PUNJAB STATE ELECTRICITY REGULATORY COMMISSION
SCO.220-221, SECTOR 34-A, CHANDIGARH

Petition No. 11 of 2004

In the matter of:



Petition in the matter of Power Purchase Agreement for proposed Hydro Power Project being set up by M/s. Triveni Engg. & Industries Limited (M/s.Triveni Power Generation Ltd.) at Khanpur (RD-23110), Sudhar (RD-105000), Akhara (RD-157000), Gholian (RD-254000) & Channowal (RD-289000) on Abohar Branch Canal and Dhariwal (RD-42825) Kunjar (RD-79768) and Aliwal (RD-123653) on UBDC System in Punjab
AND
In the matter of:

M/s. Triveni Engineering and Industries Limited (Projects and Engineering Business Group) 8th Floor, Express Trade Towers, 15-16, Sector 16-A, NOIDA.
Versus
Punjab State Electricity Board and others.
Present:


Shri Jai Singh Gill, Chairman
Smt. Baljit Bains, Member
Shri Satpal Singh Pall, Member


ORDER:

This petition was filed by M/s. Triveni Engineering and Industries Limited (TEIL) for directing the Board to execute the PPA in pursuance of the order dated 8th April 2003, passed by the Commission in Petitions No.6 to 13 of 2002. Notice of motion was issued by the Commission on July 15, 2004. The petition was adjourned sine die by the Commission in its order of 2nd August 2004 as PEDA requested for time to approach PSEB and the State Government for the purpose. Thereafter PSEB filed Petition No.10 of 2006 for approval of PPA to be entered into between TEIL and the Board. With the filing of Petition No.10 of 2006 this petition (Petition No.11 of 2004) has clearly become infructuous and is dismissed as such.

Sd/- Sd/- Sd/-
(Satpal Singh Pall) (Baljit Bains) (Jai Singh Gill)
Member Member Chairman


Chandigarh
Dated: June 1, 2007