Petition No. 58 of 2007
Date of order: 2.01.2008
In the matter of: | Petition for approval of deviations from the “Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees” issued by Ministry of Power, Govt. of India, Vide notification No.23/11/2004-R&R Vol. II dated 19-01-2005 (including its amendments dated 30.3.2006 and 18.8.2006) under section 63 of the Electricity Act, 2003. |
AND | |
In the matter of: | Nabha Power Limited |
Present: | Shri Jai Singh Gill, Chairman |
Shri Satpal Singh Pall, Member | |
Nabha Power Limited (NPL) filed this petition on 03.12.2007 seeking approval of deviations from the Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by the Distribution Licensees (Guidelines issued by the Ministry of Power, Govt. of India through Notification No.23/11/2004-R&R Vol.II dated 19.1.2005) including subsequent amendments. The petitioner company has been incorporated under the Companies Act, 1956 as a wholly owned company of the Punjab State Electricity Board (PSEB) with its registered office at The Mall, Patiala. NPL is a Special Purpose Vehicle (SPV) for the establishment of a coal based thermal power plant of a contracted capacity in the range of 1080 MW -1320 MW to be set up at Village Nalash (near Rajpura), District Patiala (Punjab), India on build own and operate (BOO) basis (hereinafter referred to as the “Project”).
The Commission notes that the petitioner has sought approval for effecting certain deviations in the Standard Bid Document pertaining to Request for Qualification (RFQ). In addition, concurrence has also been sought to the deviations made in the time table for the bidding process. Furthermore, the petitioner has also prayed for approval to shift the site of the project from Nabha to Rajpura. The Commission has given its careful consideration to the grant of approval to the deviations keeping in view the provisions in clauses 3.1, 3.2, 5.16 and 5.18 of the Guidelines. The Commission’s findings on each deviation for which approval has been sought are discussed in the succeeding paragraphs:
The standard notice and RFQ documents require the procurer to enlist tasks completed before publication of RFQ. Clause 3.2 of the Guidelines further enumerates such tasks and stipulates the time by which these are to be completed. The tasks are:
Further, as per the Guidelines, notification under Section-6 of the Land Acquisition Act is required to be issued before issuance of the RFP. The petitioner has requested to allow this notification to be issued before submission of the RFP bids by the bidders. The Commission observes that with the publication of the notification under Section-6, the area to be acquired gets frozen and this information is an essential input for the bidders. The Commission is , thus, inclined to permit this deviation only to the extent that the Section 6 notification must be issued within 90 days of issuance of RFP.
As per recent amendments in the Guidelines, the Rapid Environmental Impact Assessment (EIA) report should be available before the publication of the RFQ. The petitioner has submitted that the Rapid EIA Report will be available two months before submission of the RFP. Furthermore, the Guidelines require that the proposal for environmental clearance must also be submitted to the competent authority before issuance of the RFP whereas the petitioner has sought approval for submission of this proposal before receipt of RFP. The Commission observes that non-availability of the Rapid EIA report before publication of the RFQ would not in any way jeopardize the bidding process and accordingly allows this deviation with the stipulation that this report shall be forthcoming before the RFP is issued. In so far as submission of the proposal for environmental clearance to the concerned authority is concerned, the Commission appreciates that obtaining such clearance is a long drawn process which does not directly affect other time lines. Moreover, the stipulation for the environmental clearance proposal requiring submission before issue of RFP has been prescribed only recently in the amended Guidelines issued by the Ministry of Power on 27.9.2007. In the light of the above, the Commission allows the petitioner to submit the application for environmental clearance to the concerned authority within 60 days of issuance of the RFP.
The Guidelines provide that water linkage should be available before the publication of the RFQ. The Petitioner has requested that the water linkage for the proposed power station be allowed to be firmed up before submission of RFQ. The Commission allows deviation in this respect to the extent that this activity be completed within 45 days of the publication of the RFQ.
The Guidelines require that the requisite hydrological, geological, meteorological and seismological data necessary for preparation of the Detailed Project Report (DPR) be made available before issue of RFP while the petitioner intends to do so two months before the submission of RFP by the bidders. The Commission is of the view that availability of the basic data is an essential requirement and any deviation on this account will be prejudicial to the bidding process. Accordingly, the Commission orders that the requisite hydrological, geological, meteorological and seismological data which is an essential input for preparation of the DPR be made available before issuance of RFP.
sd/- | sd/- |
(Satpal Singh Pall) | (Jai Singh Gill) |
Member | Chairman |