka implemented on Build, Own, Operate and Transfer (BOOT) basis under Section 62, 64 read with 86(e) of the Electricity Act, 2003. |
14.9.2011 | |
45. |
44/2011 |
A.B. Grain Spirits Pvt. Ltd. |
Petition under Section 86 read with Section 94(f) of the Electricity Act, 2003 for the revision of tariff rates fixed by the Commission vide Order dated 13.12.2007 after the year 2011-12 in respect of Bio-mass Co-generation Power Plant with aggregate capacity of 5.5 MW. |
19.09.2012 | |
45.a. |
44/2011 |
A.B. Grain Spirits Pvt. Ltd. |
Petition under Section 86 read with Section 94(f) of the Electricity Act, 2003 for the revision of tariff rates fixed by the Commission vide Order dated 13.12.2007 after the year 2011-12 in respect of Biomass Co-generation Power Plant with aggregate capacity of 5.5 MW. |
07.10.2014 | |
46. |
45/2011 |
Punjab Bio-mass Power Limited |
Petition under Section 86 of the Electricity Act, 2003 for revision of rates fixed by the Commission vide Order dated 13.12.2007 whereby the tariff of Bio-mass based Power Projects was fixed as Rs.3.49 per unit (with base year 2006-07) with five annual escalations @ 5% upto 2011-12 and for implementing the order dated 30.9.2010 passed by the Commission in Petition No.32 of 2010 (Suo-Motu) vide which the Commission has determined tariff rate as Rs.5.05 per unit with effect from FY 2010-11. |
28.03.2012 | |
47. |
46/2011 |
M/s Hero Cycles Limited and others |
Petition U/S 142/146 of the Electricity Act, 2003 for punishment to the respondents, for their failure to comply with Orders/directions issued by the Appellate Tribunal for Electricity, New Delhi in Appeal No.15 of 2010, decided on 31.8.2010. |
28.02.2012 | |
48. |
47/2011 |
Shree Krishna Captive Energy Pvt. Ltd. |
Petition under Section 62, read with Section 61(h) and Section 86(1)(e) of the Electricity Act 2003 read with Section 151 of the Code of Civil Procedure praying for Fixation of Tariff for Biogas Power Plants based on Otto Cycle 800 KW each (Three No. Plants) |
21.9.2011 | |
49. |
48/2011 |
Shri Gurnek Singh Brar |
Petition under Section 65 of the Electricity Act 2003, Section-4(7) of PSERC Terms and Conditions for determination of Tariff Regulations and Section 53 of PSERC (Conduct of Business) Regulations regarding subsidy payment to PSPCL. |
15.11.2011 | |
50. |
48/2011 |
Shri Gurnek Singh Brar |
Petition under Section 65 of the Electricity Act 2003, Section-4(7) of PSERC Terms and Conditions for determination of Tariff Regulations and Section 53 of PSERC (Conduct of Business) Regulations regarding subsidy payment to PSPCL. |
28.11.2011 | |
51. |
49/2011 |
M/s Lalru Industries Association |
Petition under Section 86(1) K of Electricity Act, 2003 read with Regulation 49 and 50 of PSERC (Electricity Supply Code and Related Matters) Regulations, 2007 (as amended upto date) for removal of difficulty pertaining to security deposit based on average monthly consumption charges as per Regulation 15 also seeking stay of demand notice dated 18.7.2011 raised by respondent for security deposit during the pendency of the present petition and the proposal dated 7.6.2011 to the Supply Code Review Panel. |
11.08.2011 | |
52. |
50/2011 |
Punjab State Power Corporation Limited |
Petition regarding imposing regulatory measures on Category IV Continuous Process Industrial Consumers |
7.10.2011 | |
53. |
51/2011 |
Suo motu petition |
Compliance of the directions of the Hon’ble Punjab and Haryana High Court order dated 19.07.2011 passed in CWP No. 4881 of 2011 and other connected petitions being CWPs No.18135 of 2007 and 3104 of 2009. |
19.9.2011 | |
54 |
53/2011 |
Shri Gurnek Singh Brar |
Petition under Section 86-1A, 86-1B, 79(4), 86(3), 86(4) of the Electricity Act 2003 and Regulation 46 of PSERC (Conduct of Business) Regulations AND MOU dated 28.7.2010 for Extension Unit at Rajpura and MOU dated 4.10.2010 for Extension Unit at Talwandi Sabo. |
11.09.2014 | |
55 |
54/2011 |
M/s Universal Bio-mass Energy Pvt. Ltd. |
Petition under Section 94 (1) (f) of the Electricity Act 2003 for review of the Order dated 16.8.2011 passed by the Commission in Petition No.27 of 2011 and Review of Order dated 26.11.2010 passed by the Commission in Petition No.11 of 2009 titled M/s Universal Bio-mass Energy Pvt. Ltd. Versus State of Punjab and others. |
15.11.2011 | |
56. |
55/2011 |
Punjab State Power Corporation Limited |
Petition under Section 42 (4) of the Electricity Act, 2003 and Section 18 of Punjab State Electricity Regulatory Commission (Open Access) Regulations 2005 |
22.05.2012 | |
57. |
56/2011 |
M/s Mithila Malleables Pvt. Ltd. |
Petition under clause 51 of ‘Conditions of Supply’ under Reg.3.2 of PSERC (Electricity Supply Code & Related Matters) Regulations, 2007 ‘regarding peak load exemption charges’. |
30.09.2011 | |
58. |
57/2011 |
M/S Mithila Malleables Pvt. Ltd. |
Petition under clause 51 of ‘Conditions of Supply’ for modification/clarification regarding clause 49 of the Conditions of Supply and for removing the anomaly regarding restricted load allowed to the Induction Furnaces and to Arc furnaces. |
12.12.2012 | |
59. |
58/2011 |
Shree Krishna Captive Energy Pvt. Ltd |
Petition under Section 62, read with Section 61(h) and Section 86(1)(e) of the Electricity Act 2003 read with Section 151 CPC for Fixation of Tariff for 400 KW Biogas Power Plants based on Otto Cycle (Bio methanation process) |
30.05.2012 | |
60. |
59/2011(Suo motu) |
Suo Motu |
Determination of generic levelised generation tariff for Renewable Energy Power Projects |
31.10.2011 | |
61. |
60/2011 |
Punjab State Power Corporation Limited |
Review Petition under Section 94(1)(F) of the Electricity Act, 2003 read with Section 42(4) for review of order dated Ist July, 2011 of PSERC regarding terms & conditions for intra-State Open Access Regulations, 2011. |
04.05.2012 | |
62. |
61/2011 |
M/S JMP Industries |
Petition under Section 41 of PSERC (Terms and Conditions for Intra-state Open Access) Regulations, 2011 read with section 142 and 45 of the Electricity Act, 2003, for quashing the demands raised by the respondents on account of alleged peak load hours violations by drawing electricity under open access system, against the terms and conditions of open access agreements dated 21.10.2010 and 26.5.2011 entered into between the applicant and respondents, and provisions of PSERC (Terms and Conditions for Intra-state Open Access) Regulations, 2011; PSERC Open Access Regulations, 2005 and Electricity Act, 2003. |
25.11.2011 | |
63. |
62/2011 |
M/s A2Z Maintenance & Engineering Services Ltd. |
Petition for determination of project specific Tariff for Independent Power Projects of 15 MW capacity each at Cooperative sector Sugar Mills at Morinda , Nakodar and Fazilka implemented on Build, Own, Operate and Transfer (BOOT) basis under the provisions of Sections 61, 62 and 86(1)(e) of the Electricity Act, 2003 and under the provisions of Regulation 7 of the CERC RE Regulations, 2009. |
15.03.2012 | |
64. |
63/2011 |
Punjab Energy Development Agency |
Petition under Section 94 (1) (f) of Electricity Act, 2003 for review of Clause 5 (4) of the R.P.O. Regulations notified by the Commission vide notification dated 03.06.2011. |
04.05.2012 | |
65. |
64/2011 |
Punjab State Power Corporation Limited |
Petition under Section 61 of the Electricity Act, 2003 read with Regulations 45 & 46 of the PSERC (Terms & Conditions for Determination of Tariff) Regulations, 2005 and Regulations 70 & 71 of PSERC (Conduct of Business) Regulations, 2005. |
10.10.2012 | |
66. |
65/2011 |
Shri Harinder Puri, Secretary, Steel Furnace Association of India (Punjab Chapter) C/o Upper India Steel Mfg. & Engg. Co. Ltd. |
Petition for waiver of cross subsidy surcharge on power purchase under Open Access in case of mandatory power cut imposed by the Board (under Section 46 of the PSERC Open Access Regulations) |
08.08.2012 | |
66.a. |
65/2011 (on Remand by APTEL vide Judgement dated 01.08.2014 in Appeal No. 38 of 2013) |
Steel Furnace Association of India |
Petition for waiver of cross subsidy surcharge on power purchase under Open Access in case of mandatory power cut imposed by the Board (under Section 46 of the PSERC Open Access Regulations) |
17.09.2014 | |
67. |
66/2011 |
Rice Millers Association |
Petition against Clause No. 18.4 of the General Conditions of Tariff approved by the Punjab State Electricity Regulatory Commission. |
23.10.2012 | |
68. |
67/2011 |
Punjab State Transmission Corporation Limited |
Petition for ARR & Determination of Tariff for FY 2012-13 filed by Punjab State Transmission Corporation Limited |
16.07.2012 | |
69. |
68/2011 |
Punjab State Power Corporation Limited |
Petition for Fuel Cost Adjustment (FCA) Surcharge for 2nd Quarter (July, 2011 to Sept. 2011) of FY 2011-12. |
16.07.2012 | |
70. |
69/2011 |
Punjab State Power Corporation Limited |
Petition for Aggregate Revenue Requirement and Determination of Tariff for FY 2012-13 filed by Punjab State Power Corporation Limited |
16.07.2012 | |
71. |
70/2011 |
Punjab State Power Corporation Limited |
Petition regarding AP Policy Guidelines for release of Agricultural Pump Sets in the State of Punjab during 2011-12 |
16.02.2012 | |
72. |
71/2011 |
Punjab State Power Corporation Limited |
Petition regarding imposing regulatory measures on Category IV Continuous Process Industrial Consumers on emergent basis. |
05.06.2012 |