SCO
220-221 SECTOR-34-A
Petition No. 21 of 2002
Date of hearing:5.2.2004
Date of order:
IN THE
MATTER OF: Petition filed by M/S Chandigarh Distillers & Bottlers Ltd. for approval of
Power Purchase Agreement (PPA) for 2.5 MW
co-generation Plant at existing distillery at Banur,
Tehsil Rajpura Distt.
AND
IN THE MATTER OF:
M/s Chandigarh
Distillers & Bottlers Ltd.
VERSUS
Punjab State Electricity Board & others Respondent.
Present: Shri R.S. Mann, Chairman.
Shri L. S. Deol, Member.
For the petitioner: Sh. L.M.Suri, Senior Advocate,
Sh. Vivek Bakshi, Company Secretary.
For the PEDA & Govt.: Sh. A.K.Singla, Director/ PGL and
Sh. M.P.Singh Sr.Manager.
For the PSEB: Sh. B.D.Bansal, Director/Sales.
Sh. V.K.Shanan, Dy. Director/ Sales.
ORDER:
This petition
has been filed by the petitioner for granting approval to the project and for
fixing the tariff for sale of 2.5 MW energy by the petitioner to PSEB in
accordance with NRSE Policy 2001 notified by the Government of Punjab. Further it has been prayed that the Board be
directed to provide the evacuation system for the purchase of energy from the
generation site at its own cost and to extend all benefits and incentives as
applicable under the NRSE Policy 2001. It is stated in the petition that the
petitioner is already operating one
Turbine with capacity of 0.8 MW and that another Turbine of 3.1 MW capacity has
been installed by the petitioner. It is further stated that out of total 3.9 MW
energy, 1.4 MW is for captive use and 2.5 MW is surplus for sale to PSEB. It is also stated that PSEB granted approval
for captive use of energy for the said Turbine and in the approval it is
stipulated that the petitioner would be required to obtain necessary approval
from the Commission in order to sell the surplus power to the Board.
2. NRSE Policy was formulated
by the State Government for development and promotion of new and renewable
sources of energy based technologies and energy conservation measures. Under this policy incentives are offered to
the investors for the setting up of power projects based on new and renewable
sources of energy. PEDA is to provide
complete project support and facilitation services and is to act as nodal agency for promoting such
projects.
3. The State Government had
issued notification dated 28.10.2002 under Section 39 of the Electricity Regulatory
Commissions Act, 1998 directing the Commission to comply with the NRSE Policy
issued by the Government on July 24, 2001.
4. The petition was admitted
and notices were issued to the Respondents to file their replies.
5. Government and PEDA in their
replies submitted that as the project has not been set up as per procedure
prescribed under the NRSE Policy and PEDA was
also not the facilitator in the
Project, the petition may be dismissed. The Board, in reply, stated that the petitioner was granted
permission on 25.8.2000 as standby source of supply, that permission
for installation of 3.1 MW Captive Power Plant (CPP) was accorded for its
in-house consumption on 27.9.2002 and that there is no commitment on the part
of the PSEB to import power from the petitioner. It was further submitted in
the reply of the Board that the qualifying requirement of treating any project
as NRSE based power project is that the proposal should have the approval of
PEDA as it is the nodal agency for the implementation of the NRSE Policy
of the Punjab Government. The Board prayed that the petitioner may be
asked to furnish approval of its project by PEDA before reply on merits is
submitted for consideration by the Commission.
6. The petitioner filed
rejoinder in which it was stated that the petitioner did not accept the plea of
the Respondents that the Project of the petitioner does not fall under the NRSE
Policy 2001 merely because it has not been promoted or facilitated by
PEDA. It was further submitted in the
rejoinder that the Company has approached the Government of Punjab in the
matter and is confident of getting a favourable reply
in the matter confirming that the project is covered under the NRSE Policy.
7. Vide order dated 10.1.2003,
petitioner, PEDA and the Government were allowed to file additional affidavits.
8.
On
i) The Commission may permit PSEB to buy power from the Developers at the rates provided in the NRSE Policy of State Government circulated vide notification dated 24.7.2001 and PSEB may be allowed to pass on full cost of the power so purchased in the ARR and load it to the consumers.
ii) Since the transmission lines/works required to be laid for evacuating this power to the nearest PSEB Grid Sub Station could not be included in the ARR (being capital expenditure), this cost should be borne by the Developers (except for PPAs already signed with PEDA).
iii) All other terms & conditions/incentives for the Private projects developed through PEDA shall be same as envisaged in the NRSE Policy – 2001 of the State Government.
iv) In the changed scenario in which per unit cost of generation is to be determined by the State Regulatory Commission, for future projects the NRSE Policy circulated by the State Government needs to be reviewed/recast for which Secretary, Science & Technology, shall bring suitable proposal for consideration of CMM.
v) As per the policy guidelines of the State Government the developers may be allowed to install suitable metering at their generating end to record the generation made for sale to PSEB and billing done on the basis of readings recorded by the meter installed at the generator end. The power available for sale to PSEB to be included in the ARR shall be units so generated and recorded minus 5% transmission losses.
The matter was considered by the Commission
and it was decided that the letter of
9. PEDA and the Government
filed additional replies in which it was stated that the case had been taken up
by the Empowered Committee constituted under NRSE Policy 2001 for granting
approval/clearance for the Project, that the Committee on 22.4.2003 decided
that all such projects which had come up after notification of NRSE Policy and
whose financial closure was after the declaration of the Policy 2001, could be
taken into consideration for extending the benefits of NRSE Policy 2001 and
that as the financial closure of this project was on 9.3.2002, the Empowered
Committee had granted approval for
covering the project under the NRSE Policy.
10. The case was taken up by the
Commission on 19.5.2003 when the Board requested for time to file counter reply to the reply filed by PEDA and
Government. This was allowed. The Board
filed counter reply to the reply filed by PEDA and Government on 12.5.2003
wherein it was requested that the petitioner may be asked to sign
Implementation Agreement and that the Government may be directed to review/
recast NRSE Policy for future project to enable the Commission to determine the
actual cost of generation payable by PSEB under NRSE Policy. The petitioner
filed counter reply to the reply filed by the Board on 8.7.2003 in which it was
stated that the Implementation Agreement has been signed on 18.6.2002 with
PEDA, that approval of PSEB had been obtained for the Commissioning of 3.1 MW
co-generation plant vide letter dated 27.9.2002, that the petitioner has
already taken effective steps to implement the project, that the Turbine has
been commissioned in October, 2002, that the power produced is being used for
in-house consumption and that in view of all this, the project cannot be
treated as ‘future project’ as mentioned in the Government letter dated
18.2.2003. The Government and PEDA also filed their submissions similar to
those of the petitioner.
11. A question arose regarding
the Government direction dated
12. On receipt of Govt. response
dated 6.1.2004, parties were directed to file their submissions with regard to
the said reference. The Board filed its submissions on 20.1.2004 which are
reproduced below :-
“Notwithstanding the objections of PSEB about the higher per unit rate recommended by Punjab Government to be paid to the Developers of NRSE based projects in the State as per policy & guidelines of the Punjab Govt. and the power of the Hon’ble State Electricity Regulatory Commission to regulate electricity purchase as per Section 22(1) (c ) of ERC Act, 1998 & Section 86 (1) (b ) of EA, 2003; PSEB shall have no objection to purchase this power and make payment to the power developers at the rate provided in the NRSE Policy, provided the same are approved and allowed as expenditure in the annual Revenue Requirement of the Board by the Commission”.
This stand of
the PSEB is apparently quite different from the position taken by it through
its reply dated
13. Vide order dated 29.1.2004,
petitioner was directed to file additional affidavit to explain as to why the
project should be covered under NRSE Policy and allowed NRSE rates. To this
purpose, the petitioner was to explain as to how it can be inferred that the
project has been set up in view of and under NRSE Policy and if so, as to why
the procedure laid down for NRSE project has not been followed by the
petitioner from the beginning. The
petitioner was further directed to explain as to why ABT principle of tariff
determination should not be followed while determining the price of power in
this case.
14. In compliance with the order dated 29.1.2004 passed by the Commission, the petitioner stated that immediately after the notification of NRSE Policy by the Government in July 2001, the Board of Directors of the petitioner company met on 24.8.2001 and approved setting up of 3.1 MW co-generation plant. In this connection, the petitioner has produced a certified copy of an extract from the minutes of the meeting of the Board of Directors of the Company wherein it is clearly stated that surplus power will be sold to the PSEB under the NRSE Policy 2001 which will improve the financial health and resources of the Company. The petitioner has stated that immediately thereafter, the PSEB was also approached for permission to install 3.1 MW co-generation plant and in this application, it was clearly stated that the surplus power from the co-generation project will be sold to PSEB. It is further stated by the petitioner that the PSEB while granting the necessary permission through its letter dated 27.9.2002 interalia advised the petitioner that the rate of sale of power will have to be got approved from the PSERC. The petitioner has further stated that the Government of Punjab has also approved the project and has clearly stated that the petitioner’s case is covered by the NRSE Policy 2001. With regard to the ABT principles, the petitioner emphasized that these do not apply as the NRSE Policy 2001 makes no mention of these.
15.
The Commission
noted that it has already approved certain projects including some micro hydel and biomass projects under the NRSE Policy of the
Government as amended vide its letter dated February 18, 2003 (with slight
changes). For these projects, the
Commission has already allowed rates for purchase of power by the Board
according to the rates contained in the NRSE Policy. Thus, ordinarily, there is no reason for the
Commission to differentiate between the projects approved under NRSE Policy
2001 earlier and those being approved now.
As long as a project is covered under NRSE Policy 2001, it is entitled
for all benefits thereunder. In view of this, the only question before the
Commission is whether a project is covered under NRSE Policy 2001 or not.
16.
The Commission further noted that the
Government has already committed that application of NRSE Policy in its present
form shall remain restricted to only those projects for which the petitions have
been filed with the Commission till November 30, 2003. All projects where petitions will be
filed with the Commission thereafter are
to be covered under the revised NRSE Policy
to be framed by the Government.
The Commission noted that in fact only three petitions involving_about 15 MWs of
capacity are now pending before the
Commission which were all filed before November 30, 2003. Thus extension of NRSE Policy in its present
form is restricted to a very limited number of projects. In view of this, the
Commission accepts the view of the Government conveyed vide its letter dated
17.
The Commission further considered the
question whether the petitioner’s case is covered under NRSE Policy 2001
or not.
The Commission noted that the petitioner has produced an extract from
the minutes of the meeting of the Board of the Company which clearly shows that
it was immediately after the
pronouncement of the NRSE Policy by the Government in July 2001 and well before
the commissioning of the project, that it was envisaged by the promoters that the project was to be
set up for taking advantage of the NRSE Policy 2001. Reference to
the Board for granting permission for installation of 3.1 MW T.G. set
was also made soon thereafter. Further, in the approval of the Board, it was
stated that the Company may move the Commission for getting the rate of sale of
power approved from the Commission.
Thus it is clear that the intent of the petitioner was to sell
electricity to the Board and the Board was also
willing to go by such an arrangement. The Commission also notes that
PEDA has categorically stated that this project is fully covered under NRSE
Policy 2001. The Commission further notes that even the Government in its
reference to the Commission has clearly stated that this project is covered
under the NRSE Policy 2001 of the Government as amended vide its letter of
18. Once the project is covered under the
NRSE Policy, it is entitled to all the incentives as contained in NRSE Policy
2001 of the Government subject to amendment carried out by the Government in
its letter dated
19. The Commission accordingly decides that PPA in this case is approved and the rates allowed are as applicable to the new projects of the NRSE Policy 2001 and in accordance with the direction of the Government as per its letter dated 28th October, 2002 as amended vide their reference dated February 18, 2003 except that the clause pertaining to 5% losses be amended to state that each year only assessed transmission losses be allowed to the PSEB subject to adjustment based on actuals. The PEDA and PSEB may also ensure that during the period PPA is valid, the petitioner will produce power using only non conventional energy source for which the Project has been approved. Also, in order to protect the interests of the PSEB and the consumers in general, PEDA and State Government must adopt suitable safeguards to ensure that the developers continue to supply power at the prescribed rates during the entire period of agreement under the NRSE Policy.
( L.S. Deol) ( R.S.Mann)
Member Chairman.
Dated: