List of  Commission orders/ judgments passed in various cases.

 

 

 

 

S.No.

Petition No.

Filed by

Subject matter

Date of final decision.

 

1.

1/2008

: PSEB

 

 

  Petition seeking additional time for filing of ARR/Tariff Petition for the year 2008-09 upto January 31, 2008 .

18.2.2008

2.

2/2008

  Punjab State Electricity Board, The Mall, Patiala

Petition for approval of bidding document (RFQ) for the proposed bidding process to be undertaken by the Petitioner for procurement of 1800 MW (±10 %) of power under Case 1, under the “Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees”, issued by Ministry of Power, Govt. of India vide notification No.23/11/2004-R&R (Vol. II) dated 19.01.2005 under Section 63 of the Electricity Act, 2003, as amended from time to time.

05.09.2008

 

 

3.

2/2008

  Punjab State Electricity Board

Petition for approval of bidding document (RFQ) for the proposed bidding process to be undertaken by the Petitioner for procurement of 1800 MW (±10 %) of power under Case 1, under the “Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees”, issued by Ministry of Power, Govt. of India vide notification No.23/11/2004-R&R (Vol. II) dated 19.01.2005 under Section 63 of the Electricity Act, 2003, as amended from time to time.

22.12.2008

 

 

4.

3/2008

  Punjab State Electricity Board

Petition under Section 23 of the Electricity Act, 2003 for authorizing the Board to impose Power cuts, Peak Load Hours Restrictions and taking other Power Regulatory Measures for the year 2008-09.

29.4.2008

5.

4/2008

  M/s Indian Acrylics Ltd.

Petition for issuing directions to the PSEB to enter into revised PPA with the petitioner-Company, to grant the benefits of the NRSE Policy-2006 and to incorporate the said rates as per the Order dated 13.12.2007 passed by PSERC, in the revised PPA and to grant the benefits of the same to the petitioner-Company

05.08.2008

6.

5/2008 (on remand by Appellate Tribunal for Electricity New Delhi)

  Northern Railways

Redetermination of Tariff for the Northern Railways for the year 2008-09

19.01.2011

7.

6/2008

  M/S Winsome Yarns Limited.

Miscellaneous Application to review the Commission’s Order dated January 8, 2008 in Petition No.30 of 2007 vide which petitioner’s petition has been ordered to be disposed off in terms of Order dated December 13, 2007 without passing any orders on Misc. Application dated December 28, 2007.

05.08.2008

 

8.

7/2008

(review order)

  Talwandi Sabo Power Limited,

  PSEB Patiala

Petition for approval of deviations from the “Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees”, issued by the Ministry of Power, Govt. of India, under Section 63 of the Electricity Act, 2003 – Talwandi Sabo Power Limited.

22.4.08

9.

7/2008

  Talwandi Sabo Power Limited,

  PSEB Patiala

Petition for approval of deviations from the “Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees”, issued by the Ministry of Power, Govt. of India, under Section 63 of the Electricity Act, 2003 – Talwandi Sabo Power Limited.

17.4.08

10.

8/2008

: PSEB

  Petition for continuation of Tariff as revised by the Commission vide its order 17.9.2007 after 31.3.2008 till the time ARR/Tariff for 2008-09 is determined by the Commission.

31.3.2008

11.

9/2008

  Punjab State Electricity Board, The Mall, Patiala.

Issue of Commercial Circular No. 34 of 2008 allowing refund of the amount charged on account of tariff hike to the consumers with effect from 1.9.2007 for the period from 1.9.2007 to 31.3.2008.

29.08.2008

 

 

12.

10/2008

  G.V.K Power (Goindwal Sahib) Ltd.

Review Petition under Section 94(1)(f) of the Electricity Act 2003 read with Regulation 64 of the Punjab State Electricity Regulatory Commission (Conduct of Business) Regulations, 2005 for review/ clarification/ modification of Order dated 29.4.2008 passed by the Hon’ble Commission in Petition No.4 of 2007

06.08.2008

 

 

13.

11/2008

  Nabha Power Ltd.

Petition for approval of deviations from the “Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees”, issued by the Ministry of Power, Govt. of India, under Section 63 of the Electricity Act, 2003 – Rajpura Thermal Power Project.

14.08.2008

 

 

14.

12/2008

  Er. Padamjit Singh, Chief Engineer, PSEB (Retd), 45, Ranjit Bagh, Passey Road, Patiala.

Petition for issue of directions by the Commission and for action under Section 142 and 146 of the Electricity Act, 2003 for non-payment of Cash Subsidy by the Government of Punjab to PSEB as prescribed in Commission order dated 13.09.07 and Tariff Order 2008-09 dated 03.07.08 for the year 2008-09.

04.09.2008

 

 

15.

13/2008

  Punjab State Electricity Board, The Mall, Patiala

Petition for approval of Project cost of 168 MW Shahpur Kandi Hydro Electric Project under Section 86 (a) & (b) read with 62(a) of the Electricity Act, 2003.

13.10.2008

 

 

16.

14/2008

  Punjab State Electricity Board

Petition No.14 of 2008 under Section 94 of the Electricity Act, 2003 for review of Punjab State Electricity Regulatory Commission Tariff Order dated July 3, 2008 of 2008-09.

24.03.2009

 

 

17.

15/2008

 Punjab State Electricity Board

Petition/Representation by the Punjab State Electricity Board for Amendment/Modification/Substitution of the provisions of the Tariff Regulations, 2005.

19.08.2009

18.

16/2008

  Gidderbaha Power Limited

Petition for approval of deviations from the “Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees”, issued by the Ministry of Power, Govt. of India, vide Notification No.23/11/2004-R&R (Vol.II) dated 19.1.2005 (including its amendments dated 30.3.2006, 18.8.2006 and 27.9.2007) under Section 63 of the Electricity Act, 2003.

22.09.2008

 

 

19.

17/2008

  Nabha Power Limited, PSEB Building, The Mall, Patiala, Admn. Office: # 25, 29 & 30, Officers Flat, Shakti Vihar, PSEB, Patiala.

Petition for approval of deviations from the “Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees”, issued by the Ministry of Power, Govt. of India, vide notification No.23/11/2004-R&R (Vol. II) dated 19-01-2005 (including amendments dated 30.03.2006, 18.08.2006 and 27.09.2007), under Section 63 of the Electricity Act, 2003.

05.09.2008

 

 

20.

18/2008

 Punjab State Electricity Board

Petition for approval of Fuel Cost Adjustment (FCA) surcharge for 1st Quarter, FY 2008-09.

08.09.2009

21.

19/2008

 Punjab State Electricity Board

Petition for Regulations covering applicability of U.I. tariff in case of Open Access Customers for mismatch of injection and drawl.

04.01.2010

22.

20/2008

  Punjab State Electricity Board

Petition under Section 63 of the Electricity Act, 2003 for adoption of tariff for the Talwandi Sabo Thermal Power Project at village Banawala, District Mansa, Punjab

14.01.2009

 

 

23.

21/2008

  Punjab State Electricity Board

Review Petition with reference to PSERC Order dated September 5, 2008 in Petition No.2 of 2008 for considering request of PSEB for issuance of NIT and RFP for procurement of 1800 MW + 10% of power.

22.12.2008

 

 

24.

22/2008

  Nabha Power Limited

Petition for approval of Bidding process under Clause 5.7 of the Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees (Guidelines) issued by the Ministry of Power, Government of India, vide notification No.23/11/2004-R&R (Vol. II) dated 19.01.2005 (including amendments dated 30.03.2006, 18.08.2006 and 27.09.2007).

08.12.2008

 

 

25.

23/2008

 Punjab State Electricity Board

Petition for approval of Fuel Cost Adjustment (FCA) surcharge for 2nd Quarter, FY 2008-09.

08.09.2009

26.

24/2008

  Punjab State Electricity Board

Petition for extension of time for filing ARR/Tariff Petition for the year 2009-2010 under Regulation 13 of the Punjab State Electricity Regulatory Commission (Terms & Conditions for Determination of Tariff) Regulations 2005.

22.12.2008

 

 

27.

25/2008

 M/s Winsome Yarns Limited

Petition for direction to PSEB, under Reg.28 of PSERC (Open Access) Regulations, 2005, to carry out the process of evacuation of power, produced from renewable resources, under the open access for banking and wheeling for captive consumption and third party sale.

27.05.2009