PUNJAB STATE ELECTRICITY REGULATORY COMMISSION
SCO 220-221 SECTOR-34-A CHANDIGARH
Petition No. 7 of 2003.
Date of order: 14.7.2003
In the matter of:
Petition for approval of supply of power, laying of 132 KV line and fixation of wheeling charges for transfer of power from Himachal Pradesh State Electricity Board .
AND
In the matter of:
M/s. Grasim Industries Limited.
Present:
Sh R.S.Mann, Chairman.
Sh. L.S.Deol, Member.
For the Petitioner:
Sh. Vinod Bahety, Dy. Manager (Finance).
ORDER:
Sri Vinod Bahety appearing for the petitioner has requested that in view of the fresh petition having
been filed this petition may be dismissed as withdrawn. Allowed as prayed.
Sd/-
Sd/-
(L.S.Deol)
(R.S.Mann)
Member
Chairman.
Place: Chandigarh
Dated: 14.7.2003.